Registration lapsed No litigation declared Residential / Group Housing project

GHD CASA GRANDE

By Gulshan Homez And Developers

RG-MH-82920 · RERA P52900049552 · Last updated on MahaRERA portal: 22 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
173 of 264Construction stages doneacross 24 buildings; furthest along: External plumbing and external plaster, 80%
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

GHD CASA GRANDE is a Residential / Group Housing project by Gulshan Homez And Developers in Sindhudurg, Maharashtra, registered with MahaRERA as P52900049552 on 15 Feb 2023. Possession was promised by 31 Jul 2024 and is now 27 months past that date.

At a glance

Project

  • NameGHD CASA GRANDE
  • TypeResidential / Group Housing
  • Location
    • GHD AANGAN
    • IYE-SANQLI ROAD
    • Vazare
    • Dodamarg
    • Sindhudurg
    • 416512
  • Pincode416512
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52900049552
  • ReraGenie IDRG-MH-82920

Builder

  • NameGulshan Homez And Developers
  • Entity typeCompany
  • Managing DirectorBharat Thakran
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

27 months past promisethis monthRegisteredFeb 2023PromisedJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Feb 2023
  • Promised completion31 Jul 2024
  • Revised completionNone
  • Buildings24 building records
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Villa No101NA20000
Villa No102NA20000
Villa No103NA20000
Villa No104NA20000
Villa No105NA20000
Villa No106NA20000
Villa No107NA20000
Villa No108NA20000
Villa No109NA20000
Villa No110NA20000
Villa No 111NA20000
Villa No 112NA20000
Villa No 113NA20000
Villa No 114NA20000
Villa No 115NA20000
Villa No 116NA20000
Villa No 117NA20000
Villa No 118NA20000
Villa No 119NA20000
Villa No 120NA20000
Villa No 121NA20000
Villa No 122NA20000
Villa No 123NA20000
Villa No 124NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 22 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 24 buildings; the table lists the first 20.

173 of 264 construction stages are filed complete across 24 buildings. The stage furthest along is External plumbing and external plaster, at 80%.

Villa No10182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No10982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No1100%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No 11186%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Villa No 11286%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Villa No 11386%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Villa No 1140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No 11586%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Villa No 11675%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No 11770%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No 11870%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa No 11986%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Villa No 12086%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 22 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Open Space38
BuildingOpen SpaceTotal
Villa No10111
Villa No10211
Villa No10311
Villa No10411
Villa No10511
Villa No10611
Villa No10711
Villa No10811
Villa No10911
Villa No11011
Villa No 11122
Villa No 11222
Villa No 11322
Villa No 11422
Villa No 11522
Villa No 11622
Villa No 11722
Villa No 11822
Villa No 11922
Villa No 12022
Villa No 12122
Villa No 12222
Villa No 12322
Villa No 12422

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
BHARAT SURESH KUMAR THAKRAN-North Goa

Approvals and building plan

Permissible FSI6079.63
Proposed, not sanctioned6,080 sq m
Buildings approved24
Buildings sanctioned24

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPORVORIM, GOA

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUPESH NARAYAN tAWTE
EngineerRajesh Mahambrey
Chartered AccountantAmar Madkaikar
Chartered AccountantSURESH KUMAR SAINI
Chartered AccountantSVN Gaunekar
PartnerRole in project
Gulshan Homez And Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: Consent- Form B.pdf22 Feb 2025
Other - LegalFile: extension to the project with customer's approval.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Architect CERTIFICATES-Q4 FY 23-24.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate -Mar 2024 (Q4 of FY 2023-24).pdf10 Dec 2024
Other - LegalFile: Affidavit to rera - declaration for extention.pdf10 Dec 2024
Other - LegalFile: Casa Grande self declaration for extention.pdf10 Dec 2024
Declaration in FORM BFile: Form 2- Affidavit cum declaration - Casa Grande.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MONTH OF MARCH 2024_compressed.pdf27 Nov 2024
Other - LegalFile: Casa Grande self declaration for extention.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold: Booked Inventory.pdf27 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rera Form 2A-2023-24 .pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - 2023-24.pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 22-23.pdf4 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4 FY 22-23-compressed.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 FY 23-24.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 FY23-24-compressed.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 FY 23-24_compressed.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Mar 2023 (Q4 of FY 2022-23).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - June 2023 (Q1 of FY 2023-24).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Sep 2023 (Q2 of FY 2023-24).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2- Dec 2023 (Q3 of FY 2023-24)).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 2023 (Q4 of FY 2022-23).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 2023 (Q1 of FY 2023-24).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep 2023 (Q2 of FY 2023-24).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2023 (Q3 of FY 2023-24)).pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MONTH OF DECEMBER 2023_compressed.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 -Q4 22-23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Q1- 23-24.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2- 23-24.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 23-24.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 22-23.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 05 April 2023-compressed.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 05 July 2023-compressed.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 05 Oct 2023-compressed.pdf4 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CERTIFICATE--1-compressed.pdf4 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA CERTIFICATE--3-compressed.pdf4 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA CERTIFICATE--2-compressed.pdf4 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA CERTIFICATE--1-compressed.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MONTH OF MARCH-compressed.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MONTH OF JUNE-compressed.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MONTH OF SEPTEMBER-compressed.pdf4 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf4 Jan 2024
Other - FinanceFile: Declaration for deposit amount.pdf1 Feb 2023
Details of encumbrancesFile: Encumbrance letter casa grande.pdf4 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: discloser of interest.pdf4 Jan 2023
Proforma of Allotment letterFile: AL casa grande.pdf1 Dec 2022
Proforma of Agreement for saleFile: Agreement to sale final casa grande.pdf1 Dec 2022
Deviation Report with respect to Allotment letterFile: Devi AL.pdf1 Dec 2022
Copy of the legal title reportFile: Title report.pdf29 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Encumbrance.pdf29 Sep 2022
Details of encumbrances concerned to LegalFile: Encumbrance certificate.pdf6 Jul 2022
CERSAI detailsFile: Encumbrance letter casa grande.pdf6 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - CASA GRANDE 1_11zon-4.pdf6 Jul 2022
Deviation Report with respect to model copy of AgreementFile: Devi AFS.pdf6 Jul 2022
Details of encumbrancesFile: declaration about commencement certificate .pdf26 Jun 2022
Declaration about Commencement CertificateFile: declaration about commencement certificate .pdf26 Jun 2022
Layout approvalFile: plan 1-2.pdf24 Jun 2022
Building plan approvalFile: Approval Plan 1.pdf24 Jun 2022
Building plan approvalFile: Approval Plan 2.pdf24 Jun 2022
PAN CardFile: Pan card.pdf24 Jun 2022
Copy of Layout Approval (in case of layout)File: plan 1-2.pdf24 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Approval Plan 1.pdf24 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Approval Plan 2.pdf24 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMERNCEMENT ORDER.pdf24 Jun 2022
Declaration in FORM BFile: FORM B-casa grande.pdf24 Jun 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
GHD AANGANVILLAGE VAZRE DODAMARG MAHARASHTRA195CompletedAug 2021Late, Aug 2022

How this compares with Sindhudurg

21%of Sindhudurg projects moved their completion datethis one has not
30%of Sindhudurg registrations have lapsed or been cancelledthis one is among them

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep GHD CASA GRANDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near IYE-SANQLI ROAD530+ in Sindhudurg

Builder: Gulshan Homez And Developers

GULSHAN HOMEZ AND DEVELOPERS has 2 registrations on MahaRERA, including AANGAN and GHD CASA GRANDE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What does it mean that GHD CASA GRANDE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GHD CASA GRANDE is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GHD CASA GRANDE?

The registered promoter entity is Gulshan Homez And Developers, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GHD CASA GRANDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GHD CASA GRANDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GHD CASA GRANDE?

The professionals named in the filing: Architect: RUPESH NARAYAN tAWTE; Engineer: Rajesh Mahambrey; Chartered Accountant: Amar Madkaikar; Chartered Accountant: SURESH KUMAR SAINI; Chartered Accountant: SVN Gaunekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GHD CASA GRANDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GHD CASA GRANDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GHD CASA GRANDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.