Home / Browse projects / Pune, Maharashtra / GANGA LEGEND BUILDING A1

Registration lapsed Litigation declared Residential / Group Housing project

GANGA LEGEND BUILDING A1

By Legends County Landmark Pvt Ltd

RG-MH-97934 · RERA P52100034957 · Last updated on MahaRERA portal: 22 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 18 cases
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 6 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
1 of 11Construction stages donefurthest along: Slabs of Super Structure, 99%
0 of 80Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

GANGA LEGEND BUILDING A1 is a Residential / Group Housing project by Legends County Landmark Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100034957 on 28 Apr 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 80 of the 80 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameGANGA LEGEND BUILDING A1
  • TypeResidential / Group Housing
  • Location
    • DSK RANWARA ROAD RAMNAGAR
    • BAVDHAN
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034957
  • ReraGenie IDRG-MH-97934

Builder

  • NameLegends County Landmark Pvt Ltd
  • Entity typeCompany
  • CINU45403PN2018PTC174806
  • GSTIN27AAHCG1862A1ZX
  • DirectorsJAIPRAKASH SITARAM GOEL, Amit Jaiprakash Goel
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

4 months past promisethis monthRegisteredApr 2022First promiseDec 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Apr 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed92 files

Current status

100%80 of 80 units booked
73.7%Work done, per cost certificate

Figures as on 22 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1 BUILDINGNA292380080

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 99%.

A1 BUILDING: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)75%
Plinth90%
Stilt Floor69%
Slabs of Super Structure99%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.17%

Progress on shared amenities15

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes98%
Landscaping & Tree PlantingYes98%
Street LightingYes60%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes98%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,702 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Oct 2025

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI12000.0
Proposed, not sanctioned6,096 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2401 GENERAL THIMAIYYA ROAD, PUNE
Estimated costRs 39.56 cr
Cost incurredRs 29.15 cr
Work done73.69%
BuildingWingEstimatedIncurred
A1 BUILDINGNARs 38.16 crRs 27.89 cr
-NARs 1.40 crRs 1.26 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR PRAKASH KULKARNI
EngineerSUDHIR AGRAWAL
EngineerGaurav Shah
Chartered AccountantDHARINI NASWA
Chartered AccountantSSAP & Associates LLP
Chartered AccountantSachin Chordiya & Co
Chartered AccountantSAYALI DIGHE & ASSOCIATES
Chartered AccountantSachin Gogave & Co. LLP
Chartered AccountantRSAR & ASSOCIATES
PartnerRole in project
Legends County Landmark Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29102518191Dec 2025 → Jun 2026

Reason as filed by the promoterWe are expecting the further FSI in the project and in anticipation of further planning and approval requirements, we foresee the necessity of extending the project timeline. We remain fully committed to completing the project efficiently and effectively. We believe that granting an extension at this stage will enable us to adhere to all legal requirements, maintain construction quality, and ultimately meet stakeholder expectations without compromise. Therefore, we respectfully request a time extension to accommodate the pending approvals and ensure the successful execution of the project.

Litigation declared18

CaseCourtStatus
482/2023CJSD PUNEPENDING
21/2017ADDNL COMMISSIONER PUNEPENDING
1338/2007CJSD PUNEPENDING
880/2012CJSD PUNEPENDING
1192/2012CJSD PUNEPENDING
1025/2012CJSD PUNEPENDING
50/2023CJSDPENDING
1594/2023CJSD PUNEPENDING
903/2020HIGH COURT MUMBAIPENDING
3282/2019BOMBAY HIGH COURTPENDING
4163/2019BOMBAY HIGH COURTPENDING
470/2019CJSD PUNEPENDING
1300/2012CJSD PUNEPENDING
1119/2020HIGH COURT MUMBAIPENDING
4614/2023HIGH COURT MUMBAIPENDING
39/2015NGTDISPOSED OFF
116/2018NGTDISPOSED OFF
1338/2007CJSDOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4.pdf22 May 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf22 May 2026
Withdrawal Update Form 3File: Form 3 Q4.pdf22 May 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf22 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate-Legend A1 - Dec 2025.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate-Legend A1 - Dec 2025.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate A1 Dec 2025.pdf28 Jan 2026
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3..pdf29 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 2024-25 Signed (3).pdf29 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 A1.pdf28 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1 A1.pdf25 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1.pdf25 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23_SINGED.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24_SINGED.pdf29 May 2025
Form 1File: 1 Form 1 - Architect's Certificate-Legend A1 - 31st March 2025.pdf5 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A A1 March 2025.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE A1.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate-Legend A1 - 31st March 2025.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: A1 FORM 3 March-2025.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - 31st March 2025.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Form - 2A - Engineer's Certificate (Quality Assurance)- Legend A1 March 2024 organized.p7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A1 Tower.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate-Legend A1 - Dec 2024.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - Dec 2024.pdf30 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A A1.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Discloser of sold inventory A1.pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate-Legend A1 - Sept 2024.pdf29 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A1 Sept 2024.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - Sept 2024.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate-Legend A1 - June 2024.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3A1-signed.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold data A1 March 2024.pdf29 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ganga legend A1_compressed.pdf14 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - March 2024.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate-Legend A1 - March 2024.pdf31 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - March 2024.pdf31 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Form - 2A - Engineer's Certificate (Quality Assurance)- Legend A1 March 2024.pdf29 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 GANGA LEGEND PHASE A1 AS ON 31122023_compressed.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Architect's Certificate-Legend A1 December 2023.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate-Legend A1 - December 2023.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 A1 RERA FORM 3 - Sept 2023_.pdf30 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Architect's Certificate-Legend A1 Sept 2023 signed.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Engineer's Certificate-Legend A1 Sept 2023 signed.pdf26 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 CA CERTIFICATE- LEGEND A1 JUNE 2023.pdf28 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for RERA Legend A1 June 23.pdf17 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate for RERA Legend A1 June 23.pdf17 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GANGA LEGEND PHASE A1 FORM 3 - 310323.pdf1 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Legend A1.pdf14 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Legend A1.pdf14 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate A1.pdf11 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate A1.pdf11 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Bldg A1.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Bldg A1.pdf18 Oct 2022
Building plan approvalFile: Sheet No 4.pdf20 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 4.pdf20 Apr 2022
Proforma of Allotment letterFile: Allotment Letter - Ganga Legend - Bldg No A1 - dt 20 04 2022.pdf20 Apr 2022

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
GANGA LEGEND A2 AND B4P52100021020BAVDHAN, Pune272May 2019CompletedDec 2023Dec 2023
GANGA GLITZSurvey No 16 P AND Survey No 17 P Village Undri Taluka Haveli District Pune 411 060192-CompletedApr 2018Apr 2017
GANGA ARCADIASR NO 22 Hissa No 2 Village Kharadi Taluka Haveli District Pune 41101428-CompletedJun 2017Jun 2017
GANGA ARCADIASurvey No. 22 Hissa No 2 situated at Village Kharadi Taluka Haveli District Pune 411 014120-CompletedDec 2015Oct 2015
GANGA SPARSHSurvey No 16Pand 17 P Village Undri Taluka Haveli District Pune154-CompletedApr 2014Nov 2013
AMRUTGANGAVADGAON BK PUNE611-CompletedDec 2013Oct 2013

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGA LEGEND BUILDING A1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BAVDHAN13,700+ in Pune

2 kmGANGA LEGEND BUILDING A1Completed 25Lapsed / revoked 14Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 80 registered projects within 2 km.

Builder: Legends County Landmark Pvt Ltd

Legends County Landmark Pvt Ltd has 3 registrations on MahaRERA, including GANGA LEGEND BUILDING A1 and GANGA LEGEND B5 BUILDING. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that GANGA LEGEND BUILDING A1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GANGA LEGEND BUILDING A1 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGA LEGEND BUILDING A1?

The registered promoter entity is Legends County Landmark Pvt Ltd, a company as per the filing. Its CIN U45403PN2018PTC174806 and GSTIN 27AAHCG1862A1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGA LEGEND BUILDING A1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANGA LEGEND BUILDING A1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGA LEGEND BUILDING A1?

The professionals named in the filing: Architect: AR PRAKASH KULKARNI; Engineer: SUDHIR AGRAWAL; Engineer: Gaurav Shah; Chartered Accountant: DHARINI NASWA; Chartered Accountant: SSAP & Associates LLP; Chartered Accountant: Sachin Chordiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGA LEGEND BUILDING A1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGA LEGEND BUILDING A1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGA LEGEND BUILDING A1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.