ANANTAYA APARTMENTS
RG-MH-90117 · RERA P51900011221 · Last updated on MahaRERA portal: 5 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 60 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANTAYA APARTMENTS is a Residential / Group Housing project by Sanskriti Developers in Mumbai City, Maharashtra, registered with MahaRERA as P51900011221 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 60 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameANANTAYA APARTMENTS
- TypeResidential / Group Housing
- Location
- T G path
- Girgaon
- Mumbai City
- 400004
- Pincode400004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900011221
- ReraGenie IDRG-MH-90117
Builder
- NameSanskriti Developers
- Entity typePartnership
- PartnersHitesh Babulal Bohra, Vijay Bhawarlal Jain
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed180 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ANANTAYA | NA | 38 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.
ANANTAYA: 99% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed47
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | Karia Chheda & Associates |
| Partner | Role in project |
|---|---|
| Sanskriti Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate sector and Prolonged delay in obtaining necessary delay from the Authority. However, we shall endeavor completion of project within extended duration of 12 months.
Reason as filed by the promoterDetailed reasons are provided in the other attachment.
Reason as filed by the promoterThe delay has been caused by a combination of procurement issues, site conditions, temporary funding constraints, and delays in obtaining the final Occupancy Certificate (OC). However, we have received the Part Occupancy Certificate (OC) for the floors up to the 13th level, and possession letters have been issued to the allottees of these floors. For flats beyond the 13th floor, we have obtained consents from the allottees and submitted the required consents to the authorities. We kindly request an extension until 31st December 2026 to finalize the construction, secure the final OC, and ensure
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000334131 | VINOD JAIN | M/s. Sankriti Developer | 04/02/2023 |
| CC006000000375404 | Sanskriti Developers | VINOD NANDLAL JAIN | 27/04/2023 |
| CC12401175 | Sanskriti Developers | Vinod Nandlal Jain | 19/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Apr 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Jul 2023
Documents filed180
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Anantaya Apartments as on March 2026.pdf | 5 May 2026 |
| Form 2File: Form 2 - Anantaya Apartments as on March 2026.pdf | 5 May 2026 |
| Form 3File: Form 3 - Anantaya Apartments as on March 2026.pdf | 5 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Anantaya Apartment as on March 2026.pdf | 5 May 2026 |
| Form 1File: Form 1 - Anantaya Apartments as on Dec 2025.pdf | 20 Jan 2026 |
| Form 2File: Form 2 - Anantaya Apartments as on Dec 2025.pdf | 20 Jan 2026 |
| Form 3File: Form 3 - Anantaya Apartments as on Dec 2025.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Anantaya Apartments as on Dec 2025.pdf | 20 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Anantaya Apartments FY 2024-25.pdf | 8 Dec 2025 |
| Form 1File: Form 1 - Anantaya Apartments as on Sept 2025.pdf | 29 Oct 2025 |
| Form 2File: Form 2 - Anantaya Apartments as on Sept 2025.pdf | 29 Oct 2025 |
| Form 3File: Form 3 - Anantaya Apartments as on Sept 2025.pdf | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Anantaya Apartments as on Sept 2025.pdf | 29 Oct 2025 |
| Form 1File: Form 1 - Anantaya Apartment as on June 2025.pdf | 28 Jul 2025 |
| Form 2File: Form 2 - Anantaya Apartments as on June 2025.pdf | 28 Jul 2025 |
| Form 3File: Form 3 - Anantaya Apartments as on June 2025.pdf | 28 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Anantaya Apartments as on June 2025.pdf | 28 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 Anantaya Apartments as on 31-03-2025.pdf | 20 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Anantaya Apartments as on March 2025.pdf | 20 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Anantaya Apartments as on March 2025.pdf | 7 Apr 2025 |
| Declaration in FORM BFile: FORM B (4).pdf | 15 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11zon_rotated-PDF (1).pdf | 30 Jan 2025 |
| Certificates of CA (Form 3)File: 11zon_rotated-PDF (3).pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11zon_rotated-PDF (2).pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29.pdf | 30 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Anantaya Apartments as on Dec 2024.pdf | 7 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 - Anantaya Apartments as on Dec 2024.pdf | 7 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Anantaya Apartments as on Dec 2024.pdf | 7 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Anantaya Apartment - 2021.pdf | 16 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Anantaya Apartment - 2021.pdf | 16 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Anantaya CC.pdf | 12 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate year 2019-2020.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate year 2023-2024.pdf | 19 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 24 (2).pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 24.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Sept 24.pdf | 17 Oct 2024 |
| Declaration in FORM BFile: Form B.pdf | 16 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep 24.pdf | 16 Oct 2024 |
| Certificates of CA (Form 5)File: Form 5 17-18.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 16 Oct 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 16 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 16 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Interest.pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 16 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Anantaya Apartments as on June 2024.pdf | 11 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 - Anantaya Apartments as on June 2024.pdf | 11 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Anantaya Apartments as on June 2024.pdf | 1 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: ANANTAYA APARTMENT SOLD BOOKED INVETORY.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Anantaya Apartments as on March 2024.pdf | 18 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 - Anantaya Apartments as on March 2024.pdf | 18 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Anantaya Apartments as on March 2024.pdf | 3 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Anantaya Apartments as on Dec 2023.pdf | 4 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 - Anantaya Apartments as on Dec 2023.pdf | 4 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ANANTAYA APARTMENTS as on Dec 2023.pdf | 9 Jan 2024 |
| Certificates of CA (Form 3)File: Form_3_Oct_Signed_compressed.pdf | 11 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAN_ENG.pdf | 8 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera certificate dt 30 09 2023.pdf | 4 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ANNUAL AUDIT REPORT_Form 5.pdf | 4 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT certificate dt 30 06 2023.pdf | 14 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2 (2).pdf | 14 Jul 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2362302_OC_signed.pdf | 10 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc.pdf | 28 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1.pdf | 28 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng.pdf | 28 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM_2.pdf | 28 Jun 2023 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 28 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM_2A_2022.pdf | 23 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM_2A_2023.pdf | 23 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1_AC_Mar_21.pdf | 21 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2_AC_June_21.pdf | 21 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3_AC_Dec_21.pdf | 21 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4_AC_Mar_22.pdf | 21 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5_AC_June_22.pdf | 21 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6_AC_Sept_22.pdf | 21 Jun 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Shakuntala SadanP51900055307 | Bhuleshwar | 61 | Mar 2024 | Ongoing | Dec 2028 | Not due yet |
| Annapurna SadanP51900007411 | J S S ROAD,GIRGAON CHURCH, Mumbai City | 82 | Aug 2017 | Ongoing | Jun 2026Registered original: Dec 2024 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 180 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANANTAYA APARTMENTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Girgaon780+ in Mumbai City
Filed coordinates, straight-line distance. 152 registered projects within 2 km.
SHREEPATI CASTLE
SHREEPATI CASTLE
Meadows
Celestial Globe (A.O.P.)
SHREEPATI BAYVIEW
SHREEPATI BUILD INFRA INVESTMENT LIMITED
NAKODA MEHTA SUNSHINE HEIGHTS A AND C WINGS
CHANDULAL JORAVARMALJI MEHTA
Earth Enclave
Earth Graphics
Chandan Signature
PAVAN KUMAR BACHHRAJ CHANDAN
See every Mumbai City project, with the district possession charts
Builder: Sanskriti Developers
Sanskriti Developers has 1 registration on MahaRERA, including ANANTAYA APARTMENTS. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if ANANTAYA APARTMENTS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANTAYA APARTMENTS?
The registered promoter entity is Sanskriti Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANTAYA APARTMENTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ANANTAYA APARTMENTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ANANTAYA APARTMENTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANTAYA APARTMENTS?
The professionals named in the filing: Chartered Accountant: Karia Chheda & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANTAYA APARTMENTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.