Home / Developers / ALLIANCE CITY DEVELOPERS REALTORS PVT LTD
ALLIANCE CITY DEVELOPERS REALTORS PVT LTD: RERA track record
CIN U65990MH1993PTC075177 · GSTIN 27AACCC0953F1ZY · Company · attribution by exact filing name, entity resolution in progress
ALLIANCE CITY DEVELOPERS REALTORS PVT LTD has 16 registrations on MahaRERA, including Alliance Ravi Kiran and AMARDEEP ALLIANCE. Its filings disclose 12 earlier MahaRERA projects: declares 12 of 12 past projects completed on time.
Projects by this developer
Showing all 16 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| ALLIANCE KANCHAN KRUPAP51800077232 | MULUND WEST, Mumbai Suburban, 400080 | 78 | 24% | 31 Jul 2024 | Registered |
| ALLIANCE ABHIMANYUP51800052607 | MALAD WEST, Mumbai Suburban, 400064 | 61 | 41% | 11 Sep 2023 | Registered |
| ALLIANCE VISTAP51800076826 | VILE PARLE EAST, MUMBAI, Mumbai Suburban, 400057 | 26 | 31% | 28 Jun 2024 | Registered |
| ALLIANCE ETERNISP51800076690 | BORIVALI WEST, Mumbai Suburban, 400092 | 25 | 24% | 20 Jun 2024 | Completed |
| ALLIANCE SEA BREEZEP51800077565 | SANTACRUZ WEST, Mumbai Suburban, 400054 | 19 | 11% | 11 Oct 2024 | Registered |
| ALLIANCE HARMONYPR1170002600398 | WADALA WEST, Mumbai City, 400031 | 15 | 0% | 12 May 2026 | Registered |
| 22 ALLIANCE HOUSEPR1180002501852 | Vile Parle, Mumbai Suburban, 400057 | - | - | 23 Dec 2025 | Registered |
| ALLIANCE BHASKARP51800028213 | MALAD WEST, Mumbai Suburban, 400064 | - | - | 10 Feb 2021 | Completed |
| ALLIANCE LEGACYP51900035128 | MATUNGA ROAD, Mumbai City, 400019 | - | - | 10 May 2022 | Completed |
| ALLIANCE MATHURESHP51800025030 | MULUND WEST, Mumbai Suburban, 400080 | - | - | 18 Mar 2020 | Completed |
| Alliance Ravi KiranP51800018068 | Mulund East, Mumbai Suburban, 400081 | - | - | 10 Oct 2018 | Completed |
| ALLIANCE RUIA SADANP51800028041 | MALAD WEST, Mumbai Suburban, 400064 | - | - | 26 Jan 2021 | Completed |
| ALLIANCE SAAWAIP51800047608 | MALAD WEST, Mumbai Suburban, 400064 | - | - | 14 Nov 2022 | Completed |
| AMARDEEP ALLIANCEP51800024225 | St. Pius Church Mulund West, Mumbai Suburban, 400080 | - | - | 27 Jan 2020 | Completed |
| NIRMAL MILANP51800029310 | VILE PARLE EAST, Mumbai Suburban, 400057 | - | - | 18 May 2021 | Completed |
| SWATI SADAN ALLIANCEP51800028825 | MULUND EAST, Mumbai Suburban, 400081 | - | - | 30 Mar 2021 | Completed |
What this promoter declares as its own experience
ALLIANCE CITY DEVELOPERS REALTORS PVT LTD declares experience on 12 earlier projects. 8 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
8 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Sudeep CHSL | 17 Dec 2016 | 30 Mar 2016 | On time |
| sUDEEP chsl | 31 Dec 2016 | 30 Mar 2016 | On time |
| MANDAR PUSHPA CHSL | 16 Aug 2018 | 26 Jul 2017 | On time |
| MANDAR PUSHPA CHSL | 31 Oct 2018 | 26 Jul 2017 | On time |
| Alliance Ravi Kiran P51800018068 | 30 Oct 2022 | 21 Oct 2022 | On time |
| ALLIANCE MATHURESH P51800025030 | 30 Dec 2023 | 11 Apr 2023 | On time |
| ALLIANCE BHASKAR P51800028213 | 30 Dec 2023 | 22 Aug 2022 | On time |
| ALLIANCE RUIA SADAN P51800028041 | 30 Jun 2024 | 22 Sep 2022 | On time |
| AMARDEEP ALLIANCE P51800024225 | 31 Jul 2024 | 22 Sep 2022 | On time |
| SWATI SADAN ALLIANCE P51800028825 | 28 Aug 2024 | 13 Jun 2023 | On time |
| NIRMAL MILAN P51800029310 | 30 Nov 2024 | 21 Apr 2023 | On time |
| ALLIANCE SAAWAI P51800047608 | 30 Aug 2025 | 2 Jan 2024 | On time |
Frequently asked questions
How do I verify ALLIANCE CITY DEVELOPERS REALTORS PVT LTD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U65990MH1993PTC075177 and GSTIN 27AACCC0953F1ZY on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with ALLIANCE CITY DEVELOPERS REALTORS PVT LTD?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.