ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / AUDUMBAR NEST BUILDING - C

Registration lapsed No litigation declared Residential / Group Housing project

AUDUMBAR NEST BUILDING - C

By AUDUMBAR SHIV PROPERTIES

RG-MH-41603 · RERA P52100049337 · Last updated on MahaRERA portal: 2 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

AUDUMBAR NEST BUILDING - C is a Residential / Group Housing project by AUDUMBAR SHIV PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100049337 on 7 Feb 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameAUDUMBAR NEST BUILDING - C
  • TypeResidential / Group Housing
  • Location
    • S NO 151/1/1
    • 151/2/1
    • MORWADI
    • PIMPRI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411018
  • Pincode411018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100049337
  • ReraGenie IDRG-MH-41603

Builder

  • NameAUDUMBAR SHIV PROPERTIES
  • Entity typePartnership
  • PartnerSHASHIKANT DATTATRAY WAGHERE

Key dates

10 months past promisethis monthRegisteredFeb 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Feb 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed82 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AUDUMBER NEST BUILDING - CNA33000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

AUDUMBER NEST BUILDING - C: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 2 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Open Space4

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,861 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Aug 2025
LandownerVillageDistrict
AUDUMBER SHIV PROPERTIESPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Muncipal Corporation
Permissible FSI1768.96
Proposed, not sanctioned1,327 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJAI GANESH VISION, B- BUILDING, AKURDI, PUNE - 411035

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIL PAWAR
ArchitectANIL VILAS PAWAR
EngineerSACHIN BHAURAO DEVADKAR
Chartered AccountantSAYYED MOHAMMAD AKBAR
Chartered AccountantMOHAMMAD AKBAR SAYYED
PartnerRole in project
AUDUMBAR SHIV PROPERTIES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf2 Jan 2026
Form 2File: FORM 2_compressed.pdf2 Jan 2026
Form 3File: FORM 3.pdf2 Jan 2026
Disclosure of Sold and Booked InventoryFile: AUDUMBER SOLD UNSOLD SEP 2025.pdf2 Jan 2026
Form 1File: Audumber Form 1 Dec 2025.pdf2 Jan 2026
Form 2File: Audumber Form 2 Dec 2025.pdf2 Jan 2026
Form 3File: FORM 3.pdf2 Jan 2026
Disclosure of Sold and Booked InventoryFile: Unsold inventory Q42025.pdf2 Jan 2026
Form 5 (FY 2022-2023)File: FORM 5 FY 2223.pdf2 Jan 2026
Form 5 (FY 2023-2024)File: FORM 5 FY 2324.pdf2 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 FY 2425.pdf2 Jan 2026
Form 1File: FORM 1.pdf25 Sep 2025
Form 2File: Form 2.pdf25 Sep 2025
Form 3File: FORM 3.pdf25 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf25 Sep 2025
Form 1File: Form 1.pdf25 Sep 2025
Form 2File: Form 2.pdf25 Sep 2025
Form 3File: FORM 3.pdf25 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf25 Sep 2025
Form 1File: Form 1.pdf25 Sep 2025
Form 2File: Form 2.pdf25 Sep 2025
Form 3File: FORM 3.pdf25 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of sold.pdf25 Sep 2025
Form 1File: FORM 1.pdf25 Sep 2025
Form 2File: Form 2.pdf25 Sep 2025
Form 3File: FORM 3.pdf25 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf25 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf23 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf23 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf23 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of sold.pdf23 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of sold.pdf23 Sep 2025
Form 1File: Form 1.pdf23 Sep 2025
Form 2File: Form 2.pdf23 Sep 2025
Form 3File: FORM 3.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: List of Sold.pdf23 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf5 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf5 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY CERTIFICATE.pdf5 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NEW FORMAT_compressed (1).pdf31 Jan 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT-2.pdf28 Jan 2023
Copy of the legal title reportFile: search Tital Report.pdf13 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: PROMOTERS DISCLOSURE.pdf9 Jan 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION AGREEMENT FOR SALE.pdf29 Dec 2022
CERSAI detailsFile: CERSAI REPORT.pdf28 Dec 2022
Proforma of Allotment letterFile: Allotment Letter.pdf28 Dec 2022
Deviation Report with respect to Allotment letterFile: NO DEVIATION ALLOTMENT LETTER.pdf28 Dec 2022
Layout approvalFile: Saction Plan Copy-5_compressed.pdf27 Dec 2022
Building plan approvalFile: Saction Plan Copy-6.pdf27 Dec 2022
Building plan approvalFile: Saction Plan Copy-7.pdf27 Dec 2022
Building plan approvalFile: Saction Plan Copy-9.pdf27 Dec 2022
PAN CardFile: Audumbar Shiv Properties PAN Card.pdf27 Dec 2022
Copy of the legal title reportFile: img20230105_15360861.pdf27 Dec 2022
Details of encumbrances concerned to FinanceFile: Encumbrances Certificates.pdf27 Dec 2022
Details of encumbrances concerned to LegalFile: Encumbrances Certificates.pdf27 Dec 2022
Copy of Layout Approval (in case of layout)File: Saction Plan Copy-5_compressed.pdf27 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Saction Plan Copy-6.pdf27 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Saction Plan Copy-7.pdf27 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Saction Plan Copy-9.pdf27 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf27 Dec 2022
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf27 Dec 2022
Declaration in FORM BFile: Form B.pdf27 Dec 2022
CERSAI detailsFile: Encumbrances Certificates.pdf27 Dec 2022
Proforma of Agreement for saleFile: PROFORMA AGREEMENT DRAFT.pdf27 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Detaqils (1).pdf27 Dec 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AUDUMBAR NEST BUILDING - C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MORWADI, PIMPRI13,700+ in Pune

2 kmAUDUMBAR NEST BUILDING -Completed 56Lapsed / revoked 30Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 226 registered projects within 2 km.

Builder: AUDUMBAR SHIV PROPERTIES

AUDUMBAR SHIV PROPERTIES has 1 registration on MahaRERA, including AUDUMBAR NEST BUILDING - C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that AUDUMBAR NEST BUILDING - C shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AUDUMBAR NEST BUILDING - C is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AUDUMBAR NEST BUILDING - C?

The registered promoter entity is AUDUMBAR SHIV PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AUDUMBAR NEST BUILDING - C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AUDUMBAR NEST BUILDING - C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AUDUMBAR NEST BUILDING - C?

The professionals named in the filing: Architect: ANIL PAWAR; Architect: ANIL VILAS PAWAR; Engineer: SACHIN BHAURAO DEVADKAR; Chartered Accountant: SAYYED MOHAMMAD AKBAR; Chartered Accountant: MOHAMMAD AKBAR SAYYED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AUDUMBAR NEST BUILDING - C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AUDUMBAR NEST BUILDING - C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AUDUMBAR NEST BUILDING - C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.