YASHOMATI CHSL
RG-MH-15776 · RERA P51800023057 · Last updated on MahaRERA portal: 4 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
- Completion date moved by 40 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
YASHOMATI CHSL is a Residential / Group Housing project by SAMRAT ENTERPRISE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800023057 on 22 Nov 2019. Possession was promised by 30 Apr 2026 and is now 6 months past that date. The completion date has moved by 40 months from the original filing. 4 of the 9 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameYASHOMATI CHSL
- TypeResidential / Group Housing
- Location
- SAHAKAR NAGAR 1
- SHELL COLONY
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- RERA no.P51800023057
- ReraGenie IDRG-MH-15776
Builder
- NameSAMRAT ENTERPRISE
- Entity typePartnership
- PartnersDEEPAK VAZIR, JAGDISH SHAH
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Nov 2019
- Promised completion30 Apr 2026
- Revised completionRevised to 30 Apr 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed50 files
Current status
Figures as on 4 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| YASHOMATI CHSL | NA | 16 | 15 | 9 | 0 | 9 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
YASHOMATI CHSL: 92% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 4 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| YASHOMATI CHSL | NA | Rs 3.75 cr | Rs 1.80 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ELLORA CONSULTANTS |
| Engineer | SIHAVAT CONSULTANCY SERVICES |
| Chartered Accountant | JRSM & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SAMRAT ENTERPRISE | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir/Madam, We request you to extend the due date by further 12 months. We have attached herewith the consents obtained from the buyers for your kind perusal.
Reason as filed by the promoterDear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘YASHOMATI CHSL’ is registered on the MahaRERA webportal vide Registration Number: P51800023057. The registration certificate was issued for the period ending 30 December 2022 (A copy of the certificate is attached herewith as Annexure 1). With reference to the above, we would like to inform you that there has been delay in obtaining various permissions required to complete the building. The plans will have to be amended as per DCPR 2034. We request you to extend the project completion dat
Reason as filed by the promoterDear Sir, Please refer to the annexure
Reason as filed by the promoterDear Sir/Madam, We request you to extend the due date by further 6 months. We have attached herewith the consents obtained from the buyers for your kind perusal.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1033 OF 2013/2013 | HIGH COURT | The parties are in the process of filing consent terms to settle the case |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Sep 25.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2_sep 25.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_sep 25_updated.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1_Sep 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_sep 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_sep 25_updated.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_signed.pdf | 27 Nov 2025 |
| Withdrawal Update Form 1File: Form 1_signed.pdf | 27 Nov 2025 |
| Withdrawal Update Form 2File: Form 2_signed.pdf | 27 Nov 2025 |
| Withdrawal Update Form 2File: Form 2_signed.pdf | 27 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_sep 25.pdf | 27 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_sep 25.pdf | 27 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_signed_24-25_signed.pdf | 27 Nov 2025 |
| Other - TechnicalFile: List of activities.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dec 24_signed_updated.pdf | 5 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 5 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: disclosure sold unsold.pdf | 5 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_signed_23-24_signed.pdf | 5 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_23-24_signed.pdf | 5 Mar 2025 |
| Declaration in FORM BFile: Form B_SamratNEW.pdf | 18 Feb 2025 |
| CERSAI detailsFile: asset based cersai.pdf | 11 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dec 24_signed.pdf | 29 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 14 Jan 2025 |
| Declaration in FORM BFile: Affidavit_signed.pdf | 11 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_signed.pdf | 11 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_signed.pdf | 11 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_signed.pdf | 11 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure_sold and unsold_signed.pdf | 11 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_signed.pdf | 11 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 2A_signed.pdf | 11 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_22-23_signed.pdf | 11 Jan 2024 |
| Declaration about Commencement CertificateFile: cc declaration.pdf | 18 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a.pdf | 18 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a.pdf | 18 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: samrat disclosure.pdf | 18 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5_19-20_signed.pdf | 27 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_20-21_signed.pdf | 27 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_21-22_signed.pdf | 27 Feb 2023 |
| OtherFile: RPM_3.pdf | 18 Nov 2019 |
| Building plan approvalFile: IOD_compressed.pdf | 5 Nov 2019 |
| Layout approvalFile: Layout plan.pdf | 5 Nov 2019 |
| PAN CardFile: Samrat PAN.pdf | 5 Nov 2019 |
| Copy of the legal title reportFile: Title certificate-compressed.pdf | 5 Nov 2019 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 5 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: Layout plan.pdf | 5 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD_compressed.pdf | 5 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 5 Nov 2019 |
| Declaration in FORM BFile: FORM B (1)_compressed.pdf | 5 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OUTGOING PROJECT_compressed.pdf | 5 Nov 2019 |
| Proforma of Allotment letterFile: Draft Agreement.pdf | 5 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 50 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep YASHOMATI CHSL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHELL COLONY6,700+ in Mumbai Suburban
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SAMRAT ENTERPRISE
SAMRAT ENTERPRISE has 1 registration on MahaRERA, including YASHOMATI CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that YASHOMATI CHSL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if YASHOMATI CHSL is delayed beyond 30 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of YASHOMATI CHSL?
The registered promoter entity is SAMRAT ENTERPRISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in YASHOMATI CHSL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for YASHOMATI CHSL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at YASHOMATI CHSL?
The professionals named in the filing: Architect: ELLORA CONSULTANTS; Engineer: SIHAVAT CONSULTANCY SERVICES; Chartered Accountant: JRSM & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in YASHOMATI CHSL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback