Kohinoor City Residential Phase 2 Block 2
RG-MH-24720 · RERA P51800003258 · Last updated on MahaRERA portal: 14 Feb 2026
Source: official MahaRERA filing
Red flags
- 59 complaints at MahaRERA
- Completion date moved by 72 months
- 6 extensions taken
- Rs 75.00 crore secured on the land, in favour of Omkara Assets Reconstruction Pvt. Ltd.
- The charge is held by Omkara Assets Reconstruction Pvt. Ltd., a distressed-debt buyer or stressed-asset fund rather than an originating lender
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kohinoor City Residential Phase 2 Block 2 is a Residential / Group Housing project by Kohinoor Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003258 on 5 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 72 months from the original filing. 209 of the 209 units on this registration are recorded sold or booked, and 58 of 66 construction stages are filed complete. 59 complaints are on record with the regulator.
At a glance
Project
- NameKohinoor City Residential Phase 2 Block 2
- TypeResidential / Group Housing
- Location
- Kirol Road
- Kurla
- Mumbai Suburban
- 400070
- Pincode400070
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003258
- ReraGenie IDRG-MH-24720
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
- Buildings6 building records
- Documents filed181 files
Current status
Figures as on 14 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 12A | NA | 14 | 10 | 30 | 0 | 30 |
| 12B | NA | 14 | 10 | 36 | 0 | 36 |
| 13 | NA | 14 | 10 | 36 | 0 | 36 |
| 14 | NA | 14 | 10 | 36 | 0 | 36 |
| 20A | NA | 14 | 10 | 39 | 7 | 46 |
| 20B | NA | 14 | 10 | 20 | 5 | 25 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 14 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
58 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 99%.
12A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
12B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
20A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
20B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed338
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| 12A | 47 | 12 | 59 |
| 12B | 59 | 0 | 59 |
| 13 | 60 | 1 | 61 |
| 14 | 58 | 0 | 58 |
| 20A | 63 | 0 | 63 |
| 20B | 38 | 0 | 38 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 20A | NA | Rs 22.03 cr | Rs 22.03 cr |
| 14 | NA | Rs 20.74 cr | Rs 20.74 cr |
| 12A | NA | Rs 20.63 cr | Rs 20.63 cr |
| 13 | NA | Rs 20.53 cr | Rs 20.53 cr |
| 12B | NA | Rs 20.13 cr | Rs 20.13 cr |
| 20B | NA | Rs 11.95 cr | Rs 11.95 cr |
| - | NA | Rs 10.01 cr | Rs 10.01 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sandeep Shikre & Associates |
| Architect | Sandeep Shikre |
| Engineer | S.W. Mone & Associates |
| Engineer | Santosh Shingare |
| Chartered Accountant | Abhijit Deshpande |
| Chartered Accountant | Tejal Mahajan |
| Partner | Role in project |
|---|---|
| Kohinoor Developers | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDuring construction of the said 8 buildings we encountered a Hard Rock and the permission for blasting the rock was denied by the Authorities for the safety of adjacent structures. Similarly, there was Hume Pipe obstruction due to which the entire design of the basement and the parking layout were required to be changed and approved from the MCGM as an amendment to the original sanctioned plan, leading to the delay. Due to the basement work being carried out by the adjoining property Developer during the heavy monsoon, there was landslide and the DP Road was disconnected for the entire monsoon
Reason as filed by the promoter(a) During construction of said 4 buildings we encountered Hard Rock and permission for blasting the rock was denied by Authorities for safety of adjacent structures. There was Hume Pipe obstruction which also obstructed construction of said buildings. The entire design of basement and parking layout was changed and revised plan got approved from BMC as an amendment to original sanctioned plan (b) The Govt. of Maharashtra had issued Modification dated 30/04/2015 under DCR 34 regarding use of TDR/DRC. The Modification to DCR 34 was sanctioned by Govt. vide its G.R. dated 16/11/2016 i.e. after 1
Reason as filed by the promoteri. Due to the Pandemic of Covid-19, a nation-wide lockdown and restrictions for break the chain of Covid-19 were imposed by the Government of Maharashtra, we could not resume construction work immediately in full capacity after getting relaxation from the Government due to non-availability of labour and material. ii. As a result of the pandemic induced lockdown, work on site had to be stopped, workers released, and progress came to a complete standstill. Work could not resume in full capacity immediately due to non-availability of labour and material even after the lockdown was relaxed around
Reason as filed by the promoter1) the Covid-19 pandemic struck the nation and became a global pandemic, there was a nation-wide lockdown and restrictions for break the chain of Covid-19 were imposed by the Government of Maharashtra, due to which the construction activities were at a stand-still. 2) Due to pandemic induced lockdown, work on site had to be stopped, workers released and progress came to a complete standstill. Work could not resume in full capacity immediately due to non-availability of labour and material even after the lockdown was relaxed around July, 2021. 3) Even after work recommenced, its progress was sl
Reason as filed by the promoterIn this context please note that we have complete constructions of all buildings / Flats of the Project and obtained Part Occupation Certificate dated 26th September,2024 in respect of all flats / units in the said project except Flat Nos. 101 and 102 in building No. 20B. The competent authority has not issued Occupation Certificate in respect of these flats No. 101 and 102 due to handing over of project R.G. We are in the process of handing over of R.G. to the competent authority and therefore, request you to grant us Project extension till 30th July, 2025.
Reason as filed by the promoterPending compliances for obtaining Full Occupation Certificate in respect of the project.
Complaints filed with MahaRERA59
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196939 | Mohamed Sahid Anwar Momin | Umesh Manohar Joshi | 09/05/2021 |
| CC006000000044509 | RAVI RAJAGOPAL | KOHINOOR DEVELOPERS | 16/05/2018 |
| CC006000000000189 | Paresh Rajgarhia | KOHINOOR DEVELOPERS | 04/09/2017 |
| CC006000000001647 | SHAFI SHAIKH | KOHINOOR DEVELOPERS | 14/11/2017 |
| CC006000000195367 | Mr. Rajneesh Kumar Gupta and Mrs Priya Gupta | Umesh Manohar Joshi | 25/12/2020 |
| CC006000000044153 | DR. RAKESH MOHAN BADHE | MR. UNMESH MANOHAR JOSHI, PROP: M/S. KOHINOOR DEVELOPERS | 18/04/2018 |
| CC006000000055213 | Vijay Kumar Gupta and Gauri Gupta | Unmesh Joshi, Sole Proprietor of Kohinoor Developers | 09/07/2018 |
| CC006000000055542 | DR SHREE PHANSE | UNMESH MANOHAR JOSHI | 27/07/2018 |
| CC006000000055561 | MS. CHRISTINE QUADRAS | MR UNMESH MANOHAR JOSHI, PROP KOHINOOR DEVELOPERS | 30/07/2018 |
| CC006000000056250 | Mr. Altaf Mohamad Yusuf Khatri | M/s.Kohinoor Developers through its Sole ProprietorMr. Unmesh M. Joshi | 26/09/2018 |
| CC006000000056216 | MRS. VINAYA AJIT DALVI | UNMESH MANOHAR JOSHI, PROP KOHINOOR DEVELOPERS | 15/09/2018 |
| CC006000000056513 | INAYATULLAH SHAIKH | KOHINOOR DEVELOPERS | 15/10/2018 |
| CC006000000056502 | DR RAJRATAN N SADAWARTE | MR UNMESH MANOHAR JOSHI, PROP. KOHINOOR DEVELOPERS | 09/10/2018 |
| CC006000000056580 | Sudesh Kumari | Kohinoor Developers | 15/10/2018 |
| CC006000000056819 | Turab Fidvi | Kohinoor Developers | 03/11/2018 |
| CC006000000056856 | Abhishek Singh | Mr. Unmesh Manohar Joshi | 03/12/2018 |
| CC006000000057336 | 1) MR. JUDE SERPES 2) MR. RUSSEL SERPES 3) MRS. SHARLETTE SERPES | Kohinoor City Residential Phase 2 Block 1 | 16/05/2019 |
| CC006000000192898 | Suryakant Bhonde | Shivtara Properties Pvt. Ltd. | 07/01/2021 |
| CC006000000057827 | MR SYLVESTER BOSCO HENRIQUES | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 25/01/2019 |
| CC006000000057964 | Mohan Raghunath Phatak | Unmesh Manohar Joshi, Sole Proprietor of M/s Kohinoor Developers | 09/02/2019 |
| CC006000000078984 | MRS. SHALON LUCIANA GOMES and Mr. LEIGHTON JOSEPH FRANCIS GOMES | Mr. UNMESH MANOHAR JOSHI Prop. M/s. KOHINOOR DEVELOPERS | 22/04/2019 |
| CC006000000079033 | LEON SUNIL D'SOUZA | Mr. UNMESH MANOHAR JOSHI, PROP. KOHINOOR DEVELOPERS | 30/04/2019 |
| CC006000000089781 | MRS. MEERA MARIAM BASIL | MR. UNMESH MANOHAR JOSHI, PROP. KOHINOOR DEVELOPERS | 25/06/2019 |
| CC006000000100248 | DEEPAK K MANDLIK | UNMESH MANOHAR JOSHI | 24/07/2019 |
| CC006000000141009 | Mrs Priyanka Vij and Mrs Vandana Vij | Kohinoor Developers | 23/09/2019 |
| CC006000000141014 | mr Lokesh Vij and Mrs Vandana Vij | Kohinoor Developers | 23/09/2019 |
| CC006000000141122 | FAROOQ, MEHRUNISSA, AARIF MERCHANT AND M/S FARAZ TRADING CO. (P) LTD | KOHINOOR DEVELOPERS THROUGH UNMESH MANOHAR JOSHI | 02/10/2019 |
| CC006000000192236 | MR. ARIF M. MERCHANT | KOHINOOR DEVELOPERS THROUGH ITS AUTHORISED SIGNATORY UNMESH MANOHAR JOSHI | 21/01/2020 |
| CC006000000192258 | M/S FARAZ TRADING CO. (P) LTD. THORUGH ITS DIRECTORS MR. FAROOQ MERCHANT AND MR. ARIF MERCHANT | KOHINOOR DEVELOPERS THROUGH ITS AUTHORIZED SIGNATORY MR. UNMESH MANOHAR JOSHI | 21/01/2020 |
| CC006000000171555 | Mehtab Ahmed Ali Malik and Aftab Ahmed Ali Malik | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 15/11/2019 |
| CC006000000171556 | Mr. Israil Ahmed Ali Malik And Mr. Altaf Ahmed Ali Malik | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 15/11/2019 |
| CC006000000197678 | Benedict Fernandes | Kohinoor Developers | 21/07/2021 |
| CC006000000197701 | ABDULKALAM ABBAS CHOGLE | KOHINOOR DEVELOPERS | 26/07/2021 |
| CC006000000197722 | MR. SIKANDAR ABDULLAH MODAK AND MR. RUHI ABDULLAH MODAK | Kohinoor Developers | 28/07/2021 |
| CC006000000197744 | MR. SIKANDAR ABDULLAH MODAK AND MRS. RUHI SIKANDAR MODAK | Kohinoor Developers | 28/07/2021 |
| CC006000000197745 | MR. MOHSIN ABBAS CHOUDHARY AND MRS. FATIMA MOHSIN CHOUDHARY | Kohinoor Developers | 28/07/2021 |
| CC006000000197858 | MOHSIN ABBAS CHOUDHARY AND MRS. FATIMA ABBAS CHOUDAHRY | KOHINOOR DEVELOPER | 04/08/2021 |
| CC006000000198270 | Mr. RIZWAN MALIK | Mr. UNMESH MANOHAR JOSHI, Prop. KOHINOOR DEVELOPERS | 07/09/2021 |
| CC006000000220839 | Seetha Ramanathan | M/s Kohinoor Developers | 15/04/2022 |
| CC006000000194109 | Mrs Rakhi Dadoo and Mr Vikas Dadoo | M/s Kohinoor Developers | 21/09/2020 |
| CC006000000231190 | DALIP KUMAR RAJPOOT | KOHINOOR DEVELOPERS | 09/07/2022 |
| CC006000000251542 | Kohinoor Developers | Arif Merchant | 21/06/2022 |
| CC006000000251551 | Kohinoor Developers | Faraz Trading Co. Pvt. Ltd. | 21/06/2022 |
| CC006000000303559 | Kohinoor Developers | Mr. Farooq Merchant | 02/12/2022 |
| CC006000000303297 | Gangaram Janu Pawar | Mr Unmesh Manohar Joshi, Prop. Kohinoor Developers | 22/11/2022 |
| CC006000000397772 | Gangaram Janu Pawar | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 23/10/2023 |
| CC006000000303342 | Kohinoor Developers | Farid Hussain Ibrahim and Ors | 16/11/2022 |
| CC006000000303564 | KARUNA JAIN | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 10/12/2022 |
| CC006000000303636 | Mr Ashwin Chandramohan Rao and Mrs Simli Nag | Unmesh Manohar Joshi Proprietor Kohinoor Developers | 10/12/2022 |
| CC006000000354445 | Srijith Surendranathan Nair | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 01/03/2023 |
| CC006000000396099 | Moinuddin Nizamuddin Don | M/s. Kohinoor Developers through its sole proprietor Mr. Unmesh Manohar Joshi | 06/06/2023 |
| CC006000000397949 | Gangaram Janu Pawar (HUF) | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 23/10/2023 |
| CC006000000397950 | Renuka Gangaram Pawar | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 23/10/2023 |
| CC006000000479908 | NARAYAN JANU PAWAR | Mr. Unmesh Manohar Joshi, Prop. Kohinoor Developers | 12/04/2024 |
| CC12400057 | KARUNA JAIN | Kohinoor Developers | 07/09/2024 |
| CC12400094 | Voderbet Pandurang Kamath | Kohinoor Developers | 13/09/2024 |
| CC12502208 | Kohinoor Developers | Shrijeet Nair | 03/07/2025 |
| CC12601907 | Kohinoor Developers | Srijith Surendranathan Nair | 31/03/2026 |
| CC12602563 | Kohinoor Developers | Voderbet Pandurang Kamat | 02/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Dec 2024
Documents filed181
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 181 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 14 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 14 Feb 2026 |
| Withdrawal Update Form 3File: KD FORM 3_compressed.pdf | 14 Feb 2026 |
| Occupational CertificateFile: OC-13 AND 14.pdf | 14 Feb 2026 |
| Occupational CertificateFile: 12A12B20A20B.pdf | 14 Feb 2026 |
| Occupational CertificateFile: 2473067_OC_signed.pdf | 14 Feb 2026 |
| Occupational CertificateFile: page1.pdf | 14 Feb 2026 |
| Occupational CertificateFile: 31-12-2025 Drawing_compressed-2-3.pdf | 14 Feb 2026 |
| Occupational CertificateFile: 31-12-2025 Drawing_compressed-4-7.pdf | 14 Feb 2026 |
| Occupational CertificateFile: 31-12-2025 Drawing_compressed-8-10.pdf | 14 Feb 2026 |
| Occupational CertificateFile: page1-26-09-2024.pdf | 14 Feb 2026 |
| Occupational CertificateFile: page2-5.pdf | 14 Feb 2026 |
| Occupational CertificateFile: page 6-10.pdf | 14 Feb 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 10 Oct 2025 |
| Withdrawal Update Form 2File: EC.pdf | 10 Oct 2025 |
| Withdrawal Update Form 3File: CA cert.pdf | 10 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 7 Oct 2025 |
| Withdrawal Update Form 2File: EC.pdf | 7 Oct 2025 |
| Withdrawal Update Form 3File: CA cert.pdf | 7 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 4 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 4 Oct 2025 |
| Withdrawal Update Form 2File: EC.pdf | 4 Oct 2025 |
| Withdrawal Update Form 2File: EC.pdf | 4 Oct 2025 |
| Withdrawal Update Form 3File: CA cert.pdf | 4 Oct 2025 |
| Withdrawal Update Form 3File: CA cert.pdf | 4 Oct 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 30 Sep 2025 |
| Form 1File: Form 1.pdf | 16 Jul 2025 |
| Form 2File: Form 2.pdf | 16 Jul 2025 |
| Form 3File: Form 3.pdf | 16 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory.pdf | 16 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 18 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf | 18 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q-3 Kohinoor Developers.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: Form-3 Q-3 Oceana.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q-3 Kohinoor Developers.pdf | 18 Jan 2025 |
| Declaration in FORM BFile: Form B_Affidavit cum Declaration.pdf | 7 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kohinoor City-PhaseII-OC26092024.pdf | 7 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory.pdf | 7 Dec 2024 |
| OtherFile: OC KD.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Form-03.pdf | 31 Oct 2024 |
| Certificates of CA (Form 3)File: Form-03 revised.pdf | 31 Oct 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_Kohinoor Developers.pdf | 31 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Certificate.pdf | 24 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate.pdf | 24 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5_KD.pdf | 8 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revalidation CC.pdf | 19 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revalidation CC.pdf | 31 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf | 22 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf | 22 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 18 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 18 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf | 24 Jun 2024 |
| Certificates of CA (Form 3)File: Form-3.pdf | 18 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf | 16 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf | 16 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Cert.pdf | 18 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineer Cert.pdf | 18 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3-CA Cert.pdf | 18 Jan 2024 |
| Certificates of CA (Form 3)File: FORM 3- CA CERT.pdf | 19 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - ARCHITECT'S CERT.pdf | 16 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2- ENGINEER'S CERT.pdf | 16 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 27 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf | 7 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3- CA Certificate.pdf | 18 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect's Certificate.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer's Certificate.pdf | 7 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM_2A-ENGINEER CERTIFICATE QA.pdf | 30 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf | 30 Jun 2023 |
| Certificates of CA (Form 3)File: Form-3_2.pdf | 19 Apr 2023 |
| Certificates of CA (Form 3)File: Form-3_2.pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect's Certificate.pdf | 11 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineer's Certificate.pdf | 11 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1-Architect's Certificate.pdf | 18 Jan 2023 |
| Certificates of CA (Form 3)File: Form-3-CA Certificate.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-Engineer's Certificate.pdf | 16 Jan 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kohinoor City Residential Phase 2 Block 1 | Kohinoor City Kirol Road Off LBS Marg Kurla West Mumbai 400070 | 234 | Completed | Dec 2013 | Late, May 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 181 filed documents as one ZIP, foldered, with a manifest
Keep Kohinoor City Residential Phase 2 Block 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 283 registered projects within 2 km.
Sayba Badr
Star Shine
Yojan One
MERU REALTY LLP
SAYBA ELYSIA
SAYBA HOME MAKERS
Sayba Olympia
Star Shine
DSK MADHUKOSH
D S Kulkarni Developers Limited
RUDRA STARLIGHT
RT HOUSING PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: Kohinoor Developers
Kohinoor Developers has 4 registrations on MahaRERA, including Kohinoor City Residential Phase 2 Block 2 and OLIVE BLISS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Kohinoor City Residential Phase 2 Block 2 is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kohinoor City Residential Phase 2 Block 2?
The registered promoter entity is Kohinoor Developers, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kohinoor City Residential Phase 2 Block 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Kohinoor City Residential Phase 2 Block 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Kohinoor City Residential Phase 2 Block 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kohinoor City Residential Phase 2 Block 2?
The professionals named in the filing: Architect: Sandeep Shikre & Associates; Architect: Sandeep Shikre; Engineer: S.W. Mone & Associates; Engineer: Santosh Shingare; Chartered Accountant: Abhijit Deshpande; Chartered Accountant: Tejal Mahajan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kohinoor City Residential Phase 2 Block 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback