Home / Browse projects / Pune, Maharashtra / 101
101
RG-MH-65774 · RERA PR1260002601573 · Last updated on MahaRERA portal: 29 Jun 2026
Source: official MahaRERA filing
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- All 3 earlier projects delivered on promise
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 12 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
101 is a Residential / Group Housing project by ARR Lifespace LLP in Pune, Maharashtra, registered with MahaRERA as PR1260002601573 on 18 Aug 2026. Possession is promised by 31 Dec 2031.
At a glance
Project
- Name101
- TypeResidential / Group Housing
- Location
- Gahunje
- Mawal
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1260002601573
- ReraGenie IDRG-MH-65774
Builder
- NameARR Lifespace LLP
- Entity typeLimited Liability Partnership
- LLPINAAZ-0729
- GSTIN27ABWFA5094P1ZD
- Track record3 past projects →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Aug 2026
- Promised completion31 Dec 2031
- Revised completionNone
- Buildings2 building records
- Documents filed12 files
Current status
Figures as on 29 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 16 | 12 | 24 | 0 | 24 |
| Building B | NA | 15 | 11 | 22 | 0 | 22 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
Building A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | Not applicable |
Parking filed394
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Basement | Total |
|---|---|---|
| Building A | 196 | 196 |
| Building B | 198 | 198 |
Land and ownership
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G M Architects |
| Chartered Accountant | CA Rinkesh Gupta |
| Partner | Role in project |
|---|---|
| ARR Lifespaces LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed12
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| Sanction plan-1_compressed | 29 Jun 2026 |
| Annexure A tech | 29 Jun 2026 |
| Sanction plan-3_compressed | 29 Jun 2026 |
| Sanction plan-4_compressed | 29 Jun 2026 |
| Sanction plan-2_compressed | 29 Jun 2026 |
| Sanction plan-5_compressed | 29 Jun 2026 |
| Sanction plan-6-11-1_compressed | 29 Jun 2026 |
| Sanction plan-6-11-2_compressed | 29 Jun 2026 |
| Sanction plan-6-11-3_compressed | 29 Jun 2026 |
| Sanction plan-6-11-4_compressed | 29 Jun 2026 |
| Sanction plan-6-11-5_compressed | 29 Jun 2026 |
| Sanction plan-6-11-6_compressed | 29 Jun 2026 |
Promoter's earlier projects3
As disclosed by the promoter in this filing.
| Project | Status | Promised | Delivered | Litigation |
|---|---|---|---|---|
| APNA MARKET | Certificate Signed | Dec 2026 | Jun 2026 | No |
| Courtyard 15 NXT Phase 1 | Certificate Signed | Dec 2028 | Jun 2026 | No |
| Courtyard 15 NXT Phase 2 | Certificate Signed | Dec 2030 | Jun 2026 | No |
How this compares with Pune
Computed across the 13,635 Pune projects on ReraGenie, from their own filings.
Track 101
Save this project to your account and get an email when its filing changes: status, dates, complaints, new documents. Free during the pilot beta.
Other projects near Gahunje13,635 in Pune
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: ARR Lifespace LLP
ARR Lifespace LLP has 1 registration on MahaRERA, including 101. Its filings disclose 3 earlier MahaRERA projects: 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if 101 is delayed beyond 31 Dec 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 101?
The registered promoter entity is ARR Lifespace LLP, a limited liability partnership as per the filing. Its LLPIN AAZ-0729 and GSTIN 27ABWFA5094P1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 101?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 101?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 101?
The professionals named in the filing: Architect: G M Architects; Chartered Accountant: CA Rinkesh Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 101?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback