Home / Browse projects / Sindhudurg, Maharashtra / AXIS BLUES
AXIS BLUES
By EEJAK HOLDINGS PRIVATE LIMITED
RG-MH-02805 · RERA P52900019883 · Last updated on MahaRERA portal: 16 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 9 complaints at MahaRERA
- Completion date moved by 43 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AXIS BLUES is a Commercial project by EEJAK HOLDINGS PRIVATE LIMITED in Sindhudurg, Maharashtra, registered with MahaRERA as P52900019883 on 7 Mar 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 43 months from the original filing. 69 of the 128 units on this registration are recorded sold or booked, and 15 of 33 construction stages are filed complete. 9 complaints are on record with the regulator.
At a glance
Project
- NameAXIS BLUES
- TypeCommercial
- Location
- Yog City Main Road
- Yog City
- Maneri
- Dodamarg
- Sindhudurg
- 416512
- Pincode416512
- RERA no.P52900019883
- ReraGenie IDRG-MH-02805
Builder
- NameEEJAK HOLDINGS PRIVATE LIMITED
- Entity typeCompany
- DirectorsAshish Kushwaha, Padmaja Kushwaha, Devesh Kumar
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Mar 2019
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 May 2024)
- Buildings3 building records
- Documents filed87 files
Current status
Figures as on 16 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING G | NA | 4 | 4 | 44 | 0 | 44 |
| BUILDING D | NA | 4 | 4 | 44 | 0 | 44 |
| BUILDING A | NA | 5 | 4 | 33 | 7 | 40 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 16 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 85%.
BUILDING G63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 62% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
BUILDING D66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 67% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
BUILDING A67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 67% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 16 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING D | NA | Rs 6.61 cr | Rs 4.74 cr |
| BUILDING A | NA | Rs 6.61 cr | Rs 4.74 cr |
| BUILDING G | NA | Rs 6.61 cr | Rs 4.74 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Space design Group PROPRIETOR CHANDER MOHAN |
| Engineer | Space design Group |
| Engineer | SACHIN BALAKRISHNA TENDULKAR |
| Chartered Accountant | Satya Prakash Kushwaha |
| Chartered Accountant | Ashok Jayesh and Associates |
| Partner | Role in project |
|---|---|
| EEJAK HOLDINGS PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCOVID 19 started shortly after we launched our project and because of in Konkan Region, last two years were very heavy rain fall, hence seeking extension u/s 6,
Reason as filed by the promoterThe delay in the project is primarily due to the COVID-l9 pandemic, which affected development activities for two continuous years after its commencement in 2019. Additionally, the rising prices of steel and overall costs funher impacted progress. Since Sindhudurg is a coastal region, it experiences continuous rainfall for nearly six months each year, further slowing down construction activities. These factors collectively contributed to the project's prolonged timeline, making it challenging to maintain the expected pace. Despite these setbacks, efforts are being made to overcome these obstac
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502011 | Perugu Anusha | EEJAK HOLDINGS PRIVATE LIMITED | 19/06/2025 |
| CC12503498 | Rishikesh Deodas Gajbhiye | EEJAK HOLDINGS PRIVATE LIMITED | 30/09/2025 |
| CC12601199 | Asadkhan Alisherkhan Pathan | EEJAK HOLDINGS PRIVATE LIMITED | 05/03/2026 |
| CC12602687 | Sunil Lowanshi | EEJAK HOLDINGS PRIVATE LIMITED | 08/05/2026 |
| CC12602983 | Zakir Hussain | EEJAK HOLDINGS PRIVATE LIMITED | 20/05/2026 |
| CC12603106 | Ranganath Joseph Kallubhavi | EEJAK HOLDINGS PRIVATE LIMITED | 25/05/2026 |
| CC12603562 | Priyanka Ulavakayala | EEJAK HOLDINGS PRIVATE LIMITED | 09/06/2026 |
| CC12603829 | Mansoor Changankattil | EEJAK HOLDINGS PRIVATE LIMITED | 20/06/2026 |
| CC12604344 | Smitha Madhusudan Shetty | EEJAK HOLDINGS PRIVATE LIMITED | 11/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form1 ADG Q3 FY 25-26.pdf | 16 May 2026 |
| Withdrawal Update Form 1File: Form 1 ADG 19883 FY 25-26 Q1.pdf | 16 May 2026 |
| Withdrawal Update Form 1File: Form1 ADG Q4 FY 25-26.pdf | 16 May 2026 |
| Withdrawal Update Form 2File: Form 2 ADG 19883 Q3 25-26.pdf | 16 May 2026 |
| Withdrawal Update Form 2File: Form 2 ADG 19883 FY 25-26 Q1.pdf | 16 May 2026 |
| Withdrawal Update Form 2File: Form 2 ADG 19883 Q4 25-26.pdf | 16 May 2026 |
| Withdrawal Update Form 3File: form 3 19883 q4.pdf | 16 May 2026 |
| Withdrawal Update Form 3File: Form 3 ADG 19883 FY 25-26 Q1.pdf | 16 May 2026 |
| Withdrawal Update Form 3File: Form 3 ADG 19883 Q4 FY 25-26.pdf | 16 May 2026 |
| Form 3File: Form 3 19883 ADG Q2.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: ADG Disclosure of Sold or booked inventory-Axis Blues All Towers Q2 FY 25-26.pdf | 7 Mar 2026 |
| Form 2File: From 2 FY 25-26 Q2 19883.pdf | 7 Mar 2026 |
| Form 1File: FORM 1 ADG Q2 FY 25-26.pdf | 7 Mar 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ADG FY 24-25 Q2.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ADG FY 24-25 Q1.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ADG FY 24-25 Q3.pdf | 4 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3 P52900019883 FY 24-25 Q3.pdf | 31 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 P52900019883 FY 24-25 Q1.pdf | 31 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 P52900019883 FY 24-25 Q2.pdf | 31 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 P52900019883 FY 24-25 Q3.pdf | 31 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or booked inventory ADG up to .pdf | 31 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Eejak FY 24-25 ADG Q1.pdf | 13 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 Eejak FY 24-25 ADG Q2.pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2a 19883.pdf | 20 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Tower AGD Discloser of Sold unsold inventory.pdf | 19 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 19883.pdf | 12 Jun 2024 |
| Declaration in FORM BFile: Affidavit P52900019883.pdf | 10 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 19883 1st qtr.pdf | 7 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 19883 2nd qtr.pdf | 7 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 19883 3rd qtr.pdf | 7 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 19883 4th qtr.pdf | 7 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 19883 q1.pdf | 7 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 19883 q2.pdf | 7 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 19883 q3.pdf | 7 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 19883 q4.pdf | 7 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 19883.pdf | 7 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ADG.pdf | 23 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate ADG.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: P52900019883 1 QTR.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: P52900019883 2 QTR.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: P52900019883 4 QTR.pdf | 14 May 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance related to Legal - ADG.pdf | 7 May 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance related to Legal - ADG.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A,D ,G QTR-1.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Qtr 2.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Qtr 3.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Qtr 4.pdf | 7 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory .pdf | 7 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of interest in other real estate organizations.pdf | 7 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Separate Bank Account Declaration ADG.pdf | 7 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EC 2022 ADG.pdf | 19 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: EC 2023 ADG.pdf | 19 Feb 2024 |
| Certificates of CA (Form 3)File: Rera Cetificate-ADG.pdf | 19 Feb 2024 |
| Certificates of CA (Form 3)File: Eejak FORM 3 ADG-min.pdf | 18 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Eejak -form-5 ADG.pdf | 18 Oct 2023 |
| Certificates of CA (Form 3)File: eejak adg form 3.pdf | 23 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form-5ADG.pdf | 23 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archtiect Certificate ADG.pdf | 18 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3 ADG.pdf | 18 Jul 2022 |
| Certificates of CA (Form 3)File: ADG.pdf | 4 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATEADG2.pdf | 24 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Tower A,D,G.pdf | 3 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: TOWER -A D G_compressed.pdf | 3 Aug 2021 |
| Certificates of CA (Form 3)File: RERA CERTIFICATE_ADG.pdf | 27 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 eejak ADG.pdf | 27 Jul 2021 |
| Declaration about Commencement CertificateFile: EEJAK_ADG.pdf | 10 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE ADG.pdf | 6 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE - A, D, G.pdf | 4 Dec 2020 |
| Certificates of CA (Form 3)File: TOWER-ADG.pdf | 4 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 A D G.pdf | 23 Nov 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: A D G.pdf | 19 Aug 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A D G.pdf | 4 Aug 2020 |
| Certificates of CA (Form 3)File: form 3 A D G.pdf | 4 Aug 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 2A Signed.pdf | 25 Feb 2020 |
| Proforma of Allotment letterFile: ATS - - Blank Format Phase 1.pdf | 24 Sep 2019 |
| PAN CardFile: PAN_EEJAK.pdf | 1 Mar 2019 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT_UPLOAD.pdf | 1 Mar 2019 |
| Declaration in FORM BFile: AFFIDAVIT_FORM B.pdf | 1 Mar 2019 |
| Certificates of CA (Form 3)File: FORM 3_CA CERTIFICATE.pdf | 1 Mar 2019 |
| Proforma of Allotment letterFile: ALLOTMENT LETTETR AND SALE AGREEMENT.pdf | 1 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AXIS BLUES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Yog City530+ in Sindhudurg
AXIS BLUES
EEJAK HOLDINGS PRIVATE LIMITED
AXIS BLUES
EEJAK HOLDINGS PRIVATE LIMITED
AXIS LAKE CITY
GIRIRAJJI INFRASTRUCTURE PRIVATE LIMITED
YOG ANAND
Abome Real Estate Private Limited
YOG CITY PH 1
Jayprakash Ramawadh Maurya
SATERI TOWERS
PRASAD RAGHUNATH PANGAM
See every Sindhudurg project, with the district possession charts
Builder: EEJAK HOLDINGS PRIVATE LIMITED
EEJAK HOLDINGS PRIVATE LIMITED has 3 registrations on MahaRERA, including AXIS BLUES and AXIS BLUES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What are my rights if AXIS BLUES is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AXIS BLUES?
The registered promoter entity is EEJAK HOLDINGS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AXIS BLUES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AXIS BLUES?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AXIS BLUES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AXIS BLUES?
The professionals named in the filing: Architect: Space design Group PROPRIETOR CHANDER MOHAN; Engineer: Space design Group; Engineer: SACHIN BALAKRISHNA TENDULKAR; Chartered Accountant: Satya Prakash Kushwaha; Chartered Accountant: Ashok Jayesh and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AXIS BLUES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.