Home / Developers / AMIT ENTERPRISES HOUSING LIMITED
AMIT ENTERPRISES HOUSING LIMITED: RERA track record
CIN U45200PN2008PLC131731 · GSTIN 27AAGCA9192A1ZP · Company · attribution by exact filing name, entity resolution in progress
AMIT ENTERPRISES HOUSING LIMITED has 8 registrations on MahaRERA, including AMITs COLORI Phase-II H and I Building and AMITs COLORI Phase-III G Building. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Litigation is declared on 4 of its registrations.
Projects by this developer
Showing all 8 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| AMITs BLOOMFIELD PHASE III - J AND K BUILDINGP52100005644 | Ambegaon, Pune, 411046 | 252 | 68% | 11 Aug 2017 | Registered |
| Astonia Royale Phase II - K and L BuildingP52100001124 | Ambegaon Bk, Pune, 411046 | 165 | 88% | 26 Jul 2017 | Completed |
| Astonia Royale Phase IV M and N BuildingsPR1262022601145 | Ambegaon Budruk-Ext, Pune, 411046 | 165 | 0% | 13 Jul 2026 | Registered |
| Astonia Classic Phase II - A5 BuildingP52100001359 | Undri, Pune, 411060 | 96 | 50% | 27 Jul 2017 | Registered |
| Astonia Royale Phase III - P BuildingP52100001045 | Ambegaon Bk, Pune, 411046 | 81 | 90% | 25 Jul 2017 | Registered |
| Astonia Royale Phase V - O BuildingPR1263032602094 | Ambegaon Budruk-Ext, Pune, 411046 | 72 | 0% | 1 Oct 2026 | Registered |
| AMITs COLORI Phase-II H and I BuildingP52100001940 | Undri, Pune, 411060 | - | - | 29 Jul 2017 | Completed |
| AMITs COLORI Phase-III G BuildingP52100000785 | Undri, Pune, 411060 | - | - | 23 Jul 2017 | Completed |
What this promoter declares as its own experience
AMIT ENTERPRISES HOUSING LIMITED declares experience on 10 earlier projects. 7 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
7 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Astonia Royale A to J, Q and R Building | 20 Aug 2012 | 27 Nov 2013 | +15 months |
| Amits Colori A to F Building | 31 Dec 2012 | 30 Mar 2012 | On time |
| Astonia Classic A1 to A4 Building | 31 Dec 2015 | 2 Nov 2016 | +10 months |
| AMITs COLORI Phase-II H and I Building P52100001940 | 19 Jan 2019 | 30 Jun 2019 | +5 months |
| Astonia Classic Phase II - A5 Building P52100001359 | 31 Dec 2020 | Not completed yet | Ongoing |
| AMITs COLORI Phase-III G Building P52100000785 | 30 Jun 2021 | 27 Mar 2025 | +45 months |
| Astonia Royale Phase II - K and L Building P52100001124 | 31 Dec 2021 | 24 Jul 2025 | +43 months |
| Astonia Royale Phase III - P Building P52100001045 | 31 Dec 2021 | Not completed yet | Ongoing |
| AMITS BLOOMFIELD PHASE III - J AND K BUILDING P52100005644 | 31 Dec 2021 | Not completed yet | Ongoing |
| Astonia Royale Phase IV M and N Buildings PR1262022601145 | 31 Mar 2031 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify AMIT ENTERPRISES HOUSING LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200PN2008PLC131731 and GSTIN 27AAGCA9192A1ZP on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with AMIT ENTERPRISES HOUSING LIMITED?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make AMIT ENTERPRISES HOUSING LIMITED unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.