Home / Browse projects / Pune, Maharashtra / addressOne - Phase 5

Completed No litigation declared Residential / Group Housing project

addressOne - Phase 5

By Peninsula Land Limited

RG-MH-60066 · RERA P52100018855 · Last updated on MahaRERA portal: 27 Nov 2024

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • 1 extension taken

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
144 of 176Construction stages doneacross 16 buildings; furthest along: Podiums (if any), 0%
5Complaints at MahaRERAon this registration
Jump to the 130 documents Report an error

addressOne - Phase 5 is a Residential / Group Housing project by Peninsula Land Limited in Pune, Maharashtra, registered with MahaRERA as P52100018855 on 6 Dec 2018. The registration is recorded completed; possession was promised by 30 Dec 2023. 5 complaints are on record with the regulator.

At a glance

Project

  • NameaddressOne - Phase 5
  • TypeResidential / Group Housing
  • Location
    • Off Mumbai Pune Expressway
    • Near MCA Stadium Gahunje Pune
    • Gahunje
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018855
  • ReraGenie IDRG-MH-60066

Builder

  • NamePeninsula Land Limited
  • Entity typeCompany
  • CINL17120MH1871PLC000005
  • GSTIN27AAACT5173A1ZN
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorMahesh Gupta
  • Other registrations16 more →
  • Completed8 of 17
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects12 →

Key dates

this monthRegisteredDec 2018PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Dec 2018
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings16 building records
  • Documents filed130 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 53NA50000
Building 54NA50000
Building 55NA50000
Building 56NA50000
Building 57NA50000
Building 58NA50000
Building 59NA50000
Building 60NA50000
Building 61NA50000
Building 62NA50000
Building 63NA50000
Building 64NA50000
Building 65NA50000
Building 74NA50000
Building 75NA50000
Building 76NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building16

As on 27 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

144 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Podiums (if any), at 0%.

Building 5382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Open Space33
BuildingOpen SpaceTotal
Building 741111
Building 751111
Building 761111

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,723 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI15993.0
Proposed, not sanctioned14,539 sq m
Buildings approved16
Buildings sanctioned16

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch215 Free Press House Free Press Journal Marg Nariman Point Mumbai 400021

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJagadish Deshpande
ArchitectMahesh D Vanja
EngineerAchyut Watve
EngineerJ W Consultants LLP
Chartered AccountantOmprakash Kedia & Co.
PartnerRole in project
Peninsula Land Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018361Dec 2023 → Dec 2024

Reason as filed by the promotera) The said Project viz. phase 5 is a part of the larger layout/phase-wise development having phase 1-6. The original amended Environmental Clearance for larger layout including the said Phase was obtained on 10/01/2019. However, due to the impact of the COVID-19 pandemic, subsequent permissions for all the phases were significantly delayed. As a result, the revalidation of consent to operate permission could only be obtained in May 2022 for phase 1 to 4. Therefore, the consent to operate for the remaining phases viz the said Project and phase 6, experienced a delay. b) Further, the Vendor- M/

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000258843Peninsula Land LimitedMr. Dhiraj Jopat11/05/2023
CC005000000258948Peninsula Land LimitedRekha Prakash Gaikwad26/06/2023
CC12400383Swati PugaliaPeninsula Land Limited10/10/2024
CC12500404MANE AMBADAS PANDURANGPeninsula Land Limited06/02/2025
CC12504560Bhushan Satish KulkarniPeninsula Land Limited21/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Oct 2024

Documents filed130

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architects Certificate Phase 5 091024 revised.pdf27 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architects Certificate Phase 5 091024 revised.pdf22 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architects Certificate Phase 5 09 10 2024.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold unsold invertory addressOne Ph5 sept 2024.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate _ Gahunje Phase 5 September 2024.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate _ Gahunje Phase5 30 Sept '24.pdf6 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate - Phase V.pdf6 Oct 2024
Certificates of CA (Form 3)File: FORM 3 GAHUNJE PHASE 5 MAR 24.pdf8 Jul 2024
Certificates of CA (Form 3)File: FORM 3 GAHUNJE PHASE 5 JUN 24.pdf8 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate _ Gahunje Phase 5 June 2024.pdf2 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Director Pankaj Kanodia.pdf2 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: addressOne Ph-05 Engineer Certificate Jun'24.pdf1 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Director Urvi Piramal.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Addressone Ph05 QA Certificate March24.pdf27 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Deepak Summanwar.pdf26 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Mahesh Gupta.pdf26 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory - addressone Phase 5 june, 2024.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior 1.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior 2.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Pawan Swamy.pdf25 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Directior Krupal Kanakia.pdf25 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 March 2024.pdf5 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Addressone Ph05 Engineer Certificate March24.pdf5 Apr 2024
Form 2AFile: Addressone Ph05 QA Certificate March24.pdf5 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory - addressone Phase 5.pdf5 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - addressone Phase 5.pdf16 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form No 1 for RERA Address One Phase 5.pdf8 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 addressOne Ph-05 Engineer Certificate Dec'23.pdf8 Jan 2024
Certificates of CA (Form 3)File: FORM 3 addressone PHASE 5 Dec 2023_compressed.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold unsold inveatory - Phase 5_compressed.pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 PHASE 5 ADDONE M23.pdf29 Dec 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate - Phase 5 dec 2023.pdf22 Dec 2023
Details of encumbrancesFile: Encumbrance Certificate - Phase 5 dec 2023.pdf22 Dec 2023
Details of encumbrances concerned to LegalFile: Encumbrance Certificate - Phase 5 dec 2023.pdf22 Dec 2023
Declaration in FORM BFile: Declaration (form B) Phase dec 2023.pdf22 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Addressone Ph-05 QA Certificate March '23.pdf31 Oct 2023
CERSAI detailsFile: PLL CERSAI_Search_Report_06-10-2023.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold unsold flat - Phase V.pdf9 Oct 2023
Certificates of CA (Form 3)File: FORM 3 -GAHUNJE PHASE 5 - SEP 23_06 10 23_compressed.pdf9 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Addressone Phase 5 for RERA.PDF7 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Addressone Phase 5 Engg Certificate Sept '23.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold unsold flat - Phase V.pdf24 Jul 2023
Certificates of CA (Form 3)File: FORM 3 GAHUNJE PHASE 5 30th June 2023.pdf7 Jul 2023
Certificates of CA (Form 3)File: FORM 3 ADDRESSONE PHASE 5.pdf7 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Arch Certificate - Addressone Ph05 June 23.pdf6 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Addressone Ph-05 Engineer Certificate Jun'23.pdf4 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate addressOne Phase 5 March 2023.pdf10 May 2023
CERSAI detailsFile: PLL CERSAI Search Report 190423.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Addressone Ph-05 Engineer Certificate March '23.pdf10 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Addressone Ph-05 QA Certificate March '23.pdf10 Apr 2023
Certificates of CA (Form 3)File: AddressOne RERA FORM 3 Phase 5_compressed.pdf7 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold flats Phase 5 310323.pdf5 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Gahunje Phase 5 December 2022 page 1 to 8.pdf6 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Gahunje Phase 5 December 2022 page 9 to 15.pdf6 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Addressone phase 5 Engg Dec '22.pdf6 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Addressone phase 5 Quality assurance 20-21.pdf6 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Addressone phase 5 Quality assurance 21-22.pdf6 Jan 2023
Certificates of CA (Form 3)File: AddressOne - Phase 5 Dec 22 compressed.pdf6 Jan 2023
PAN CardFile: 1 PAN Card - Peninsula.pdf28 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form_5_Mar_2019_Address One Phase 5.pdf28 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Addressone Form 5 - Phase 5.pdf23 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 September 2022 page 1 to 8.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 September 2022 page 9 to 15_compressed.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_Addressone Phase 5.pdf7 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA Certificate_Addressone Phase 5.pdf7 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report - Sept 2022.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: RERA upload_addressOne_ -Phase 5.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3 Addressone Phase 5_compressed_compressed.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 June 2022 page 1 to 8.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 June 2022 page 9 to 15_compressed.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Phase 5.pdf7 Jul 2022
Form 2AFile: Quality Assurance_Phase 5.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: RERA upload_addressOne_June'22 -phase 5.pdf7 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200241606249_For_Debtor_Based_Search_06_07_2022_20_09_57_582.pdf7 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2020 P5_compressed.pdf7 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2021 P5_compressed.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 March 2022 page 1 to 8.pdf7 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Gahunje Phase 5 March 2022 page 9 to 15_compressed.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer's Addressone Phase 5 (Mar'22).pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA Quality Assurance Addressone Phase 5 (Mar'22).pdf7 Apr 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
addressOne - Phase 1P52100015756Nr Maharashtra Cricket Association Stadium, Gahunje Pune, Pune254Mar 2018CompletedDec 2022Dec 2022
Ashok Astoria Phase IGat no 2 Govardhan Village Gangapur Road Nashik270-CompletedSep 2016Late, May 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep addressOne - Phase 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near MCA Stadium Gahunje Pune13,700+ in Pune

2 kmaddressOne - Phase 5Completed 25Lapsed / revoked 19Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: Peninsula Land Limited

Peninsula Land Limited has 17 registrations on MahaRERA, including Celestia Spaces and addressOne - Phase 1. Its filings disclose 12 earlier MahaRERA projects: declares 7 of 11 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if addressOne - Phase 5 is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of addressOne - Phase 5?

The registered promoter entity is Peninsula Land Limited, a company as per the filing. Its CIN L17120MH1871PLC000005 and GSTIN 27AAACT5173A1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in addressOne - Phase 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against addressOne - Phase 5?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for addressOne - Phase 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at addressOne - Phase 5?

The professionals named in the filing: Architect: Jagadish Deshpande; Architect: Mahesh D Vanja; Engineer: Achyut Watve; Engineer: J W Consultants LLP; Chartered Accountant: Omprakash Kedia & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in addressOne - Phase 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About addressOne - Phase 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save addressOne - Phase 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.