Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
9 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 85%
155 of 318Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

ELINA LUXE TOWER G and H is a Others project by Ramkrishna Cine Exhibitors in Pune, Maharashtra, registered with MahaRERA as P52100052556 on 11 Sep 2023. Possession is promised by 30 Jun 2027. 163 of the 318 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameELINA LUXE TOWER G and H
  • TypeOthers
  • Location
    • S M Ghule Road
    • Kondhwa
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052556
  • ReraGenie IDRG-MH-82789

Builder

  • NameRamkrishna Cine Exhibitors
  • Entity typePartnership
  • PartnerPushkraj Arvind Chaphalkar
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2023PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed86 files

Current status

51%163 of 318 units booked

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER GNA232312631157
TOWER HNA232312734161

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 85%.

TOWER G50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER H49%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)85%
Plinth100%
Stilt Floor100%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed968

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots968
Closed/Covered2
Open Space966
BuildingClosed/CoveredOpen SpaceTotal
TOWER G1482483
TOWER H1484485

Land and ownership11

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,969 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
LandownerVillageDistrict
VIKRAM VILAS KARANDIKARPune (M Corp.)Pune
Pushkaraj Arvind ChaphalkarPune (M Corp.)Pune
Arvind Damodar ChaphalkarPune (M Corp.)Pune
Dnayandas Damodar ChaphalkarPune (M Corp.)Pune
Vinayak Pandurang ChaphalkarPune (M Corp.)Pune
Rishikesh Arvind ChaphalkarPune (M Corp.)Pune
Gaurav Dnayandas ChaphalkarPune (M Corp.)Pune
Shrinivas Dnyandas ChaphalkarPune (M Corp.)Pune
Tejas Vilas KarandikarPune (M Corp.)Pune
Mohammed Zafeer Iqbal Ahmed MehterPune (M Corp.)Pune
Hafizul Rehman Moinuddin Ahmed MehterPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI26800.0
Proposed, not sanctioned26,800 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN GYMKHANA PUNE

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAJAKTA JADHAV
EngineerMs G A Bhilare
Chartered AccountantKhire Khandekar and Kirloskar Chartered Accountants
Chartered AccountantJPNR & Associates
Chartered Accountant193944
Chartered AccountantPritheish Achaliya
PartnerRole in project
Ramkrishna Cine Exhibitors-

Litigation declared1

CaseCourtStatus
1299/2022/2022CIvil Court Senior Division PuneAwaiting Summons

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Elina Luxe Form 1.pdf22 Jun 2026
Form 2File: Form 2 (Elina Luxe) 20-04-2026001.pdf22 Jun 2026
Form 3File: FORM 3 FEB 2026.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DISLSOER.pdf22 Jun 2026
Form 1File: Form 1- Architect certificate.pdf10 Feb 2026
Form 2File: Form 2- Engineer Certificate.pdf10 Feb 2026
Form 3File: form 3- CA certificate.pdf10 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure sold and unsold inventory.pdf10 Feb 2026
Form 1File: Form 1- Elina Luxe001.pdf6 Nov 2025
Form 2File: Form 2- Elina Luxe.pdf6 Nov 2025
Form 3File: Form 3- Elina Luxe001_compressed.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold and unsold inventory.pdf6 Nov 2025
Form 5 (FY 2024-2025)File: Form 5- Elina Luxe001.pdf17 Oct 2025
Form 1File: Form 1 Architect Q1 Elina Luxe.pdf4 Aug 2025
Form 2File: Elina Luxe Form 2_ 30062025.pdf4 Aug 2025
Form 3File: Elina Luxe Form 3_ 30062025.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory G H TowerQ1 25-26Elina Luxe.pdf4 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Elina Luxe Q3.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Elina Luxe Q3.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Elina Luxe Q3.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Luxe Q3.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RCE - ELINA LUXE RERA FORM 5 (2023-2024).pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ELINA LUXE Q2.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ELINA LUXE Q2.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ELINA LUXE Q2.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: RCE Elina Luxe Disclosure of Inventory Q2 24-25.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 24-25.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 24-25.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Q1 24-25.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2023-24.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 23-24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Q4 23-24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Quarter 3 Elina Luxe.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory G H Tower 2023-24 Q3.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2023-24.PDF1 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience ARVIND Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience DNYANDAS Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience VINAYAK Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience GAURAV Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience RISHIKESH Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience PUSHKARAJ Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience SHRINIVAS Chaphalkar.PDF11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience TEJAS Karandikar.PDF11 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE DTD 08 Aug 23.pdf8 Aug 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf4 Aug 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate by Developer.pdf23 Jun 2023
Other - TechnicalFile: Layout.pdf23 Jun 2023
Other - TechnicalFile: Self Declaration Elina Luxe RERA.pdf23 Jun 2023
Details of encumbrances concerned to FinanceFile: Details Non Encumbrances.pdf6 Jun 2023
Details of encumbrances concerned to LegalFile: Details Non Encumbrances.pdf6 Jun 2023
CERSAI detailsFile: CERSAI_Search_Report_TJSB.pdf6 Jun 2023
CERSAI detailsFile: CERSAI UNDERTAKING BY PROMOTER.pdf6 Jun 2023
Proforma of Agreement for saleFile: ATS Luxe 17 May.pdf17 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Previous RERA Experience .pdf16 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report declaration ATS.pdf16 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Bank Acct by Developer Order No 34.pdf19 Apr 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrances Tower G H.pdf5 Apr 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances Tower G H.pdf5 Apr 2023
Layout approvalFile: Layout.pdf4 Apr 2023
Building plan approvalFile: G H.pdf4 Apr 2023
Building plan approvalFile: G H 2.pdf4 Apr 2023
Building plan approvalFile: G H 3.pdf4 Apr 2023
Building plan approvalFile: G H 4.pdf4 Apr 2023
Building plan approvalFile: G H 5.pdf4 Apr 2023
Building plan approvalFile: G H 6.pdf4 Apr 2023
Building plan approvalFile: G H 7.pdf4 Apr 2023
Building plan approvalFile: G H 8.pdf4 Apr 2023
Building plan approvalFile: G H 9.pdf4 Apr 2023
Building plan approvalFile: G H 10 .pdf4 Apr 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 2.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 3.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 4.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 5.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 6.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 7.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 8.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 9.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: G H 10 .pdf4 Apr 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
ELINA LIVA Tower I and JP52100049751Mohmmadwadi, Pune181Feb 2023OngoingJun 2027Not due yet

How this compares with Pune

51%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELINA LUXE TOWER G and H on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kondhwa13,700+ in Pune

2 kmELINA LUXE TOWER G and HCompleted 66Lapsed / revoked 24Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 158 registered projects within 2 km.

Builder: Ramkrishna Cine Exhibitors

Ramkrishna Cine Exhibitors has 4 registrations on MahaRERA, including ELINA LIVING and ELINA LIVING PHASE III. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ELINA LUXE TOWER G and H is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELINA LUXE TOWER G and H?

The registered promoter entity is Ramkrishna Cine Exhibitors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELINA LUXE TOWER G and H?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELINA LUXE TOWER G and H?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELINA LUXE TOWER G and H?

The professionals named in the filing: Architect: PRAJAKTA JADHAV; Engineer: Ms G A Bhilare; Chartered Accountant: Khire Khandekar and Kirloskar Chartered Accountants; Chartered Accountant: JPNR & Associates; Chartered Accountant: 193944; Chartered Accountant: Pritheish Achaliya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELINA LUXE TOWER G and H?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELINA LUXE TOWER G and H. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELINA LUXE TOWER G and H to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.