Home / Browse projects / Mumbai Suburban, Maharashtra / AMARDEEP ALLIANCE
AMARDEEP ALLIANCE
By ALLIANCE CITY DEVELOPERS REALTORS PVT LTD
RG-MH-27806 · RERA P51800024225 · Last updated on MahaRERA portal: 29 Sep 2022
Source: official MahaRERA filing
Red flags
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 9 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMARDEEP ALLIANCE is a Residential / Group Housing project by ALLIANCE CITY DEVELOPERS REALTORS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800024225 on 27 Jan 2020. The registration is recorded completed; possession was promised by 31 Jul 2024. 2 complaints are on record with the regulator.
At a glance
Project
- NameAMARDEEP ALLIANCE
- TypeResidential / Group Housing
- Location
- MADAN MOHAN MALAVIYA ROAD
- St. Pius Church Mulund West
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800024225
- ReraGenie IDRG-MH-27806
Builder
- NameALLIANCE CITY DEVELOPERS REALTORS PVT LTD
- Entity typeCompany
- CINU65990MH1993PTC075177
- GSTIN27AACCC0953F1ZY
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorSANKET DINESH LUHARUKA
- Other registrations15 more →
- Completed10 of 16
- Declared earlier projects12 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jan 2020
- Promised completion31 Jul 2024
- Revised completionNone
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMARDEEP ALLIANCE | NA | 20 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.
AMARDEEP ALLIANCE: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed73
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | THE DESIGN STUDIO |
| Engineer | FRAMES |
| Chartered Accountant | AKASH VIJAY AGARWAL |
| Partner | Role in project |
|---|---|
| ALLIANCE CITY DEVELOPERS REALTORS PVT LTD | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000261950 | Nitin Sharma | Alliance City Developers Realors Private Limited | 17/07/2022 |
| CC12503759 | Nitin Sharma | ALLIANCE CITY DEVELOPERS REALTORS PVT LTD | 27/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 22 Sep 2022
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 29 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf | 29 Sep 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf | 29 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amardeep Alliance - Form 1_compressed.pdf | 28 Sep 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate - Form 4.pdf | 28 Sep 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amardeep - Full OC.pdf | 22 Sep 2022 |
| CERSAI detailsFile: Cersai Amardeep Alliance.pdf | 28 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 17 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG.pdf | 17 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A.pdf | 17 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: DISC SOLD UNSOLD.pdf | 17 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 17 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Amar Saujanya.pdf | 6 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch.pdf | 14 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engform 2.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a.pdf | 14 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: sold unsold upload.pdf | 14 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca.pdf | 14 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Amardeep Alliance Full CC.pdf | 5 Aug 2021 |
| Declaration about Commencement CertificateFile: FORMAT D - CC Decleration.pdf | 5 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (30-6-2021) - Amar Saujanya (1).pdf | 31 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC LATEST.pdf | 23 Jul 2021 |
| Declaration about Commencement CertificateFile: FORMAT D - CC Decleration.pdf | 23 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 22 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG.pdf | 22 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf | 22 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf | 22 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_compressed.pdf | 22 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 24 May 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG.pdf | 24 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: A.pdf | 1 Apr 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (2nd Withdrawl) - Amar Saujanya 20210322.pdf | 30 Mar 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate (2nd Withdrawl) - Amar Saujanya(24-03-2021).pdf | 30 Mar 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - Amar Saujanya_signed.pdf | 30 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - Amar Saujanya.pdf | 30 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1st Withdrawl) - Amar Saujanya.pdf | 8 Jul 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 RERA AMARDEEP.pdf | 23 Jan 2020 |
| Proforma of Allotment letterFile: AMAR SAUJANYA - SALE DEED DRAFT.pdf | 23 Jan 2020 |
| Details of encumbrancesFile: Encumberances.pdf | 22 Jan 2020 |
| Declaration in FORM BFile: FORM B, DECLARATION (AMAR SAUJANYA).PDF | 22 Jan 2020 |
| Building plan approvalFile: IOD_signed.pdf | 18 Jan 2020 |
| Layout approvalFile: IOD-1- Signed Drawing.pdf | 18 Jan 2020 |
| PAN CardFile: PAN CARD.pdf | 18 Jan 2020 |
| Copy of the legal title reportFile: Title certificate.pdf | 18 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: IOD-1- Signed Drawing.pdf | 18 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD_signed.pdf | 18 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: 2239384_FirstCC_signed.pdf | 18 Jan 2020 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| ALLIANCE SAAWAIP51800047608 | MALAD WEST, Mumbai Suburban | 9 | Nov 2022 | Completed | Aug 2025 | Jan 2024 |
| NIRMAL MILANP51800029310 | VILE PARLE EAST, Mumbai Suburban | 33 | May 2021 | Completed | Nov 2024 | Apr 2023 |
| SWATI SADAN ALLIANCEP51800028825 | MULUND EAST, Mumbai Suburban | 22 | Mar 2021 | Completed | Aug 2024 | Jun 2023 |
| ALLIANCE RUIA SADANP51800028041 | MALAD WEST, Mumbai Suburban | 7 | Jan 2021 | Completed | Jun 2024 | Sep 2022 |
| ALLIANCE MATHURESHP51800025030 | MULUND WEST, Mumbai Suburban | 36 | Mar 2020 | Completed | Dec 2023 | Apr 2023 |
| ALLIANCE BHASKARP51800028213 | MALAD WEST, Mumbai Suburban | 26 | Feb 2021 | Completed | Dec 2023 | Aug 2022 |
| Alliance Ravi KiranP51800018068 | Mulund East, Mumbai Suburban | 24 | Oct 2018 | Completed | Oct 2022 | Oct 2022 |
| MANDAR PUSHPA CHSL | Mandar Pushpa CHSL Sant Dnyaneshwar Road Near Suyog Hall Mulund East Mumbai 400081 | 31 | - | Completed | Aug 2018 | Jul 2017 |
| Sudeep CHSL | Sudeep CHS Sant Dnyaneshwar Marg Opp Suyog Hall Mulund East Mumbai 400081 | 13 | - | Completed | Dec 2016 | Mar 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 15 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
Keep AMARDEEP ALLIANCE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near St. Pius Church Mulund West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 384 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: ALLIANCE CITY DEVELOPERS REALTORS PVT LTD
ALLIANCE CITY DEVELOPERS REALTORS PVT LTD has 16 registrations on MahaRERA, including Alliance Ravi Kiran and AMARDEEP ALLIANCE. Its filings disclose 12 earlier MahaRERA projects: declares 12 of 12 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if AMARDEEP ALLIANCE is delayed beyond 31 Jul 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMARDEEP ALLIANCE?
The registered promoter entity is ALLIANCE CITY DEVELOPERS REALTORS PVT LTD, a company as per the filing. Its CIN U65990MH1993PTC075177 and GSTIN 27AACCC0953F1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMARDEEP ALLIANCE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMARDEEP ALLIANCE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMARDEEP ALLIANCE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMARDEEP ALLIANCE?
The professionals named in the filing: Architect: THE DESIGN STUDIO; Engineer: FRAMES; Chartered Accountant: AKASH VIJAY AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMARDEEP ALLIANCE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback