Registration lapsed No litigation declared Residential / Group Housing project

addressOne - Phase 6

By Peninsula Land Limited

RG-MH-86293 · RERA P52100018788 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 31 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
80 of 110Construction stages doneacross 10 buildings; furthest along: Basement (if any), 0%
0 of 200Units unsoldnot recorded sold or booked
31Complaints at MahaRERAon this registration
Jump to the 174 documents Report an error

addressOne - Phase 6 is a Residential / Group Housing project by Peninsula Land Limited in Pune, Maharashtra, registered with MahaRERA as P52100018788 on 5 Dec 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 200 of the 200 units on this registration are recorded sold or booked, and 80 of 110 construction stages are filed complete. 31 complaints are on record with the regulator.

At a glance

Project

  • NameaddressOne - Phase 6
  • TypeResidential / Group Housing
  • Location
    • Off Mumbai Pune Expressway
    • Near MCA Stadium Gahunje Pune
    • Gahunje
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018788
  • ReraGenie IDRG-MH-86293

Builder

  • NamePeninsula Land Limited
  • Entity typeCompany
  • CINL17120MH1871PLC000005
  • GSTIN27AAACT5173A1ZN
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorMahesh Gupta
  • Other registrations16 more →
  • Completed8 of 17
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects12 →

Key dates

4 months past promisethis monthRegisteredDec 2018First promiseJun 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Dec 2018
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
  • Buildings10 building records
  • Documents filed174 files

Current status

100%200 of 200 units booked
100.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 66NA5520020
Building 67NA5520020
Building 68NA5520020
Building 69NA5520020
Building 70NA5520020
Building 71NA5520020
Building 72NA5520020
Building 73NA5520020
Building 77NA5520020
Building 78NA5520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

80 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Basement (if any), at 0%.

Building 6673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6773%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6873%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6973%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7073%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7773%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7873%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed450

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots450
Open Space450
BuildingOpen SpaceTotal
Building 664646
Building 674646
Building 684646
Building 694646
Building 704646
Building 714646
Building 724646
Building 734646
Building 774141
Building 784141

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,812 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI8857.0
Proposed, not sanctioned8,052 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch215 Free Press House Free Press Journal Marg Nariman Point Mumbai 400021
Estimated costRs 19.07 cr
Cost incurredRs 19.07 cr
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 3.55 crRs 3.55 cr
Building 77NARs 2.00 crRs 2.00 cr
Building 78NARs 2.00 crRs 2.00 cr
Building 66NARs 1.59 crRs 1.59 cr
Building 67NARs 1.59 crRs 1.59 cr
Building 68NARs 1.59 crRs 1.59 cr
Building 69NARs 1.59 crRs 1.59 cr
Building 70NARs 1.29 crRs 1.29 cr
Building 71NARs 1.29 crRs 1.29 cr
Building 72NARs 1.29 crRs 1.29 cr
Building 73NARs 1.29 crRs 1.29 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJagadish Deshpande
ArchitectMahesh D Vanja
EngineerAchyut Watve
EngineerJ W Consultants LLP
EngineerPankaj Lingot
Chartered AccountantOmprakash Kedia & Co.
PartnerRole in project
Peninsula Land Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024078Jun 2024 → Jun 2025

Reason as filed by the promotera) The said Project is a part of the larger layout/phase-wise development having phases 1-6. The original amended Environmental Clearance for larger layout including the Phase 6 was obtained on 10/01/2019. However, due to the impact of the COVID-19 pandemic, subsequent permissions for all the phases were significantly delayed. As a result, the revalidation of consent to operate permission could only be obtained in May 2022 for phase 1 to 4. Therefore, the consent to operate for the remaining phases i.e. Phase 5 and phase 6 experienced a delay. b) The Vendor- M/s Tricon Infra Buidtech Pvt. Ltd,

EA10112518294Jun 2024 → Jun 2026

Reason as filed by the promoterIn Project Certificate No. P52100018788 and Extension Application No. EA10112518294 , application is filed under Section 7(3) of the MahaRERA Act, read with Order No. 40 of 2022. Please find attached herewith the Order passed by the Hon. Chairperson, MahaRERA, granting extension from 01.07.2025 to 30.06.2026, vide Order Regulatory Case No. 432 of 2025, in respect of addressOne Phase 6. The same is enclosed at Sr. No. 10 for your reference. we have uploaded the QPR upto December 2025 in the system.

Complaints filed with MahaRERA31

Case no.ComplainantRespondentFiled
CC005000000238659Peninsula Land LimitedMr Prasad Sali07/04/2023
CC005000000238661Peninsula Land LimitedSantosh Ramrao Jadhav07/04/2023
CC005000000238662Peninsula Land LimitedMr Krishna Sudam Sapkal07/04/2023
CC005000000238673Peninsula Land LimitedKunal Subhash Alurkar21/04/2023
CC005000000238740Peninsula Land LimitedAmbarish Kumar21/04/2023
CC005000000248782Peninsula Land LimitedVikas Namdev Gaikwad27/04/2023
CC12500180Chaitanya BayasPeninsula Land Limited19/01/2025
CC12603493Ashutosh SinghPeninsula Land Limited06/06/2026
CC12503098Amol Ashok BhadulePeninsula Land Limited03/09/2025
CC12503100Shweta Amol BhadulePeninsula Land Limited03/09/2025
CC12503365Dnyaneshwar Vasant MaindadPeninsula Land Limited21/09/2025
CC12503647prasad balasaheb talekarPeninsula Land Limited14/10/2025
CC12504296YASHASWI SUSHESH PATELPeninsula Land Limited05/12/2025
CC12601457madhavi mansing labadePeninsula Land Limited16/03/2026
CC12602150Rajesh Ramdev UpadhayayPeninsula Land Limited11/04/2026
CC12602895RAJESH SAMPAT RAJGURUPeninsula Land Limited17/05/2026
CC12602573Kundan Vijay PhalakPeninsula Land Limited02/05/2026
CC12602634Guruling Ravindra ChoudhariPeninsula Land Limited06/05/2026
CC12604887laxman ashok dahibhatePeninsula Land Limited02/08/2026
CC12604897Khashaba Shamrao PawarPeninsula Land Limited03/08/2026
CC12604892Prathamesh BandekarPeninsula Land Limited02/08/2026
CC12604901Vitthal Shamrao SalunkhePeninsula Land Limited03/08/2026
CC12604903Dhanashri Umesh PhadtarePeninsula Land Limited03/08/2026
CC12604919Akash Sitaram JadhavPeninsula Land Limited03/08/2026
CC12604935sanket sanjay jainPeninsula Land Limited04/08/2026
CC12604979Korak DavidPeninsula Land Limited05/08/2026
CC12604956priyanka prasad talekarPeninsula Land Limited05/08/2026
CC12604973Anand Madhavrao BhosagePeninsula Land Limited05/08/2026
CC12605073Rahul Nagappa PatrikePeninsula Land Limited09/08/2026
CC12605001Manoj Ganpat YadavPeninsula Land Limited06/08/2026
CC12605083GIRISH JAYAWANTRO CHAVANPeninsula Land Limited09/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed174

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architects Certificate addressOne Phase 6 June 2026 Q1.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 RERA Engg Certificate addressOne Phase 6 June 2026 Q1.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3 addressOne PHASE 6 JUNE 2026 Q1.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A addrressOne Phase 6 Quality Enginer Certificatemarch 2026.pdf1 Jul 2026
Withdrawal Update Form 1File: Architects Certificate addressOne Phase 6 30092025.pdf24 Apr 2026
Withdrawal Update Form 1File: Architects Certificate addressOne Phase 6 30092025.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 December 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Gahunje addressOne Phase 6 March 2026.pdf24 Apr 2026
Withdrawal Update Form 2File: Engineers Certificate addressone Phase 6 30092025.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineering Certificate addressone phase 6 Dec 25.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressOne P6 March 2026.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressone Phase 6 30092025.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE GAHUNJE PHASE 6 31 DEC 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 March 2026.pdf15 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Gahunje addressOne Phase 6 March 2026.pdf15 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressOne P6 March 2026.pdf15 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A addrressOne Phase 6 Quality Enginer Certificatemarch 2026.pdf13 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Gahunje addressOne Phase 6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Gahunje addressOne Phase 6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressOne P6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressOne P6 March 2026.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 December 2025.pdf6 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineering Certificate addressone phase 6 Dec 25.pdf6 Apr 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE GAHUNJE PHASE 6 31 DEC 2025.pdf6 Apr 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 December 2025.pdf23 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineering Certificate addressone phase 6 Dec 25.pdf23 Jan 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE GAHUNJE PHASE 6 31 DEC 2025.pdf23 Jan 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 December 2025.pdf9 Jan 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Gahunje addressOne Phase 6 December 2025.pdf9 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineering Certificate addressone phase 6 Dec 25.pdf9 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineering Certificate addressone phase 6 Dec 25.pdf9 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressone Phase 6 30092025.pdf9 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate addressone Phase 6 30092025.pdf9 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 addresseone Phase 6 Mar 2025.pdf10 Dec 2025
Withdrawal Update Form 1File: Architectu0027s Certificate addressOne Phase 6 30092025.pdf15 Oct 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate addressone Phase 6 30092025.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate addressone Phase 6 30092025.pdf15 Oct 2025
Withdrawal Update Form 1File: Architectu0027s Certificate addressOne Phase 6 30092025.pdf10 Oct 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate addressone Phase 6 30092025.pdf10 Oct 2025
Withdrawal Update Form 3File: FORM 3 -GAHUNJE PHASE 6 - SEP 24 03-10-2024.pdf10 Oct 2025
Form 1File: Architect's Certificate Gahunje addressOne Phase 6 June 2025.pdf10 Jul 2025
Form 2File: Engineer Certificate-Addressone-Phase6 June 2025.pdf10 Jul 2025
Form 3File: FORM 3 GAHUNJE PHASE 6 June 2025.pdf10 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold Investory addressOne p6 June 2025.pdf10 Jul 2025
CERSAI detailsFile: CERSAI_PLL_15042025.pdf15 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate Gahunje addressOne Phase 6.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate addressone phase 6 March 2025.pdf3 Apr 2025
Form 2AFile: From 2A Quality Assurance certificate addressone phase 6 March 2025.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2A Quality Assurance certificate addressone phase 6 March 2025.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 4 CA Certificate Dec 2024 addressone Phase 6.pdf10 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate Gahunje Phase 6 December 2024.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineering Certificate Dec 2024 addessone Phase 6.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Dec 2024 addressone 6.pdf6 Jan 2025
Certificates of CA (Form 3)File: FORM 3 -GAHUNJE PHASE 6 - SEP 24 03-10-2024 revised.pdf16 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate _ Gahunje Phase 6 September 2024.pdf8 Oct 2024
Certificates of CA (Form 3)File: FORM 3 -GAHUNJE PHASE 6 - SEP 24 03-10-2024.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate _ Gahunje Phase 6 30 Sept '24.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold unsold invertory addressOne Ph6 sept 2024.pdf8 Oct 2024
Declaration in FORM BFile: Declaration phase 6.pdf19 Jul 2024
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf19 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ADDRESSONE PHASE 6 FORM 5 M24.pdf16 Jul 2024
Certificates of CA (Form 3)File: FORM 3 GAHUNJE PHASE 6 MAR 24.pdf8 Jul 2024
Certificates of CA (Form 3)File: FORM 3 GAHUNJE PHASE 6 JUN 24.pdf8 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate _ Gahunje Phase 6 June 2024.pdf2 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Director Pankaj Kanodia.pdf2 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: addressOne Ph-06 Engineer Certificate Jun'24.pdf1 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about Separate Bank Account addressone phase 6.pdf1 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Director Urvi Piramal.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Addressone Ph06 QA Certificate March24.pdf27 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Deepak Summanwar.pdf26 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Mahesh Gupta.pdf26 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory - addressone Phase 6 june, 2024.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior 1.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior 2.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Pawan Swamy.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Krupal Kanakia.pdf25 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form No 1 for RERA Address One Phase 6.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 6 March 2024.pdf5 Apr 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
addressOne - Phase 1P52100015756Nr Maharashtra Cricket Association Stadium, Gahunje Pune, Pune254Mar 2018CompletedDec 2022Dec 2022
Ashok Astoria Phase IGat no 2 Govardhan Village Gangapur Road Nashik270-CompletedSep 2016Late, May 2017

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep addressOne - Phase 6 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near MCA Stadium Gahunje Pune13,700+ in Pune

2 kmaddressOne - Phase 6Completed 26Lapsed / revoked 18Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: Peninsula Land Limited

Peninsula Land Limited has 17 registrations on MahaRERA, including Celestia Spaces and addressOne - Phase 1. Its filings disclose 12 earlier MahaRERA projects: declares 7 of 11 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that addressOne - Phase 6 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if addressOne - Phase 6 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of addressOne - Phase 6?

The registered promoter entity is Peninsula Land Limited, a company as per the filing. Its CIN L17120MH1871PLC000005 and GSTIN 27AAACT5173A1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in addressOne - Phase 6?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against addressOne - Phase 6?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for addressOne - Phase 6?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at addressOne - Phase 6?

The professionals named in the filing: Architect: Jagadish Deshpande; Architect: Mahesh D Vanja; Engineer: Achyut Watve; Engineer: J W Consultants LLP; Engineer: Pankaj Lingot; Chartered Accountant: Omprakash Kedia & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in addressOne - Phase 6?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About addressOne - Phase 6. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save addressOne - Phase 6 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.