Home / Browse projects / Mumbai Suburban, Maharashtra / ZYNERGY
ZYNERGY
RG-MH-25241 · RERA P51800007546 · Last updated on MahaRERA portal: 21 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 23 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 11 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ZYNERGY is a Others project by MAA ASHAPURA DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007546 on 17 Aug 2017. Possession was promised by 20 Nov 2024 and is now 23 months past that date. The completion date has moved by 11 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameZYNERGY
- TypeOthers
- Location
- Lal Dongar Road
- Lal Dongar
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007546
- ReraGenie IDRG-MH-25241
Builder
- NameMAA ASHAPURA DEVELOPERS
- Entity typePartnership
- PartnersBHAVIK LAHERIKANT BHADRA, HIMMAT SUNDARJI BHADRA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion20 Nov 2024
- Revised completionRevised to 20 Nov 2024 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed93 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ZYNERGY - F, G AND H WING | NA | 21 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 75%.
ZYNERGY - F, G AND H WING: 30% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 75% |
| Basement (if any) | 75% |
| Podiums (if any) | 0% |
| Plinth | 75% |
| Stilt Floor | 75% |
| Slabs of Super Structure | 24% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 5% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed181
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rajendra Ulhas Pagnis |
| Engineer | Mr. Niranjan Pandya |
| Partner | Role in project |
|---|---|
| MAA ASHAPURA DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid Pandemic the Construction work was stopped for a long while. we are on verge of Completion of Project kindly grant us Extension.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000193613 | Mr. Chaganty Vara Prasad Rao and Mrs. Chaganty Leela Meher | Maa Ashapura Developers | 07/08/2020 |
| CC006000000333808 | Neelam Swapnil Bane | M/s Maaa Ashapura Developers | 02/01/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Nov 2024
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC__Zynergy.pdf | 21 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC__Zynergy.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A RERA FY 2019-20 Q2.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A RERA FY 2019-20 Q3.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A RERA FY 2019-20 Q4.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A RERA FY 2020-21 Q2.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A RERA FY 2020-21 Q1.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A RERA FY 2020-21 Q3.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A RERA FY 2020-21 Q4.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A RERA FY 2020-21 Q1.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A RERA FY 2021-22 Q1.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A RERA FY 2021-22 Q2.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A RERA FY 2021-22 Q3.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A RERA FY 2022-23 Q2.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A RERA FY 2022-23 Q2.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A RERA FY 2022-23 Q3.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A RERA FY 2022-23 Q4.pdf | 27 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A RERA FY 2023-21 Q1.pdf | 27 Dec 2023 |
| Declaration in FORM BFile: Form B.pdf | 26 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: RERA Sold - Unsold_231226_142733.pdf | 26 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1_D_31-03-23_Annexure A Architect Certificate (1).pdf | 1 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1_D_30-06-23_Annexure A Architect Certificate (1).pdf | 1 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1_D_30-09-23_Annexure A Architect Certificate (1)_compressed.pdf | 1 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexure B -31-03-2023.pdf | 1 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Annexure C - 31-032023.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2018-19 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2019-20 Q1_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2019-20 Q2_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2019-20 Q3_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2019-20 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2020-21 Q1_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2020-21 Q2_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2020-21 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2020-21 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2021-22 Q1_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2021-22 Q3_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2021-22 Q3_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2021-22 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2022-23 Q1_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2022-23 Q2_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2022-23 Q3_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2022-23 Q4_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2023-24 Q1_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 RERA CA Certificate FY 2023-24 Q2_compressed.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 RERA CA Certificate FY 2018-19.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 RERA CA Certificate FY 2019-20.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 RERA CA Certificate FY 2020-21.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 RERA CA Certificate FY 2021-22.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 RERA CA Certificate FY 2022-23.pdf | 1 Dec 2023 |
| Details of encumbrancesFile: Encumberance Declaration.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Annexure A Architect certificate.pdf | 11 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31122022.pdf | 11 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31122022.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 7 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2.pdf | 7 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA Form 2A.pdf | 7 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 Annexure A Architect Certificate.pdf | 30 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexure B.pdf | 30 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30092021 FORM1 Annexure A Architect Certificate.pdf | 11 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 28022022 FORM1 Annexure A Architect Certificate.pdf | 11 Apr 2022 |
| Building plan approvalFile: APPROVED IOA.pdf | 5 Apr 2022 |
| Building plan approvalFile: AMENDED IOA.PDF | 5 Apr 2022 |
| Building Plan Approval (IOD)File: AMENDED IOA.PDF | 5 Apr 2022 |
| Building Plan Approval (IOD)File: APPROVED IOA.pdf | 5 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: AMENDED CC.pdf | 5 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexure B.PDF | 5 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Annexure C EC 21.PDF | 5 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Annexure C21.PDF | 5 Apr 2022 |
| Details of Restarting of Construction work post lockdownFile: REVISED LOI.pdf | 5 Apr 2022 |
| OtherFile: CIVIL AVIATION NOC.pdf | 5 Apr 2022 |
| Declaration about Commencement CertificateFile: Format - D - eclaration about Commencement Certificate.PDF | 30 Mar 2022 |
| Proforma of Allotment letterFile: Agreement For Sale_Zynergy.pdf | 30 Mar 2022 |
| Certificates of CA (Form 5)File: Form 5 for uploading.pdf | 12 Dec 2018 |
| Details of encumbrancesFile: To Whomsoever it may Concern.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BINDER.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: AGGREMENT DISCLOSER.pdf | 29 Jul 2017 |
| OtherFile: zynergy rera letter and proposed ioa application.pdf | 29 Jul 2017 |
| OtherFile: zynergy Certificate of Stabililty.pdf | 29 Jul 2017 |
| OtherFile: Zenergy proposed sale IOA 1.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ZYNERGY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Lal Dongar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 385 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: MAA ASHAPURA DEVELOPERS
MAA ASHAPURA DEVELOPERS has 1 registration on MahaRERA, including ZYNERGY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ZYNERGY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ZYNERGY is delayed beyond 20 Nov 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ZYNERGY?
The registered promoter entity is MAA ASHAPURA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ZYNERGY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ZYNERGY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ZYNERGY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ZYNERGY?
The professionals named in the filing: Architect: Rajendra Ulhas Pagnis; Engineer: Mr. Niranjan Pandya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ZYNERGY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback