ReraGenieLog inGet a buyer report

Home / Developers / Peninsula Land Limited

Peninsula Land Limited: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Peninsula Land Limited has 17 registrations in this build, including Celestia Spaces and addressOne - Phase 1. Its filings disclose 12 earlier MahaRERA projects: 7 of 11 past projects completed on time.

17Registrations in this build
12Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Celestia SpacesMaharashtra--Registration lapsed
addressOne - Phase 1Pune, Maharashtra25499%Completed
addressOne - Phase 2Pune, Maharashtra--Completed
addressOne - Phase 3Pune, Maharashtra--Completed
addressOne - Phase 4Pune, Maharashtra--Completed
addressOne - Phase 5Pune, Maharashtra--Completed
addressOne - Phase 6Pune, Maharashtra200100%Registration lapsed
SERENITY at Ashok AstoriaNashik, Maharashtra--De-registered
Peninsula AshokVann Phase 1Pune, Maharashtra13987%Completed
Peninsula AshokVann Phase 2Pune, Maharashtra11677%Completed
Peninsula AshokVann Phase 3Pune, Maharashtra6676%Completed
Peninsula Centre Commercial Building Shopping ComplexPune, Maharashtra52100%Registered
AshokVistas by Peninsula Land - Phase 2Pune, Maharashtra--Registered
AshokVistas by Peninsula Land Phase 1Pune, Maharashtra--Registered
Peninsula PlazaPune, Maharashtra4865%Registered
Ashok Villas ImperialPune, Maharashtra80%Registered
Ashok Villas GrandePune, Maharashtra110%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Peninsula Business Park
30 Oct 201212 Feb 2013+3 months
Ashok Astoria Phase 1
30 Sep 201618 May 2017+8 months
Ashok Astoria Phase I
30 Sep 201618 May 2017+8 months
Ashok Astoria Phase 1
30 Sep 201618 May 2017+8 months
addressOne - Phase 1
P52100015756
30 Dec 202230 Dec 2022On time
addressOne Phase 1
30 Dec 202230 Dec 2022On time
addressOne - Phase 2
P52100015747
30 Apr 2023Not completed yetCertificate Signed
addressOne - Phase 3
P52100015779
30 May 202330 May 2023On time
Peninsula AshokVann Phase 1
P52100046962
30 Jun 202330 Jun 2023On time
addressOne - Phase 4
P52100015803
28 Aug 202328 Aug 2023On time
Peninsula AshokVann Phase 2
P52100046842
30 Apr 202430 Apr 2024On time
Peninsula AshokVann Phase 3
P52100046963
30 Jun 202430 Jun 2024On time

Frequently asked questions

How do I verify Peninsula Land Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Peninsula Land Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.