Home / Browse projects / Mumbai Suburban, Maharashtra / 71 Midtown

Registered No litigation declared Others project

71 Midtown

By Paradigm Dotom Buildheights LLP

RG-MH-29502 · RERA P51800028761 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • 8 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 100.00 crore secured on the land, in favour of Mitcon Credentia Trusteeship Service Limited

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
4 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 80%
8Complaints at MahaRERAon this registration
Jump to the 116 documents Report an error

71 Midtown is a Others project by Paradigm Dotom Buildheights LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028761 on 30 Mar 2021. Possession is promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 8 complaints are on record with the regulator.

At a glance

Project

  • Name71 Midtown
  • TypeOthers
  • Location
    • Opposite Sindhi Society
    • Lal Donger
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800028761
  • ReraGenie IDRG-MH-29502

Builder

  • NameParadigm Dotom Buildheights LLP
  • Entity typeOthers
  • Named personsPPMS Real Estates LLP, DOTOM BUILDTECH LLP
  • Declared earlier projects3 →

Key dates

this monthRegisteredMar 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Mar 2021
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2025)
  • Buildings3 building records
  • Documents filed116 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sale Tower 1NA2825000
Sale Tower 2NA2920000
Sale Tower 3NA2825000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 80%.

Sale Tower 122%
ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Sale Tower 237%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Sale Tower 30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed240

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots240
Closed/Covered240
BuildingClosed/CoveredTotal
Sale Tower 18080
Sale Tower 28080
Sale Tower 38080

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,124 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofMitcon Credentia Trusteeship Service Limited
Secured amountRs 100.00 crore
CERSAI search filedYes
Declared on7 Jul 2026
LandownerVillageDistrict
Jai Bhagwati Developers and Builders & R.K.MadhaniMumbai CityMumbai City

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI27288.0
Proposed, not sanctioned24,288 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSana Building Linking Road Santacruz west Mumbai 400054

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDOT Architects
ArchitectDevang Gandhi
EngineerFRAMES
Chartered AccountantNaveen Tripathi
Chartered AccountantMallawat & Associates
PartnerRole in project
Paradigm Dotom Buildheights LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024249Dec 2025 → Dec 2026

Reason as filed by the promoterWe, Paradigm Dotom Buildheights LLP, the Promoter of the project 71 Midtown (MahaRERA Registration No. P51800028761), registered on 30.03.2021, hereby submit our application under Section 6 of the Real Estate (Regulation and Development) Act, 2016, seeking an extension of time for the completion of the project, originally scheduled for 30-12-2025. The project is being executed under the Slum Rehabilitation Scheme and consists of two Rehab buildings and one Sale Building No. 1, comprising Sale Towers 1, 2, and 3 (Ground + 23 floors). Construction of Sale Towers 1 and 2 has progressed up to the

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000396727Ketaki SarmalkarParadigm Dotom19/02/2024
CC006000000480346Paradigm Dotom Buildheights LLPMr. Tushar D. Parulekar18/05/2024
CC006000000480348Paradigm Dotom Buildheights LLPMr. Ameya M Jadhav & Mrs. Namita A. Jadhav22/05/2024
CC12400861Ankita S RijhisinghaniParadigm Dotom Buildheights LLP23/11/2024
CC12400862Ankita S RijhisinghaniParadigm Dotom Buildheights LLP23/11/2024
CC12500189Paradigm Dotom Buildheights LLPMrs Damini Raj (respondent)20/01/2025
CC12501167Paradigm Dotom Buildheights LLPAJAY SINGH PAWAR and SIMARJIT KAUR PAWAR08/04/2025
CC12501168Paradigm Dotom Buildheights LLPANIKET VYANKATESH RANSUBHE AND UNNATI PURUSHOTTAM WORLIKAR08/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed116

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Midtown - Form 1 of June 2025.pdf24 Jun 2026
Form 2File: Form 2 - 71 Midtown as on June 2025.pdf24 Jun 2026
Form 3File: Form 3 - 71 Midtown June 25.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - 71 Midtown as on June 2025.pdf24 Jun 2026
Form 1File: Form 1 - 71 Midtown as on Sep 2025.pdf24 Jun 2026
Form 2File: Form 2 - 71 Midtown as on Sep 2025.pdf24 Jun 2026
Form 3File: Form 3 - 71 Midtown as on Sep 2025.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 -71 Midtown as on Sep 2025.pdf24 Jun 2026
Form 1File: Form 1 - 71 Midtown as on March 2026.pdf24 Jun 2026
Form 2File: Form 2 - 71 Midtown as on March 2026.pdf24 Jun 2026
Form 3File: Form 3 - 71 Midtown as on March 2026.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29- 71 Midtown as on March 2026.pdf24 Jun 2026
Form 1File: Form 1 - 71 Midtown as on Dec 2025.pdf24 Jun 2026
Form 2File: Form 2 - 71 Midtown as on Dec 2025.pdf24 Jun 2026
Form 3File: Form 3 - 71 Midtown as on Dec 2025_compressed.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - 71 Midtown as on Dec 2025.pdf24 Jun 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 MARCH 2025.pdf22 May 2025
March 202129 Apr 2025
June 202129 Apr 2025
Sept 202129 Apr 2025
Dec 202129 Apr 2025
March 202229 Apr 2025
June 202229 Apr 2025
Sept 202229 Apr 2025
Dec 202229 Apr 2025
March 202329 Apr 2025
June 202329 Apr 2025
Sept 202329 Apr 2025
December, 202329 Apr 2025
March 202429 Apr 2025
June 202429 Apr 2025
Sept 202429 Apr 2025
December 202429 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 22.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to March 23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 April to June 23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 July to Sept 23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to March 24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 April to June 24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 July to Sept 24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to March 25.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: 71 Midtwon sold unsold till March 2025.pdf18 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5 23-24.pdf11 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation Receipt.pdf9 Apr 2025
Declaration about Commencement CertificateFile: Declaration on CC dated 5 April 2025.pdf9 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Apr'22 to Mar'23.pdf9 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 Jun 23.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3 Sept 23.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 Dec 23.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 MAR 24.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 JUN 24.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 SEPT 24.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 DEC 24.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Midtwon sold unsold till Dec 2024.pdf6 Feb 2025
Disclosure of sold/ booked inventoryFile: Midtwon sold unsold till sept 2024.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown sold unsold till june 2024.pdf5 Aug 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown sold unsold inventory sept 2023.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown sold unsold - Dec 2023.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown sold unsold inventory Mar 2024.pdf5 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Midtown CC.pdf17 May 2024
Details of encumbrancesFile: PDBLLP - Details of Encumbrance - TATA.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown Sold Unsold till March 2023.pdf29 Feb 2024
Disclosure of sold/ booked inventoryFile: 71 Midtown Sold Unsold till 30th June 2023.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3.pdf15 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Form 5.pdf15 May 2023
CERSAI detailsFile: CHMUM00001514538-CERSAI_Search_Report_Security_Interest_Id_Based_Search_22_03_2023_14_09_027 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 71 Midtown - Signed RERA form 3 Till December 2022 (2).pdf27 Mar 2023
Proforma of Agreement for saleFile: V2 1 Applicant with All pages - PDLLP.pdf27 Mar 2023
Details of encumbrancesFile: 1469_001.pdf15 Mar 2023
Disclosure of sold/ booked inventoryFile: 71 Midtwon Sold Unsold Dec, 2022.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA Midtown sept 2022_compressed.pdf24 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed RERA Form 5 Certificate.pdf21 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate (Laldongar) September 2022_rotated.pdf10 Oct 2022
Disclosure of sold/ booked inventoryFile: Sold unsold midtown sept 2022.pdf10 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2171_001.pdf15 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2172_001.pdf15 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Upto December 2021 (1).pdf11 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3 (Jan to March 2022) (4).pdf11 Jul 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Paradigm AntalyaP51800020208Oshiwara, Mumbai Suburban800Mar 2019OngoingDec 2036Not due yet
ANTALYAJOGESHWARI--OngoingDec 2036Not due yet

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 71 Midtown on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lal Donger6,700+ in Mumbai Suburban

2 km71 MidtownCompleted 141Lapsed / revoked 97Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 379 registered projects within 2 km.

Builder: Paradigm Dotom Buildheights LLP

Paradigm Dotom Buildheights LLP has 1 registration on MahaRERA, including 71 Midtown. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if 71 Midtown is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 71 Midtown?

The registered promoter entity is Paradigm Dotom Buildheights LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 71 Midtown?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against 71 Midtown?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for 71 Midtown?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 71 Midtown?

The professionals named in the filing: Architect: DOT Architects; Architect: Devang Gandhi; Engineer: FRAMES; Chartered Accountant: Naveen Tripathi; Chartered Accountant: Mallawat & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 71 Midtown?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 71 Midtown. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 71 Midtown to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.