Registered No litigation declared Residential / Group Housing project

Aqura Prime

By AQURA BUILDER & DEVELOPER PRIVATE LIMITED

RG-MH-23672 · RERA P52100078984 · Last updated on MahaRERA portal: 25 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2028Possession promisedmoved 15 months from the original
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
23 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Aqura Prime is a Residential / Group Housing project by AQURA BUILDER & DEVELOPER PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100078984 on 28 Jan 2025. Possession is promised by 30 Jul 2028. The completion date has moved by 15 months from the original filing. 0 of the 23 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameAqura Prime
  • TypeResidential / Group Housing
  • Location
    • Haveli
    • Ramwadi Wadgaon Sheri
    • Vadgaon Sheri
    • Pune
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100078984
  • ReraGenie IDRG-MH-23672

Builder

  • NameAQURA BUILDER & DEVELOPER PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200PN2013PTC146430
  • GSTIN27AALCA4203B1Z8
  • Managing DirectorsALANKAR DALJIT DIXIT, SUGANDHI DALJIT DIXIT
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2025First promiseApr 2027Revised toJul 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Jan 2025
  • Promised completion30 Jul 2028
  • Revised completionRevised to 30 Jul 2028 (originally 1 Apr 2027)
  • Buildings1 building record
  • Documents filed56 files

Current status

0%0 of 23 units booked
8.7%Work done, per cost certificate

Figures as on 25 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aqura PrimeNA8723023

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Aqura Prime: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,165 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jun 2025
LandownerVillageDistrict
Shri Sadguru Hambirbaba Sahakari Gruharachna Sanst-Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI4660.8
Proposed, not sanctioned2,050 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUSMALLFINANCEBANKLTD,SHOPNO.1AND2,GULMOHARPARTMENTS,USHACO-OPSOCIETY,EASTSTREET,PUNE-411001,MAHARASHTRA
Estimated costRs 21.07 cr
Cost incurredRs 1.82 cr
Work done8.66%
BuildingWingEstimatedIncurred
Aqura PrimeNARs 19.45 crRs 1.82 cr
-NARs 1.62 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJay Aeram and Associates Architects and Planners
EngineerRathi Group
Chartered AccountantBogati & Company
Chartered AccountantR H Pothiwal & Associates
Chartered AccountantVaibhav S Bhise & Associates
Chartered AccountantPravin Pise & Associates
Chartered AccountantPravin Pise and Associates
PartnerRole in project
Aqura Builder and Developer Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23062621485Apr 2027 → Jul 2028

Reason as filed by the promoterThe project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with require

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jul 2028

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Aqura Prime-FY 26-27-Q1(signed both).pdf25 Jul 2026
Withdrawal Update Form 2File: Form 2 - Aqura Prime.pdf25 Jul 2026
Withdrawal Update Form 3File: F 3 - AQURA PRIME.pdf25 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - FY 2025-26.pdf19 May 2026
Withdrawal Update Form 1File: From 1-Architect-Aqura Prime-Mar 26.pdf18 May 2026
Withdrawal Update Form 2File: Form 2-Aqura Prime-Q4-Mar 26.pdf18 May 2026
Withdrawal Update Form 3File: Form 3-Mar 26-Aqura Prime.pdf18 May 2026
Withdrawal Update Form 1File: FM_1_Sep_2025.pdf2 Feb 2026
Withdrawal Update Form 1File: Form 1_Dec_2025.pdf2 Feb 2026
Withdrawal Update Form 2File: Form 2_Sep_2025.pdf2 Feb 2026
Withdrawal Update Form 2File: Fm_2_Dec_2025.pdf2 Feb 2026
Withdrawal Update Form 3File: Form 3_Sep_2025.pdf2 Feb 2026
Withdrawal Update Form 3File: F3-AQURA PRIME-Q3.pdf2 Feb 2026
Form 5 (FY 2024-2025)File: Form 5-Aqura Prime-FY 24-25(final)(signed).pdf16 Jan 2026
Withdrawal Update Form 1File: 1 Architech certificate-Form1-Prime-June 25-Signed.pdf12 Sep 2025
Withdrawal Update Form 2File: 2 Engg certificate-Form 2-Prime-June 25-signed.pdf12 Sep 2025
Withdrawal Update Form 3File: 3 CA certificate-Form3-Prime-June25 -signed.pdf12 Sep 2025
Form 1File: Form 1_March 25.pdf18 Jun 2025
Form 2File: Form 2_March 25.pdf18 Jun 2025
Form 3File: Form 3_March 25.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure_March 25.pdf18 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Aqura Prime-Final.pdf22 Jan 2025
Other - FinanceFile: Declaration.pdf22 Jan 2025
Copy of the legal title reportFile: Legal title report.pdf9 Jan 2025
Proforma of Agreement for saleFile: Drfat Agreememt For Sale.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Form-1.pdf30 Dec 2024
Other - TechnicalFile: Declaration of One Plot One Registration - Aqura Prime.pdf30 Dec 2024
Details of encumbrances concerned to FinanceFile: EC - Fin.pdf4 Dec 2024
Details of encumbrances concerned to FinanceFile: EC - Legal.pdf4 Dec 2024
Proforma of Allotment letterFile: Allotment Letter.pdf4 Dec 2024
Declaration in FORM BFile: Scan-Form B-Developer after notary.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Dec 2024
Declaration about Commencement CertificateFile: Form D.pdf4 Dec 2024
CERSAI detailsFile: CERSAI Report.pdf4 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf4 Dec 2024
Deviation Report with respect to Allotment letterFile: Devi - AL.pdf4 Dec 2024
Details of encumbrances concerned to LegalFile: EC - Fin.pdf4 Dec 2024
Details of encumbrances concerned to LegalFile: EC - Legal.pdf4 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Devi - AFS.pdf4 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estates.pdf4 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf4 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Secure and Unsecure.pdf4 Dec 2024
Building plan approvalFile: Building Plan_Sheet No 3_compressed.pdf22 Nov 2024
Building plan approvalFile: Building Plan_Sheet No 2_compressed.pdf22 Nov 2024
Building plan approvalFile: Building Plan_Sheet No 1_compressed.pdf22 Nov 2024
Layout approvalFile: Building Plan_Sheet No 3_compressed.pdf22 Nov 2024
Layout approvalFile: Building Plan_Sheet No 2_compressed.pdf22 Nov 2024
Layout approvalFile: Building Plan_Sheet No 1_compressed.pdf22 Nov 2024
Copy of Layout Approval (in case of layout)File: Building Plan_Sheet No 1_compressed.pdf22 Nov 2024
Copy of Layout Approval (in case of layout)File: Building Plan_Sheet No 2_compressed.pdf22 Nov 2024
Copy of Layout Approval (in case of layout)File: Building Plan_Sheet No 3_compressed.pdf22 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_Sheet No 2_compressed.pdf22 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_Sheet No 1_compressed.pdf22 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_Sheet No 3_compressed.pdf22 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC-3049-23 DT 28-02-2024_compressed.pdf9 Jul 2024
PAN CardFile: PAN_Aqura Builders.pdf8 Jul 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late1 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Aqura Pride Wing APM1260002501897Near Raghunand Hall, Pune64Dec 2025OngoingMay 2028Not due yet
AQURA PRIDEP52100031863Next to Mumbai Bengaluru, Pune132Nov 2021OngoingSep 2026Registered original: Sep 2025Not delivered
AQURA PARADISEP52100000498Pune (M Corp.), Pune28Jul 2017CompletedJan 2020Late, Dec 2021

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 15 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aqura Prime on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ramwadi Wadgaon Sheri13,700+ in Pune

2 kmAqura PrimeCompleted 36Lapsed / revoked 17Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 87 registered projects within 2 km.

Builder: AQURA BUILDER & DEVELOPER PRIVATE LIMITED

AQURA BUILDER & DEVELOPER PRIVATE LIMITED has 3 registrations on MahaRERA, including AQURA PARADISE and AQURA PRIDE. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aqura Prime is delayed beyond 30 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aqura Prime?

The registered promoter entity is AQURA BUILDER & DEVELOPER PRIVATE LIMITED, a company as per the filing. Its CIN U45200PN2013PTC146430 and GSTIN 27AALCA4203B1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aqura Prime?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aqura Prime?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aqura Prime?

The professionals named in the filing: Architect: Jay Aeram and Associates Architects and Planners; Engineer: Rathi Group; Chartered Accountant: Bogati & Company; Chartered Accountant: R H Pothiwal & Associates; Chartered Accountant: Vaibhav S Bhise & Associates; Chartered Accountant: Pravin Pise & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aqura Prime?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aqura Prime. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aqura Prime to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.