Home / Browse projects / Pune, Maharashtra / AMITs COLORI Phase-III G Building

Completed Litigation declared Residential / Group Housing project

AMITs COLORI Phase-III G Building

By AMIT ENTERPRISES HOUSING LIMITED

RG-MH-09137 · RERA P52100000785 · Last updated on MahaRERA portal: 29 Mar 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 45 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
3Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

AMITs COLORI Phase-III G Building is a Residential / Group Housing project by AMIT ENTERPRISES HOUSING LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100000785 on 23 Jul 2017. The registration is recorded completed; possession was promised by 28 Mar 2025. The completion date has moved by 45 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameAMITs COLORI Phase-III G Building
  • TypeResidential / Group Housing
  • Location
    • Undri Road
    • Undri
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000785
  • ReraGenie IDRG-MH-09137

Builder

  • NameAMIT ENTERPRISES HOUSING LIMITED
  • Entity typeCompany
  • CINU45200PN2008PLC131731
  • GSTIN27AAGCA9192A1ZP
  • ChairpersonKISHOR GOVIND PATE
  • DirectorsSanjeev Govind Pate, Rohan Kishor Pate
  • Other registrations7 more →
  • Completed3 of 8
  • Past their filed date1
  • Declared earlier projects10 →

Key dates

this monthRegisteredJul 2017First promiseJun 2021Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion28 Mar 2025
  • Revised completionRevised to 28 Mar 2025 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed110 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building GNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Building G: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities22

As on 29 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes90%
Street LightingYes95%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes85%
Energy managemcntYes98%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes50%
Swiming and Toddler poolYes100%
Table Tenis roomYes100%
Study roomYes100%
Multipurpose hallYes100%
GymYes100%
Children play areaYes100%
Billiard roomYes100%

Parking filed48

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots48
Closed/Covered11
Open Space37

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,352 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityPune Municipal Corportation
Permissible FSI3453.6
Proposed, not sanctioned3,454 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCommercial Branch, Senapati Bapat Road, Pune

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
AMIT ENTERPRISES HOUSING LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008626Jun 2021 → Jun 2022

Reason as filed by the promoterDue to Covid19 pandemic shortage of manpower and material. Slow market condition.

EXT52100023045Jun 2021 → Dec 2024

Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. These economic crises impeded the progress of sale transactions, substantially impacting the project's cash flow. Just as market conditions began to show signs of improvement, the emergence of the Covid-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced considerable delays, causing monetary distress. Throughout these challe

EXT52100015059Jun 2021 → Dec 2023

Reason as filed by the promoterThe construction of the said project is almost completed (approx 85%) and we need another extension to finish the remaining work and handover the units to allottees. The consent of the allottees is attached for the extension. Therefore, request you to kindly provide the same.

EXT52100027382Jun 2021 → Mar 2025

Reason as filed by the promoter1. OC Received from Pune Municipal Corporation vide no OCC/1522/24 2. ⁠Seeking the extension till the date of OC 3. OC has uploaded in Main Application 4. Revised Form B uploaded in Other tab No. 2 5. QPR till date are updated.

Litigation declared1

CaseCourtStatus
49/2017Divisional Jt Registrar Pune Division PuneHearing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000177809HEERALAL RUPARAM SUTHARTATA CAPITAL HOUSING FINANCE LIMITED16/11/2022
CC005000000198002Prajakta Sahebrao BhosaleSanjeev Pate28/12/2022
CC005000000370929PAPPU MARUTI GADADEAMIT ENTERPRISES HOUSING LTD Throw Its Director SANJEEV GOVIND PATE, KISHOR GOVIND PATE20/06/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Mar 2025

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Colori.pdf29 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amit Completion Certificate G - Building (1).pdf28 Mar 2025
Declaration in FORM BFile: Form B - Affidavit Cum Declaration.pdf19 Mar 2025
Other - TechnicalFile: PERT Chart (4).pdf19 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Colori G.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Amits Colori G Bld - Form 2.pdf16 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Amits Colori G Bld - Form 2A.pdf16 Jan 2025
Certificates of CA (Form 3)File: Amits Colori - G Bld.pdf14 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Colori G Building Dec-24.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Colori G.pdf10 Jan 2025
Certificates of CA (Form 3)File: From3 Colori G.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori G Building.pdf22 Oct 2024
Certificates of CA (Form 3)File: From3 Colori G.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-Colori-G-Jul24-Sep24.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Colori G.pdf22 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-Colori-G-Jul24-Sep24.pdf22 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Colori G.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori G Building JUNE 24.pdf13 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-Colori-G-Apr24-June24 (2).pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-Colori-G-Apr24-June24.pdf13 Jul 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Colori G Building.pdf13 Jul 2024
Certificates of CA (Form 3)File: CA Certificate Colori G Building.pdf13 Jul 2024
Details of encumbrances concerned to FinanceFile: Details of Encumbrance.pdf17 Jun 2024
Details of encumbrances concerned to LegalFile: Details of Encumbrance.pdf17 Jun 2024
Declaration about Commencement CertificateFile: Decleration of commencement Certificate.pdf17 Jun 2024
Declaration in FORM BFile: Affidavit Cum Declaration.pdf17 Jun 2024
CERSAI detailsFile: Declaration for CERSAI.pdf17 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5 Stamped.pdf17 Jun 2024
Proforma of Agreement for saleFile: GetUserDocumentFileContent.pdf17 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for separate Bank Account.pdf17 Jun 2024
Layout approvalFile: SANCTION LAYOUT 2019.pdf14 Jun 2024
Copy of Layout Approval (in case of layout)File: SANCTION LAYOUT 2019.pdf14 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: CC-3170 Dated - 11-01-2019 - COLORI.pdf14 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Plinth Cheking 30-06-11 Building G.pdf14 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-Colori-G-Jan24-Mar24.pdf14 Jun 2024
Certificates of CA (Form 3)File: CA Certificate Colori G Building Stamped.pdf14 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of interest in other real estate ( Kishor Sir).pdf14 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of interest in other real estate ( Sanjeev Sir).pdf14 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori G Building.pdf13 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-Colori-G-Jan24-Mar24.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-Colori-G-Jan24-Mar24.pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Colori G Building.pdf13 Apr 2024
Certificates of CA (Form 3)File: CA Certificate Colori G Building.pdf13 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori G Building Dec -2023_.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-CLR-G-04-01-2024.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Colori G Building.pdf13 Jan 2024
Certificates of CA (Form 3)File: Form 3 - Colori G.pdf13 Jan 2024
Certificates of CA (Form 3)File: AEHL - COLORI G - FORM 3 - 30-9-23.pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori G Building.pdf14 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-CLR-G-July-September2023.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-CLR-G-July-September2023.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-CLR-G-July-September2023.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Booked Inventory Colori G Building.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 COLORI G 31-3-2023.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 COLORI G 31-3-2023.pdf11 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Colori G building Form 1 Architect Certificate.pdf18 Jul 2023
Disclosure of sold/ booked inventoryFile: Colori G Building.pdf18 Jul 2023
Certificates of CA (Form 3)File: RERA FORM 3 COLORI G AS ON 31-03-23.pdf18 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A CL Jan23-Mar23.pdf17 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori Phase -III G Building.pdf13 Apr 2023
Disclosure of sold/ booked inventoryFile: Colori.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Color G Dec2022.pdf16 Mar 2023
Certificates of CA (Form 3)File: RERA FORM 3 COLORI G AS ON 31-12-2022.pdf16 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form 1 for Colori Phase -III G Building.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: Colori G.pdf7 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Colori G.pdf22 Oct 2022
Certificates of CA (Form 3)File: COLORI G RERA FORM 3.pdf22 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: COLORI G FORM 5.pdf13 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Colori Phase -III G Building.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Colori G.pdf7 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate Colori G.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: Colori G.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Colori G Engg Certificate.pdf1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Colori Quality assurance certificate.pdf1 Aug 2022
Disclosure of sold/ booked inventoryFile: Colori G.pdf8 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate COLORI G BUILDING .pdf7 Jul 2022
Certificates of CA (Form 3)File: COLORI G RERA FORM 3.pdf7 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: COLORI G FORM 5.pdf13 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Colori G Building.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold Inventory Colori Building G.pdf7 Apr 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Astonia Classic A1 to A4 BuildingVillage Undri Taluka Haveli Dist. Pune384CompletedDec 2015Late, Nov 2016
Amits Colori A to F BuildingVillage Undri Taluka Haveli District Pune288CompletedDec 2012Mar 2012
Astonia Royale A to J, Q and R BuildingVillage Ambegaon Budruk Taluka Haveli Dist Pune576CompletedAug 2012Late, Nov 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 45 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AMITs COLORI Phase-III G Building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri13,700+ in Pune

2 kmAMITs COLORI Phase-III GCompleted 96Lapsed / revoked 30Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 224 registered projects within 2 km.

Builder: AMIT ENTERPRISES HOUSING LIMITED

AMIT ENTERPRISES HOUSING LIMITED has 8 registrations on MahaRERA, including AMITs COLORI Phase-II H and I Building and AMITs COLORI Phase-III G Building. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AMITs COLORI Phase-III G Building is delayed beyond 28 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AMITs COLORI Phase-III G Building?

The registered promoter entity is AMIT ENTERPRISES HOUSING LIMITED, a company as per the filing. Its CIN U45200PN2008PLC131731 and GSTIN 27AAGCA9192A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AMITs COLORI Phase-III G Building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AMITs COLORI Phase-III G Building?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AMITs COLORI Phase-III G Building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in AMITs COLORI Phase-III G Building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMITs COLORI Phase-III G Building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMITs COLORI Phase-III G Building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.