SHREEPATI BAYVIEW
By SHREEPATI BUILD INFRA INVESTMENT LIMITED
RG-MH-95589 · RERA P51900010019 · Last updated on MahaRERA portal: 8 Apr 2025
Source: official MahaRERA filing
Red flags
- De-registered
- Litigation declared, 3 cases
- 1 complaint at MahaRERA
Clear
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEPATI BAYVIEW is a Residential / Group Housing project by SHREEPATI BUILD INFRA INVESTMENT LIMITED in 400004, registered with MahaRERA as P51900010019 on 23 Aug 2017. Possession is promised by 30 Dec 2026. 0 of the 399 units on this registration are recorded sold or booked, and 0 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSHREEPATI BAYVIEW
- TypeResidential / Group Housing
- Location
- 400004
- Pincode400004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900010019
- ReraGenie IDRG-MH-95589
Builder
- NameSHREEPATI BUILD INFRA INVESTMENT LIMITED
- Entity typeCompany
- Managing DirectorRAJENDRA RAMEHCHANDRA CHATURVEDI
- Other registrations2 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on23 Aug 2017
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings5 building records
- Documents filed61 files
Current status
Figures as on 8 Apr 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GIRGAON EKTA SOCIETY | NA | 24 | 24 | 0 | 0 | 0 |
| WING B | NA | 20 | 20 | 155 | 0 | 155 |
| WING C | NA | 24 | 24 | 237 | 0 | 237 |
| WING D | NA | 23 | 23 | 7 | 0 | 7 |
| WING E | NA | 24 | 24 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 8 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 0%.
GIRGAON EKTA SOCIETY0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 8 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed133
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| GIRGAON EKTA SOCIETY | 26 | 26 |
| WING B | 31 | 31 |
| WING C | 30 | 30 |
| WING D | 28 | 28 |
| WING E | 18 | 18 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KALPESH SHAH |
| Engineer | Sunil Sohani |
| Chartered Accountant | Jain Ashwani & Co. |
| Chartered Accountant | M B Agarwal & Co. |
| Chartered Accountant | Punit B. Gupta & Associates |
| Chartered Accountant | Bansal & Co. LLP |
| Partner | Role in project |
|---|---|
| SHREEPATI BUILD INFRA INVESTMENT LIMITED | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| WP/209/2015/2015 | HIGH COURT | PREADMISSION |
| 978/2018 | High Court | Pre admission |
| 978/2018 | High Court | Closed |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056636 | PROZONE DEVELOPERS & REALTORS PRIVATE LIMITED | Shreepati Build Infra Investment Private Limited | 19/10/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed61
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Q1 24-25.pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Q2 24-25_compressed.pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Q3 24-25_compressed.pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Q1 03-07-2023.pdf | 30 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Q2 02-10-2023.pdf | 30 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Q3 02-01-2024.pdf | 30 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Q4 03-04-2024.pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 Q1 03-07-2023.pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 Q2 02-10-2023.pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 Q3 03-01-2024.pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 Q4 02-04-2024.pdf | 30 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: fORM-5 22-23.pdf | 22 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 Bayview.pdf | 2 May 2024 |
| Certificates of CA (Form 3)File: bayview.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Shreepati Bayview MARCH 2023_compressed.pdf | 18 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate ( Kalpesh Shah) 16-04-2022.pdf | 8 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginners Certificate Form 2 bayview M22.pdf | 8 May 2023 |
| Certificates of CA (Form 3)File: shreepati Bayview form-3_compressed.pdf | 8 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Bayview Report with Annex 1_compressed.pdf | 8 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Bayview Report with Annex 1_compressed.pdf | 8 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bayview Architect certificate M 21.pdf | 19 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final Engineers Certificate_Bay View 2021.pdf | 19 Sep 2022 |
| Certificates of CA (Form 3)File: Form 3 bayview M 21_compressed.pdf | 19 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Bayview M 21.pdf | 19 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 RERA.pdf | 4 Dec 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2.pdf | 4 Dec 2021 |
| Certificates of CA (Form 3)File: Form3 RERA.pdf | 4 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5.pdf | 4 Dec 2021 |
| OtherFile: Penalty Payment Ack.pdf | 6 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect certificate.pdf | 14 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bayview_Engineer_Form_2.pdf | 14 Nov 2019 |
| Certificates of CA (Form 3)File: Bayview_Form_3.pdf | 14 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual audit repoet_FORM 5.pdf | 14 Nov 2019 |
| Certificates of CA (Form 5)File: Form -5 Bay View.pdf | 23 Nov 2018 |
| OtherFile: LEGAL CERTIFICATE.pdf | 27 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rvised Engineers Certificates.pdf | 16 Oct 2018 |
| Certificates of CA (Form 3)File: CA CER_SHREEPATI BAY VEIW_REVISED.pdf | 16 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Cerrificate-compressed.pdf | 15 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 15 Oct 2018 |
| Certificates of CA (Form 3)File: CA CSR BAY VIEW.pdf | 15 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf | 31 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf | 31 Oct 2017 |
| Certificates of CA (Form 3)File: SHREEPATI BAY VIEW.pdf | 31 Oct 2017 |
| Building plan approvalFile: IOD PLAN.pdf | 29 Jul 2017 |
| Layout approvalFile: BAYVIEW.pdf | 29 Jul 2017 |
| Layout approvalFile: KRANTI NAGER Approved plan.pdf | 29 Jul 2017 |
| PAN CardFile: PAN SBIIL.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: TITLE KRANTINAGAR.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: BAYVIEW.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: KRANTI NAGER Approved plan.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: IOD PLAN.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: FORM B.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certitificate.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf | 29 Jul 2017 |
| OtherFile: CIVIL AIRPORT NOC DT 08-02-2013.pdf | 29 Jul 2017 |
| OtherFile: REVISED NOC 11-12-2013-.pdf | 29 Jul 2017 |
| OtherFile: MMRDA NOC DT-11-05-2015-.pdf | 29 Jul 2017 |
| OtherFile: CFO NOC.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 61 filed documents as one ZIP, foldered, with a manifest
Keep SHREEPATI BAYVIEW on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near this project
Filed coordinates, straight-line distance. 70 registered projects within 2 km.
SHREEPATI CASTLE
SHREEPATI CASTLE
Meadows
Celestial Globe (A.O.P.)
NAKODA MEHTA SUNSHINE HEIGHTS A AND C WINGS
CHANDULAL JORAVARMALJI MEHTA
Earth Enclave
Earth Graphics
Chandan Signature
PAVAN KUMAR BACHHRAJ CHANDAN
Jayant Sky
Jayantilal Lunkad
Builder: SHREEPATI BUILD INFRA INVESTMENT LIMITED
SHREEPATI BUILD INFRA INVESTMENT LIMITED has 3 registrations on MahaRERA, including SHREEPATI ARADHANA and SHREEPATI CORONET. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What does it mean that SHREEPATI BAYVIEW shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREEPATI BAYVIEW is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEPATI BAYVIEW?
The registered promoter entity is SHREEPATI BUILD INFRA INVESTMENT LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEPATI BAYVIEW?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHREEPATI BAYVIEW?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHREEPATI BAYVIEW?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEPATI BAYVIEW?
The professionals named in the filing: Architect: KALPESH SHAH; Engineer: Sunil Sohani; Chartered Accountant: Jain Ashwani & Co.; Chartered Accountant: M B Agarwal & Co.; Chartered Accountant: Punit B. Gupta & Associates; Chartered Accountant: Bansal & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEPATI BAYVIEW?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.