Home / Browse projects / Pune, Maharashtra / Yashodham

Registered No litigation declared Residential / Group Housing project

Yashodham

By OM DEVELOPERS

RG-MH-89579 · RERA P52100050291 · Last updated on MahaRERA portal: 7 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 22 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 22 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 127 documents Report an error

Yashodham is a Residential / Group Housing project by OM DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100050291 on 1 Apr 2023. Possession is promised by 31 Oct 2026. The completion date has moved by 22 months from the original filing.

At a glance

Project

  • NameYashodham
  • TypeResidential / Group Housing
  • Location
    • Mhaske Vasti
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100050291
  • ReraGenie IDRG-MH-89579

Builder

  • NameOM DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAGFO4077P1ZK
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersNitin Balasaheb Deshmukh, VIKAS VISHNU KAPSE, YOGESH SUBHASH NALAWADE
  • Other registrations30 more →
  • Completed13 of 31
  • No longer live11 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects10 →

Key dates

this monthRegisteredApr 2023First promiseDec 2024Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Apr 2023
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed127 files

Current status

94.5%Work done, per cost certificate

Figures as on 7 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing BNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Wing B: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes85%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes95%

Parking filed362

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots362
Closed/Covered28
Open Space334

Land and ownership13

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,784 sq m
Land owned byThe promoter, with other names on the file
Named landowners13
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Apr 2026
LandownerVillageDistrict
Goroba Hanumant KolhePimpri Chinchawad (M Corp.)Pune
Rajaram Dnyanoba ShelkePune (M Corp.)Pune
Shivani Shashikant ShindePune (M Corp.)Pune
Dattatray Changdeo KakadKiwalePune
Ananta Vasantrao BodakeGahunjePune
Swapnja Ashok RajguruPune (M Corp.)Pune
Ashok Rajaram RajguruPune (M Corp.)Pune
Sharad Vaijnath PhulariPune (M Corp.)Pune
Arvind Vitthal MahajanPimpri Chinchawad (M Corp.)Pune
Sangita Jagdish PatilPune (M Corp.)Pune
Jagdish Ramdas PatilPune (M Corp.)Pune
Sanjay Damu PatilPune (M Corp.)Pune
Suresh Dnyaneshwar MorePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI2679.48
Proposed, not sanctioned2,679 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS 4565, FIRST FLOOR , ATHARV
Estimated costRs 9.08 cr
Cost incurredRs 8.58 cr
Work done94.49%
BuildingWingEstimatedIncurred
Wing BNARs 8.58 crRs 8.58 cr
-NARs 50.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectI P Associates
EngineerAshok Admane
Chartered AccountantAghav Wavhal & Associates
Chartered AccountantKailash R Mundada & Co
PartnerRole in project
OM DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027195Dec 2024 → Jun 2026

Reason as filed by the promoterDue to material shortages, labor shortages, and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still pending. However, sufficient funds are now available. We kindly request an extension for the project completion

EA13062621360Dec 2024 → Oct 2026

Reason as filed by the promoterThe project comprises Wing A and Wing B. At the time of registration, only Wing B was sanctioned and has since been completed, with the Occupancy Certificate obtained and possession handed over to all allottees. Subsequently, the necessary approvals for Wing A have been received, and additional time is required for its completion; accordingly, extension of the project registration up to 30.06.2028 is sought. Certain project details were incorrectly reflected during migration and a separate correction application will be filed. The present extension relates solely to Wing A and does not affect

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed127

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 01 B WING_OM DEVLOPERS_17_07_2026.pdf7 Aug 2026
Withdrawal Update Form 2File: FROM -2 B Wing.pdf7 Aug 2026
Withdrawal Update Form 3File: Signed Form 3.pdf7 Aug 2026
Withdrawal Update Form 1File: FROM -1 A and B WING.pdf12 Jun 2026
Withdrawal Update Form 2File: FROM -2 A and B WING.pdf12 Jun 2026
Withdrawal Update Form 3File: Signed Form 3.pdf12 Jun 2026
Form 2A (FY 2023-2024)File: FROM -2A 31-03-2024.pdf3 Apr 2026
Form 2A (FY 2024-2025)File: FROM -2A 31-03-2025.pdf3 Apr 2026
Form 2A (FY 2025-2026)File: FROM - 2A 31-03-2026.pdf3 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf3 Apr 2026
Withdrawal Update Form 1File: Form 1.PDF5 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf5 Mar 2026
Withdrawal Update Form 3File: Signed form 3.pdf5 Mar 2026
Withdrawal Update Form 1File: From - 1 wing AB.pdf8 Jan 2026
Withdrawal Update Form 2File: From 2 wing AB.pdf8 Jan 2026
Withdrawal Update Form 3File: Signed Form - 3 September25_compressed.pdf8 Jan 2026
Form 1File: From 1_A&B Wing_June'25.pdf2 Aug 2025
Form 2File: From 2_A&B Wing_June'25.pdf2 Aug 2025
Form 3File: Form 3_A&B Wing.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories_B Wing_June'25.pdf2 Aug 2025
Self-declaration of Quarterly ProgressFile: Self Declaration - A&B Wing.pdf2 Aug 2025
Withdrawal Update Form 1File: From 1_Au0026B Wing_Juneu002725.pdf2 Aug 2025
Withdrawal Update Form 2File: From 2_Au0026B Wing_Juneu002725.pdf2 Aug 2025
Withdrawal Update Form 3File: Form 3_Au0026B Wing.pdf2 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1_AB Wing_Mar'25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_AB wing_Mar'25_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2_AB Wing_Mar'25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventories_B Wing_Mar'25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA (1).pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30032024.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30062024.pdf1 Apr 2025
Other - TechnicalFile: A.pdf1 Apr 2025
Declaration in FORM BFile: form b.pdf31 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold - Unsold Inventories - AB Wing.pdf31 Mar 2025
Declaration in FORM BFile: Form B Declaration - AB wing (Landowner).pdf19 Feb 2025
Declaration in FORM BFile: Form B Declaration - AB wing (Partners).pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - AB.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 - Wing AB - July to Sep 24.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Wing AB - As on 30-6-24.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - CD.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - AB.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - AB.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera P52100050291.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - CD.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Rera P52100050291.pdf6 Feb 2025
Declaration in FORM BFile: Form B - AB Wing (Landowner's).pdf16 Jan 2025
Declaration in FORM BFile: Form B - AB Wing (Partner's).pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architecture certificate.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certifiacte comp.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - AB Wing Sept 24_compressed.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - AB Wing June 24_compressed.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca cert _compressed.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold - Unsold Sheet - wing B.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 AB Wing.pdf18 Oct 2024
CERSAI detailsFile: Sold Unsold Inventory.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A AB wings.pdf18 Oct 2024
Layout approvalFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Building plan approvalFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Layout approvalFile: HPSCANNER0219_11zon.pdf1 Apr 2024
Building plan approvalFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Copy of Layout Approval (in case of layout)File: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Copy of Layout Approval (in case of layout)File: HPSCANNER0219_11zon.pdf1 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 30-06-2023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 30-9-2023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AB 311223.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- 31-03-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-06-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-09-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AB 31-12-23.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 31-03-2023.pdf28 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1FORM 2A.pdf28 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - AB.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - As on 3_23.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - As on 6_23.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - As on 9_23.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 As on 3_23.pdf26 Feb 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 22 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yashodham on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

Builder: OM DEVELOPERS

OM DEVELOPERS has 31 registrations on MahaRERA, including Aashirwad Apartment and KULSWAMINI APARTMENT. Its filings disclose 10 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Yashodham is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yashodham?

The registered promoter entity is OM DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAGFO4077P1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yashodham?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yashodham?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yashodham?

The professionals named in the filing: Architect: I P Associates; Engineer: Ashok Admane; Chartered Accountant: Aghav Wavhal & Associates; Chartered Accountant: Kailash R Mundada & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yashodham?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yashodham. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yashodham to a free account