Home / Browse projects / Pune, Maharashtra / ELINA LIVA Tower I and J

Registered No litigation declared Others project

ELINA LIVA Tower I and J

By Ramkrishna Cine Exhibitors

RG-MH-62210 · RERA P52100049751 · Last updated on MahaRERA portal: 6 Nov 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
3 of 181Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

ELINA LIVA Tower I and J is a Others project by Ramkrishna Cine Exhibitors in Pune, Maharashtra, registered with MahaRERA as P52100049751 on 24 Feb 2023. Possession is promised by 30 Jun 2027. 178 of the 181 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameELINA LIVA Tower I and J
  • TypeOthers
  • Location
    • Elina Living Road
    • Mohmmadwadi
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100049751
  • ReraGenie IDRG-MH-62210

Builder

  • NameRamkrishna Cine Exhibitors
  • Entity typePartnership
  • PartnerPushkraj Arvind Chaphalkar
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2023PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Feb 2023
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed77 files

Current status

98%178 of 181 units booked

Figures as on 6 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower INA242286793
Tower JNA242288088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

Tower I77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower J78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed142

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots142
Closed/Covered2
Open Space140
BuildingClosed/CoveredOpen SpaceTotal
Tower I17071
Tower J17071

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,019 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Vikram Vilas KarandikarPune (M Corp.)Pune
Pushkaraj Arvind ChaphalkarPune (M Corp.)Pune
Arvind Damodar ChaphalkarPune (M Corp.)Pune
Dnyandas Damodar ChaphalkarPune (M Corp.)Pune
Vinayak Pandurang ChaphalkarPune (M Corp.)Pune
Rishikesh Arvind ChaphalkarPune (M Corp.)Pune
Gaurav Dnyandas ChaphalkarPune (M Corp.)Pune
Shrinivas Dnyandas ChaphalkarPune (M Corp.)Pune
Tejas Vilas KarandikarPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI17747.42
Proposed, not sanctioned17,747 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDeccan Gymkhana

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Prajakta Jadhav
EngineerAbhishek Kale
Chartered AccountantPrithesh Achaliya
Chartered AccountantJPNR & Associates
Chartered AccountantKhire Khandekar and Kirloskar
PartnerRole in project
Ramkrishna Cine Exhibitors-

Litigation declared2

CaseCourtStatus
1299/2022/2022District Court PuneAwaiting Summons
577/2021/2021AdditionalCollector PuneAppellant to file his say against adverse judgement

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1- Elina Liva001.pdf6 Nov 2025
Form 2File: Form 2- Elina Liva.pdf6 Nov 2025
Form 3File: Form 3- Elina Liva001.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory.pdf6 Nov 2025
Form 5 (FY 2024-2025)File: Form 5- Elina Liva001.pdf17 Oct 2025
Form 3File: Form 3 Elina Liva Q1_compressed.pdf4 Aug 2025
Form 2File: Elina Liva Form 2_ 30062025.pdf4 Aug 2025
Form 1File: Elina Liva.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: Elina Liva.pdf4 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Elina Liva Q3.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Elina Liva Q3.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Elina Liva Q3.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Book Inventory Liva Q3 24-25.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RCE - ELINA LIVA RERA FORM 5 (2023-2024).pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ELINA LIVA Q2.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ELINA LIVA Q2.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ELINA LIVA Q2.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: RCE Elina Liva Disclosure of Inventory Q2 24-25.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2024-25.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 24-25.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 24-25.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2023-24.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 23-24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Q4 2023-24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_300623 Qarter3 2023-24.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory I J Tower 2023-24 Q3.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2023-24.PDF1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Elina Liva Form 5 Tower I and J.pdf22 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RCE - FORM 5.pdf19 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower I J.pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory I J Tower 2023-24 Q1.pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory I J Tower 2023-24 Q2.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 22-23.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 23-24.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 23-24.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_310323 Qarter 4 2022-23.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_300623 Qarter 1 2023-24.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA 300923 Qarter 2 2023-24.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q 1 2023-24.pdf9 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q 2 2023-24.pdf9 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf9 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Liva.pdf5 Sep 2023
Other - LegalFile: Self Declaration litigation - Elina Liva.pdf28 Jul 2023
Other - LegalFile: Add collector order-Appeal no 5772021 tarwade and others.pdf28 Jul 2023
CERSAI detailsFile: CERSAI UNDERTAKING BY PROMOTER.pdf16 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_200260435639_For_Asset_Based_Search_15_02_2023_17_32_28_069.pdf16 Feb 2023
Details of encumbrances concerned to FinanceFile: Financial Self Declaration Encumbrances I J.pdf7 Feb 2023
Details of encumbrances concerned to LegalFile: Financial Self Declaration Encumbrances I J.pdf7 Feb 2023
Copy of the legal title reportFile: Title Report.pdf31 Jan 2023
Layout approvalFile: Architect Undertaking Layout of Tower I J.pdf25 Jan 2023
Copy of Layout Approval (in case of layout)File: Architect Undertaking Layout of Tower I J.pdf25 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3 I J Revised.pdf22 Jan 2023
Layout approvalFile: Layout.pdf16 Jan 2023
Building plan approvalFile: I J 2.pdf16 Jan 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf16 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: I J 2.pdf16 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Disclosure by Partner.pdf3 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report declaration ATS.pdf3 Jan 2023
Building plan approvalFile: I J .pdf26 Dec 2022
Building plan approvalFile: I J 3.pdf26 Dec 2022
Building plan approvalFile: I J 4.pdf26 Dec 2022
PAN CardFile: PAN Card.pdf26 Dec 2022
Details of encumbrances concerned to FinanceFile: Legal Encumbrances Tower I J.pdf26 Dec 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrances Tower I J.pdf26 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: I J .pdf26 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: I J 3.pdf26 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: I J 4.pdf26 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: C C 30 May 22.pdf26 Dec 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.PDF26 Dec 2022
Declaration in FORM BFile: FORM 'B' AFFIDAVIT CUM DECLARATION.pdf26 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf26 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Certificate of Engineer.pdf26 Dec 2022
Proforma of Agreement for saleFile: ATS for I J Towers.pdf26 Dec 2022
Proforma of Allotment letterFile: Almt Letter.pdf26 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Bank Account Developer.pdf26 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation report declaration Allotment letter.pdf26 Dec 2022

How this compares with Pune

98%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELINA LIVA Tower I and J on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mohmmadwadi13,700+ in Pune

2 kmELINA LIVA Tower I and JCompleted 63Lapsed / revoked 24Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 154 registered projects within 2 km.

Builder: Ramkrishna Cine Exhibitors

Ramkrishna Cine Exhibitors has 4 registrations on MahaRERA, including ELINA LIVING and ELINA LIVING PHASE III. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ELINA LIVA Tower I and J is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELINA LIVA Tower I and J?

The registered promoter entity is Ramkrishna Cine Exhibitors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELINA LIVA Tower I and J?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELINA LIVA Tower I and J?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELINA LIVA Tower I and J?

The professionals named in the filing: Architect: Ar Prajakta Jadhav; Engineer: Abhishek Kale; Chartered Accountant: Prithesh Achaliya; Chartered Accountant: JPNR & Associates; Chartered Accountant: Khire Khandekar and Kirloskar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELINA LIVA Tower I and J?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELINA LIVA Tower I and J. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELINA LIVA Tower I and J to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.