Home / Browse projects / Mumbai City, Maharashtra / DILKAP CENTRE
DILKAP CENTRE
By GORKAP PROPERTIES & INVESTMENTS PVT. LTD
RG-MH-08506 · RERA P51900011709 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 44 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DILKAP CENTRE is a Commercial project by GORKAP PROPERTIES & INVESTMENTS PVT. LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900011709 on 31 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 44 months from the original filing. 68 of the 94 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameDILKAP CENTRE
- TypeCommercial
- Location
- Andheri Kurla Road
- Mumbai City
- 400070
- Pincode400070
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900011709
- ReraGenie IDRG-MH-08506
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Oct 2023)
- Buildings1 building record
- Documents filed97 files
Current status
Figures as on 3 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DILKAP CENTRE | NA | 10 | 7 | 0 | 94 | 94 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 96%.
DILKAP CENTRE: 71% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 95% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 82% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 45% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 54.38 cr | Rs 52.20 cr |
| DILKAP CENTRE | NA | Rs 30.25 cr | Rs 22.37 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PUSHKAR CONSULTANT |
| Engineer | Aquib Zakir Ansari Ansari |
| Chartered Accountant | MULANI AND ASSOCIATES |
| Chartered Accountant | Shah Binal & Associates |
| Partner | Role in project |
|---|---|
| GORKAP PROPERTIES & INVESTMENTS PVT. LTD | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCFO FINAL PLAN HAS BEEN SANCTIONED. DELAY IN DUE DILIGENCE FROM BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO SCRUTINY DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC HAS BEEN PROLONGING TO CLEAR & FINALISE.
Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900011709.As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 30.06.2027. The order is uploaded in Other Tab for your reference
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000210435 | Wilma Dsouza | Gorkap Properties & Investment Pvt. Ltd. | 17/03/2022 |
| CC006000000374843 | RONI ABRAHAM | Gorkap Properties and Investments Private Limited through its Directors. | 20/03/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed97
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Dilkap Centre as on Sep 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Dilkap Centre as on Dec 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Dilkap Centre as on Mar 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Centre as on Sep 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Centre as on Dec 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Centre as on Mar 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Centre as on Sep 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Centre as on Dec 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Centre as on Mar 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: Dilkap Centre Architect Certificate Q1 June 2025.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: Dilkap Centre Engg Cert Sept Qtr.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: Gorkap Q1 CA CERTFICATION FORM FY 2526.pdf | 11 Sep 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Dilkap Centre Form 5 31 03 23.pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Makskap Centre Form 5 AY 22 23.pdf | 19 Jan 2024 |
| Declaration in FORM BFile: Dilkap Centre Affidavit Rera Application.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dilkap Centre Architecture Cert of Rera 30 09 23 compressed.pdf | 18 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dilkap Centre Engg Cert Sept Qtr.pdf | 18 Jan 2024 |
| CERSAI detailsFile: DILKAP CENTRE CERSAI 18 01 2024.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Dilkap Centre Sold Unsold Dec 23.pdf | 18 Jan 2024 |
| Certificates of CA (Form 3)File: Dilkap Centre CA certificate June 23 Qtr.pdf | 18 Jan 2024 |
| Certificates of CA (Form 3)File: Dilkap Centre CA Cert 30 09 2023.pdf | 18 Jan 2024 |
| Certificates of CA (Form 5)File: Dilkap Centre Form 5 31 03 23.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate.pdf | 15 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 15 Sep 2023 |
| Certificates of CA (Form 3)File: CA Certificate Dilkap Centre.pdf | 15 Sep 2023 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 20 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QC of CENTRE 23.pdf | 20 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form no 5 of Centre Mar23.pdf | 20 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert of Centre Mar23.pdf | 6 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cet of Centre.pdf | 3 Jun 2023 |
| Certificates of CA (Form 3)File: CA Cert of Centre Mar23.pdf | 3 Jun 2023 |
| Certificates of CA (Form 5)File: Form no 5 of Centre Mar23.pdf | 3 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf | 22 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2022.pdf | 24 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: RERA Sold Unsold 311222.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf | 2 Feb 2023 |
| Proforma of Agreement for saleFile: Dilkap Centre.pdf | 29 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert 300621 of Centre.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert 300921 of Centre.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert 311221 centre.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert 310322 of Centre.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sakinaka Architect certificate June 2022.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sakinaka Architect certificate Sep 2022.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sakinaka Architect certificate Dec 2022.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Centre 310321.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Centre 300621.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Centre 300921.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Centre 311221.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Centre 310322.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert 310622 of Centre.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert 310922 of Centre.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert 311222 of Centre.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Centre 310321_compressed.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cart Centre 300621_compressed.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Centre 300921_compressed.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Centre 311221_compressed.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Centre 310322_compressed.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert 310622 of Centre.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert 310922 of Centre.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert 311222 of Centre.pdf | 25 Jan 2023 |
| PAN CardFile: PAN of Gorkap.pdf | 19 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: eNCUMBRANCES.pdf | 19 Jan 2023 |
| Details of encumbrances concerned to LegalFile: eNCUMBRANCES.pdf | 19 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance 310320 Centre.pdf | 19 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance 310321 Centre.pdf | 19 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance 310322 Centre.pdf | 19 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Dilkap Centre-Form 5.pdf | 25 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dilkap Centre - Engineering Certificate.pdf | 14 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dilkap Centre-Architect Certificate.pdf | 30 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dilkap Centre - Engineer Certificate.pdf | 29 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dilkap Centre.pdf | 31 Oct 2019 |
| Certificates of CA (Form 5)File: Dilkap Centre - RERA Form 5.pdf | 1 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dilkap Centre - Architect Certificate.pdf | 26 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dilkap Centre - Engineer Certificate.pdf | 26 Aug 2019 |
| Certificates of CA (Form 5)File: Form No 5.pdf | 2 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC OF CENTRE.pdf | 24 Mar 2018 |
| Building plan approvalFile: IOD of Centre- Arjun.pdf | 30 Jul 2017 |
| Layout approvalFile: 1.pdf | 30 Jul 2017 |
| Layout approvalFile: 2.pdf | 30 Jul 2017 |
| Layout approvalFile: 3.pdf | 30 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Dilkap Chambers | Dilkap Chambers, Veera Desai Road, Off. Andheri Link Road, Andher West | Completed | Jan 2008 | Jan 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 97 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DILKAP CENTRE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mumbai City780+ in Mumbai City
Filed coordinates, straight-line distance. 94 registered projects within 2 km.
Sayba Badr
Star Shine
Yojan One
MERU REALTY LLP
SAYBA ELYSIA
SAYBA HOME MAKERS
Sayba Olympia
Star Shine
Kohinoor City Residential Phase 2 Block 2
Kohinoor Developers
DSK MADHUKOSH
D S Kulkarni Developers Limited
See every Mumbai City project, with the district possession charts
Builder: GORKAP PROPERTIES & INVESTMENTS PVT. LTD
GORKAP PROPERTIES & INVESTMENTS PVT. LTD has 2 registrations on MahaRERA, including DILKAP VICTOR and DILKAP CENTRE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if DILKAP CENTRE is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DILKAP CENTRE?
The registered promoter entity is GORKAP PROPERTIES & INVESTMENTS PVT. LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DILKAP CENTRE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DILKAP CENTRE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DILKAP CENTRE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DILKAP CENTRE?
The professionals named in the filing: Architect: PUSHKAR CONSULTANT; Engineer: Aquib Zakir Ansari Ansari; Chartered Accountant: MULANI AND ASSOCIATES; Chartered Accountant: Shah Binal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DILKAP CENTRE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback