Home / Browse projects / Pune, Maharashtra / Astonia Classic Phase II - A5 Building
Astonia Classic Phase II - A5 Building
By AMIT ENTERPRISES HOUSING LIMITED
RG-MH-10567 · RERA P52100001359 · Last updated on MahaRERA portal: 15 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 72 months
- 5 extensions taken
- Rs 75.00 crore secured on the land, in favour of ICICI Bank Limited
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Astonia Classic Phase II - A5 Building is a Residential / Group Housing project by AMIT ENTERPRISES HOUSING LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100001359 on 27 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 72 months from the original filing. 48 of the 96 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameAstonia Classic Phase II - A5 Building
- TypeResidential / Group Housing
- Location
- Undri Road
- Undri
- Haveli
- Pune
- 411060
- Pincode411060
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100001359
- ReraGenie IDRG-MH-10567
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Jul 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2020)
- Buildings1 building record
- Documents filed150 files
Current status
Figures as on 15 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A5 | NA | 15 | 12 | 96 | 0 | 96 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 94%.
Building A5: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 55% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | No | Not applicable |
Parking filed79
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A5 | NA | Rs 18.77 cr | Rs 14.90 cr |
| - | NA | Rs 5.35 cr | Rs 2.40 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Jagadish Deshpande |
| Architect | Prafulla Ramchandra Nadkarni |
| Architect | Unmesh Vitthal Vaidya |
| Engineer | J + W Consultants LLP |
| Engineer | Abhay Pramod Inamdar |
| Chartered Accountant | Dharini Naswa & Associates |
| Chartered Accountant | SSAP & Associates LLP |
| Partner | Role in project |
|---|---|
| AMIT ENTERPRISES HOUSING LIMITED | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAcute economic crisis in the real estate market.
Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the COVID-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing moneta
Reason as filed by the promoterThe slow market condition and a slump in the real estate market during the period created acute economic crises which ultimately slowed down the sale transactions. However, somehow we were managing and pulling ourselves to complete the project in the scheduled time. The market conditions were getting better but due to the emergence of the Covid 19 outbreak, we faced a massive downfall affecting the project. We are committed to providing our customers with what was promised to them with the utmost standard. Therefore, we request you kindly grant us an extension of registration for 1 year to com
Reason as filed by the promoterAmit Enterprises Housing Ltd and its group entities have faced considerable pressure due to several external factors which have ultimately caused the delay in the construction of the project. COVID-19 Pandemic: The COVID-19 pandemic severely impacted the project's stability, causing significant delays primarily due to labour shortages from migrant workers returning to their native states and disruptions in the supply chain for materials and equipment. These challenges exacerbated construction delays and complicated efforts to get the project back on track. The increased costs of labour and the
Reason as filed by the promoter1. The project stands at 70% completion 2. The consent of 68.75% of allottees has been uploaded in support of this extension application. 3. Revised Form B uploaded 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a. The sector experienced subdued buyer demand and slow absorption, impacting sales, cash flows, and construction timelines. b. Funding constraints and cash flow interruptions caused delays in material procurement and site operations. c. Shortage of skilled labour and delays in the supply of key materials f
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed150
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 150 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Astonia Classic.pdf | 15 Jul 2026 |
| Withdrawal Update Form 2File: Form2-ASTC-A5- Apr 2026 - Jun 2026.pdf | 15 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate - Astonia Classic Phase II - A5 Bldg.pdf | 15 Jul 2026 |
| Withdrawal Update Form 1File: A5 ASTONIA CLASSIC -FORM 1.pdf | 14 Apr 2026 |
| Withdrawal Update Form 2File: Form2-ASTC-A5- Jan 2026 - Mar 2026.pdf | 14 Apr 2026 |
| Withdrawal Update Form 3File: AEHL-ASTONIA CLASSIC A5-FORM 3 -31-03-26.pdf | 14 Apr 2026 |
| Withdrawal Update Form 1File: Astonia Classic A5 Building -form 1.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Astonia Classic A5 - CA Certificate.pdf | 14 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - Astonia Classic A5.pdf | 29 Dec 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form -1 Astonia Classic A5 Building.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form2-ASTC-A5-July 2025-Sep 2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Astonia Classic A5.pdf | 13 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - Astonia Classic A5.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 8 Jul 2025 |
| Withdrawal Update Form 2File: Classic A5 Form 2.pdf | 8 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 - Astonia Classic A 5.pdf | 8 Jul 2025 |
| Form 1File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 26 Jun 2025 |
| Form 2File: Classic A5 Form 2.pdf | 26 Jun 2025 |
| Form 3File: Form 3 - Astonia Classic A 5.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Astonia Classic A5.pdf | 26 Jun 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 14 Jun 2025 |
| Withdrawal Update Form 2File: Classic A5 Form 2.pdf | 14 Jun 2025 |
| Withdrawal Update Form 3File: Form 3 - Astonia Classic A 5.pdf | 14 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Astonia Classic A 5.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 14 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Classic A5 Form 2.pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Astonia Classic A5.pdf | 14 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Classic A5 Form 2A.pdf | 14 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - Astonia Classic A5.pdf | 17 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Astonia Classic A5 - Form 2.pdf | 16 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Astonia Classic A5 - Form 2A.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: Astonia Classic A5.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Astonia Classic A5 Building Dec-24.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Astonia Classic A5.pdf | 10 Jan 2025 |
| Declaration in FORM BFile: Affidavit Cum Declaration Form B_compressed.pdf | 2 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 22 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Astonia Classic.pdf | 22 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AstoniaClassic-A5-Jul24-Sep24.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Astonia classic - A5.pdf | 22 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-AstoniaClassic-A5-Jul24-Sep24.pdf | 22 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Astonia classic.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Astonia Classic A5 Building JUNE 24.pdf | 11 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AstoniaClassic-A5-Apr24-June24.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-AstoniaClassic-A5-Apr24-June24.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory Astonia Clssiac A5.pdf | 11 Jul 2024 |
| Certificates of CA (Form 3)File: CA Certificate Astonia Classic A5 Building.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AstoniaClassic-A5-Jan24-Mar24.pdf | 13 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AstoniaClassic-A5-Jan24-Mar24.pdf | 13 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Astonia Classic A5 Building.pdf | 11 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AstoniaClassic-A5-Jan24-Mar24.pdf | 11 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AstoniaClassic-A5-Jan24-Mar24.pdf | 11 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory Astonia Clssiac A5.pdf | 11 Apr 2024 |
| Certificates of CA (Form 3)File: CA Certificate Astonia Classic A5.pdf | 11 Apr 2024 |
| Declaration about Commencement CertificateFile: Declaration for CC.pdf | 30 Jan 2024 |
| Declaration in FORM BFile: Declaration in Format B.pdf | 30 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AstoniaClassicA5-13-01-2024.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory Astonia Classic A5 Building (Revised).pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory Astonia Classic A5 Building (Revised).pdf | 30 Jan 2024 |
| CERSAI detailsFile: CERSAI Decleration.pdf | 30 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of interest in other real estate ( Kishor Sir).pdf | 30 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of interest in other real estate ( Sanjeev Sir).pdf | 30 Jan 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Astonia Classic A1 to A4 Building | Village Undri Taluka Haveli Dist. Pune | 384 | Completed | Dec 2015 | Late, Nov 2016 |
| Amits Colori A to F Building | Village Undri Taluka Haveli District Pune | 288 | Completed | Dec 2012 | Mar 2012 |
| Astonia Royale A to J, Q and R Building | Village Ambegaon Budruk Taluka Haveli Dist Pune | 576 | Completed | Aug 2012 | Late, Nov 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 150 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Astonia Classic Phase II - A5 Building on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Undri13,700+ in Pune
Filed coordinates, straight-line distance. 159 registered projects within 2 km.
THE SPECTRUM
SHRIRAM PROPERTIES LIMITED
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N
GOEL GANGA INDIA PVT LTD
NYATI ESTEBAN II
NYATI REALTORS LLP
Lodha Pune NIBM Project
Lodha Developers Limited
KHUSH VISTA
Elated Housing LLP
The Atrium
Arhumashtika Life Spaces
Builder: AMIT ENTERPRISES HOUSING LIMITED
AMIT ENTERPRISES HOUSING LIMITED has 8 registrations on MahaRERA, including AMITs COLORI Phase-II H and I Building and AMITs COLORI Phase-III G Building. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Astonia Classic Phase II - A5 Building is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Astonia Classic Phase II - A5 Building?
The registered promoter entity is AMIT ENTERPRISES HOUSING LIMITED, a company as per the filing. Its CIN U45200PN2008PLC131731 and GSTIN 27AAGCA9192A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Astonia Classic Phase II - A5 Building?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Astonia Classic Phase II - A5 Building?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Astonia Classic Phase II - A5 Building?
The professionals named in the filing: Architect: Mr Jagadish Deshpande; Architect: Prafulla Ramchandra Nadkarni; Architect: Unmesh Vitthal Vaidya; Engineer: J + W Consultants LLP; Engineer: Abhay Pramod Inamdar; Chartered Accountant: Dharini Naswa & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Astonia Classic Phase II - A5 Building?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback