Registered Litigation declared Commercial project

Ganga Capitol One

By SHREE BALAJI ASSOCIATES PUNE LLP

RG-MH-31759 · RERA P52100080094 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • Rs 80.00 crore secured on the land, in favour of IndusInd Bank
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 completed earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 40%
42 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Ganga Capitol One is a Commercial project by SHREE BALAJI ASSOCIATES PUNE LLP in Pune, Maharashtra, registered with MahaRERA as P52100080094 on 24 Apr 2025. Possession is promised by 31 Dec 2029. 0 of the 42 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameGanga Capitol One
  • TypeCommercial
  • Location
    • Mundhwa
    • Pune
    • Keshavnagar-Mundwa
    • Pune City
    • 411036
  • Pincode411036
  • RERA no.P52100080094
  • ReraGenie IDRG-MH-31759

Builder

  • NameSHREE BALAJI ASSOCIATES PUNE LLP
  • Entity typePartnership
  • GSTIN27ABDFS3963Q1ZE
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersGANGA HOUSING PVT LTD NA, ANURAG SUBHASH GOEL
  • Other registrations9 more →
  • Completed2 of 10
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredApr 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Apr 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Current status

0%0 of 42 units booked
0.4%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ganga Capitol OneNA161604242

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 40%.

Ganga Capitol One: 4% average across the applicable activities

ActivityProgress
Excavation40%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed189

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots189
Closed/Covered189

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofIndusInd Bank
Secured amountRs 80.00 crore
CERSAI search filedYes
Declared on11 Nov 2025

Approvals and building plan

Sanctioning authorityPUNE MUNCIPAL CORPORATION
Permissible FSI24560.6
Proposed, not sanctioned10,904 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2401,GEN.THIMMAYYA RD. (CANTONMENT), PUNE - 411 001.
Estimated costRs 49.32 cr
Cost incurredRs 20.51 lakh
Work done0.42%
BuildingWingEstimatedIncurred
Ganga Capitol OneNARs 44.32 crRs 20.51 lakh
-NARs 5.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCreative Designs Mr Sanjay Kumar Giri
EngineerMr. Chandrashekhar D Tendulkar
EngineerYOGESH VIRVADEKAR
Chartered AccountantMs CAP & CO
Chartered AccountantCA MAHESH CHANDORKAR
PartnerRole in project
SHREE BALAJI ASSOCIATES PUNE LLP-

Litigation declared4

CaseCourtStatus
NO/0000NOClosed
00/0000NOClosed
00/0000NOClosed
00/0000NOClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 GANGA CAPITOL ONE JUN 26.pdf4 Jul 2026
Withdrawal Update Form 2File: FORM 2 GANGA CAPITOL ONE JUN 26.pdf4 Jul 2026
Withdrawal Update Form 3File: FORM 3 GANGA CAPITOL ONE JUN 26.pdf4 Jul 2026
Withdrawal Update Form 1File: FORM 1 GANGA CAPITOL ONE MAR 26.pdf6 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA CAPITOL ONE MAR 26.pdf6 Apr 2026
Withdrawal Update Form 3File: FORM 3 GANGA CAPITOL ONE MAR 26.pdf6 Apr 2026
Withdrawal Update Form 1File: FORM 1 GANGA CAPITOL ONE DEC 25.pdf7 Jan 2026
Withdrawal Update Form 2File: FORM 2 GANGA CAPITOL ONE DEC 25.pdf7 Jan 2026
Withdrawal Update Form 3File: FORM 3 GANGA CAPITOL ONE DEC 25.pdf7 Jan 2026
Withdrawal Update Form 1File: FORM 1 GANGA CAPITOL ONE SEP 25.pdf10 Oct 2025
Withdrawal Update Form 2File: FORM 2 GANGA CAPITOL ONE SEP 25.pdf10 Oct 2025
Withdrawal Update Form 3File: FORM 3 GANGA CAPITOL ONE SEP 25.pdf10 Oct 2025
Withdrawal Update Form 1File: 0390_20250724111325_001_organized.pdf24 Jul 2025
Withdrawal Update Form 2File: FORM 2 GANGA CAPITOL ONE JUN 25.pdf24 Jul 2025
Withdrawal Update Form 3File: FORM 3 GANGA CAPITOL ONE JUN 25.pdf24 Jul 2025
Commencement Certificates / NA Order for plotted developmentFile: Ganga Capitol One CC Verification Email.pdf22 Apr 2025
Other - FinanceFile: Declaration Ganga Capitol One Final Secured Loan.pdf22 Apr 2025
Layout approvalFile: 1-5.pdf5 Apr 2025
Copy of Layout Approval (in case of layout)File: 1-5.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ganga Capitol One Final.pdf5 Apr 2025
Deviation Report with respect to Allotment letterFile: Deviation Report-Allottment.pdf5 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report-AFS.pdf5 Apr 2025
Copy of the legal title reportFile: Legal title report ganga caitol one 4 4 2025.pdf4 Apr 2025
Proforma of Allotment letterFile: Allotment Letter - Ganga Capitol One.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Arch Cert-Ganga Capitol One-1.pdf4 Apr 2025
CERSAI detailsFile: CERSAI_Search_Report_200348731953_For_Asset_Based_Search_04_04_2025_17_50_13_339 (2).pdf4 Apr 2025
Other - TechnicalFile: CC Declaration Anurag Goel.pdf4 Apr 2025
Proforma of Agreement for saleFile: Ganga capitol AFS 4 4 2025.pdf4 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Intrest in other Organization - GHPL.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Er Cert-Ganga Capitol One.pdf3 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured and Declaration.pdf1 Apr 2025
Details of encumbrances concerned to FinanceFile: Declaration of Legal Encumbarances Ganga Capitol One.pdf31 Mar 2025
Details of encumbrances concerned to FinanceFile: Financial Encumbrances Ganga Capitol One.pdf31 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf31 Mar 2025
Details of encumbrances concerned to LegalFile: Financial Encumbrances Ganga Capitol One.pdf31 Mar 2025
Details of encumbrances concerned to LegalFile: Declaration of Legal Encumbarances Ganga Capitol One.pdf31 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B FROM BANK SCAN.PDF31 Mar 2025
Other - LegalFile: 2.pdf29 Mar 2025
Other - LegalFile: 1.pdf29 Mar 2025
Other - LegalFile: 6.pdf29 Mar 2025
Other - LegalFile: 4.pdf29 Mar 2025
Other - LegalFile: 3.pdf29 Mar 2025
Other - LegalFile: 2.pdf29 Mar 2025
Other - LegalFile: 1.pdf29 Mar 2025
Other - LegalFile: 5.pdf29 Mar 2025
Building plan approvalFile: 1-5.pdf28 Mar 2025
Building plan approvalFile: 2-5.pdf28 Mar 2025
Building plan approvalFile: 3-5.pdf28 Mar 2025
Building plan approvalFile: 4-5.pdf28 Mar 2025
Building plan approvalFile: 5-5.pdf28 Mar 2025
PAN CardFile: SBAPLLP PAN COPY.PDF28 Mar 2025
Declaration in FORM BFile: Form B _ Affidavit Cum Declaration Ganga Capitol One.pdf28 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Ganga Capitol One CC.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 1-5.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2-5.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 3-5.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 4-5.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 5-5.pdf28 Mar 2025
Declaration about Commencement CertificateFile: Declaration about CC.pdf28 Mar 2025
Other - TechnicalFile: Annexure A Ganga Capitol.pdf28 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other Organization Aurag Goel.pdf28 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other organization Subhash Goel.pdf28 Mar 2025

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
GANGA NEWTOWN PH 5 E BLDGP52100079278DHANORI, Pune147Feb 2025Certificate SignedJun 2028May 2026
GANGA NEWTOWN PH 4 D BldgP52100055461DHANORI, Pune231Mar 2024Certificate SignedDec 2027Registered original: Jun 2027Not due yet
GANGA NEWTOWN PH 3 C BldgP52100034400DHANORI, Pune-Apr 2022Certificate SignedJun 2026May 2026
Ganga Newtown Ph 02P52100019275PORWAL ROAD-Jan 2019CompletedDec 2025May 2025

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ganga Capitol One on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

Builder: SHREE BALAJI ASSOCIATES PUNE LLP

SHREE BALAJI ASSOCIATES PUNE LLP has 10 registrations on MahaRERA, including GANGA NEWTOWN PHASE I and Ganga Newtown Ph 02. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ganga Capitol One is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ganga Capitol One?

The registered promoter entity is SHREE BALAJI ASSOCIATES PUNE LLP, a partnership as per the filing. Its GSTIN 27ABDFS3963Q1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ganga Capitol One?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ganga Capitol One?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ganga Capitol One?

The professionals named in the filing: Architect: Creative Designs Mr Sanjay Kumar Giri; Engineer: Mr. Chandrashekhar D Tendulkar; Engineer: YOGESH VIRVADEKAR; Chartered Accountant: Ms CAP & CO; Chartered Accountant: CA MAHESH CHANDORKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ganga Capitol One?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ganga Capitol One. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ganga Capitol One to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.