Home / Browse projects / AZHAAN RESIDENCY

Completed No litigation declared Residential / Group Housing project

AZHAAN RESIDENCY

By BLUE PEARL DEVELOPERS

RG-MH-12173 · RERA P51900009229 · Last updated on MahaRERA portal: 22 Feb 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2022Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

AZHAAN RESIDENCY is a Residential / Group Housing project by BLUE PEARL DEVELOPERS in 400011, registered with MahaRERA as P51900009229 on 22 Aug 2017. The registration is recorded completed; possession was promised by 30 Mar 2022. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameAZHAAN RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • 400011
  • Pincode400011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900009229
  • ReraGenie IDRG-MH-12173

Builder

  • NameBLUE PEARL DEVELOPERS
  • Entity typePartnership
  • PartnersFARHAN IQBAL PATEL, MEHBOOB AHMED PATEL, FAIZ IQBAL PATEL

Key dates

this monthRegisteredAug 2017First promiseSep 2020Revised toMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Aug 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AZHAAN RESIDENCYNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

AZHAAN RESIDENCY: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 22 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area359 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1705.54
Proposed, not sanctioned1,512 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, APSARA MULTIPLEX, DR B D MARG, GRANT RD EAST MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMAN AND ASSOCIATES
EngineerEPICON CONSULTANTS
PartnerRole in project
BLUE PEARL DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900008461Sep 2020 → Sep 2021

Reason as filed by the promoterWe hereby declare and state that the Promoters have completed their aforesaid Project in all respects i.e. “AZHAAN” (hereinafter shall be referred to as “Said Project”) situated at Plot bearing Survey No 1840 pt of Byculla Division, of “E” Ward, Pin No - 400011. We have received NOC to Oc for the Said Property from Estate Department. We have also applied for the Occupation Certificate before the Building Proposal, City. We are in the continuous process of receiving the Occupation Certificate and are complying with the directions of Building Proposal, City in order to receive the Occupation Cer

Litigation declared1

CaseCourtStatus
1708 OF 2012/2017BOMBAY CITY CIVIL COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jul 2021

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form4_BPD.pdf22 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Haji gulam rasul CHS.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2253701_OC_signed.pdf16 Jul 2021
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf18 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5_Mar2019_BPD.pdf8 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: a_ArchCert_Azhaan_Apr2019.pdf2 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: b_EngCert_Azhaan_Apr2019.pdf2 Nov 2019
Certificates of CA (Form 3)File: c_Form3_Azhaan_RERA.pdf2 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BPD_Form 1_Architect Certificate_Oct 17.pdf12 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BPD_Form 2_Engineer Certificate_Oct 17.pdf12 Dec 2017
Certificates of CA (Form 3)File: BPD_form 3_CA Certificate_Oct 17-ilovepdf-compressed.pdf12 Dec 2017
Details of encumbrancesFile: Non Encumbrance Certificate.pdf28 Jul 2017
Declaration in FORM BFile: Form B.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: Form 3 Chartered Accountants Certificate.pdf28 Jul 2017
Proforma of Allotment letterFile: AFS ALLOTMENT.pdf28 Jul 2017
OtherFile: Letter of Authority.pdf28 Jul 2017
Building plan approvalFile: IOD_26-09-2014.pdf21 Jul 2017
Layout approvalFile: Amended Plan Letter 1.pdf21 Jul 2017
Layout approvalFile: Amended Plan 2.pdf21 Jul 2017
Layout approvalFile: Amended Plan 3.pdf21 Jul 2017
PAN CardFile: BLUE PEARL PAN CARD.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Amended Plan Letter 1.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Amended Plan 2.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Amended Plan 3.pdf21 Jul 2017
Building Plan Approval (IOD)File: IOD_26-09-2014.pdf21 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Jul 2017
Copy of the legal title reportFile: Title Certificate_22-02-2016_Azhaan.pdf20 Jul 2017

Keep AZHAAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmAZHAAN RESIDENCYCompleted 8Lapsed / revoked 16Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: BLUE PEARL DEVELOPERS

BLUE PEARL DEVELOPERS has 1 registration on MahaRERA, including AZHAAN RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if AZHAAN RESIDENCY is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AZHAAN RESIDENCY?

The registered promoter entity is BLUE PEARL DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AZHAAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AZHAAN RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AZHAAN RESIDENCY?

The professionals named in the filing: Architect: AMAN AND ASSOCIATES; Engineer: EPICON CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AZHAAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AZHAAN RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AZHAAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.