ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Yashodham

Registration lapsed No litigation declared Residential / Group Housing project

Yashodham

By OM DEVELOPERS

RG-MH-22206 · RERA P52100030672 · Last updated on MahaRERA portal: 4 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 9 months past the filed date
  • Completion date moved by 28 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2026Possession promised9 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
11 of 62Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 142 documents Report an error

Yashodham is a Residential / Group Housing project by OM DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100030672 on 8 Sep 2021. Possession was promised by 31 Jan 2026 and is now 9 months past that date. The completion date has moved by 28 months from the original filing. 51 of the 62 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.

At a glance

Project

  • NameYashodham
  • TypeResidential / Group Housing
  • Location
    • MHASKE VASTI
    • RAVET
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100030672
  • ReraGenie IDRG-MH-22206

Builder

  • NameOM DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAGFO4077P1ZK
  • PartnersNitin Balasaheb Deshmukh, VIKAS VISHNU KAPSE, YOGESH SUBHASH NALAWADE
  • Other registrations30 more →
  • Completed13 of 31
  • No longer live11 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects10 →

Key dates

9 months past promisethis monthRegisteredSep 2021First promiseSep 2023Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Sep 2021
  • Promised completion31 Jan 2026
  • Revised completionRevised to 31 Jan 2026 (originally 30 Sep 2023)
  • Buildings2 building records
  • Documents filed142 files

Current status

82%51 of 62 units booked
98.9%Work done, per cost certificate

Figures as on 4 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WINGNA12830030
D WINGNA10832032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

C WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes85%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntYes85%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes95%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
C WING11
D WING11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,776 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Sep 2024
LandownerVillageDistrict
OM DEVELOPERSPimpriPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI5763.3
Proposed, not sanctioned4,134 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS 4565, FIRST FLOOR, ARTHAV BUILDING, RATNDEEP COLONY, THERGAON, PUNE
Estimated costRs 27.59 cr
Cost incurredRs 27.29 cr
Work done98.91%
BuildingWingEstimatedIncurred
D WINGNARs 13.05 crRs 13.05 cr
C WINGNARs 13.04 crRs 13.04 cr
-NARs 1.50 crRs 1.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectI P Associates
EngineerAshok Admane
Chartered AccountantAghav Wavhal & Associates
Chartered AccountantKailash R Mundada & Co
PartnerRole in project
OM DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019278Sep 2023 → Sep 2024

Reason as filed by the promoterDue to some ancillary work is pending and time required for getting completion certificate from local authority. We would like to request you grant us extension for 6 months i.e up to 29.09.2024. We would like to further inform you that, we have already received partial completion certificate from local authority. Kindly grant us extension certificate and oblige.

EXT52100012178Sep 2023 → Mar 2024

Reason as filed by the promoterDue to revision of building plan from 6th to 8th floor. the project was not able to get completed in time. We would like to request you to further grant us extension for 6 months.

EXT52100024828Sep 2023 → Jan 2026

Reason as filed by the promoterReciave completion certificate D Wing(06/02/2024) Pending C Wing Work Due to material shortages,and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still pending. However, sufficient funds are now available. We kindly request an extension for the project completion

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Feb 2024

Documents filed142

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: From- 1 wing D AND C.pdf4 Jun 2026
Withdrawal Update Form 1File: From- 1 wing D and C.pdf4 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf4 Jun 2026
Withdrawal Update Form 2File: From 2 wing C and D.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3_CD Wing.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3_CD Wing.pdf4 Jun 2026
Withdrawal Update Form 1File: FORM 1 - 31-3-2023.pdf8 Jan 2026
Withdrawal Update Form 1File: FORM 1 - 31-3-2023.pdf8 Jan 2026
Withdrawal Update Form 1File: FORM 1 - 31-3-2023.pdf8 Jan 2026
Withdrawal Update Form 2File: From 2_CD Wing_June25.pdf8 Jan 2026
Withdrawal Update Form 2File: From 2_CD Wing_June25.pdf8 Jan 2026
Withdrawal Update Form 2File: From 2_CD Wing_June25.pdf8 Jan 2026
Withdrawal Update Form 3File: Form 3_CD Wing.pdf8 Jan 2026
Withdrawal Update Form 3File: Form 3_CD Wing.pdf8 Jan 2026
Withdrawal Update Form 3File: Form 3_CD Wing.pdf8 Jan 2026
Form 1File: From 1_C&D Wing_June'25.pdf2 Aug 2025
Form 2File: From 2_C&D Wing_June'25.pdf2 Aug 2025
Form 3File: Form 3_C&D Wing.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories_C &D Wing_June'25.pdf2 Aug 2025
Self-declaration of Quarterly ProgressFile: Self Declaration - C&D Wing.pdf2 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1_CD Wing_Mar'25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CD wing_Mar'25_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2_CD Wing_Mar'25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventories_C Wing_Mar'25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventories_D Wing_Mar'25.pdf19 Apr 2025
Details of encumbrances concerned to FinanceFile: Details of Encumbrances of Concern to Legal.pdf1 Apr 2025
Details of encumbrances concerned to FinanceFile: Financial Encumbrances.pdf1 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 3.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30062024 (D).pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122024 (D).pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30032024( C ).pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122024 ( c ).pdf1 Apr 2025
CERSAI detailsFile: Cersai Decleration.pdf1 Apr 2025
Details of encumbrances concerned to LegalFile: Details of Encumbrances of Concern to Legal.pdf1 Apr 2025
Details of encumbrances concerned to LegalFile: Financial Encumbrances.pdf1 Apr 2025
Other - TechnicalFile: ANNEXURE'A'.pdf1 Apr 2025
Declaration in FORM BFile: form b.pdf31 Mar 2025
Declaration in FORM BFile: Form B Declaration - CD wing Landowner.pdf19 Mar 2025
Declaration in FORM BFile: Form B Declaration - CD wing Partners.pdf19 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 march 2024.pdf19 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 june 24.pdf19 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 sept 2024_compressed.pdf19 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dec 24.pdf19 Mar 2025
Declaration in FORM BFile: Form B Declaration - CD wing Landowner.pdf12 Mar 2025
Declaration in FORM BFile: Form B Declaration - CD wing Partners.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - CD.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera no P52100030672_compressed.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - CD.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Rera No P52100030672.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architecture certificate.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C and D Draft Form 30-6-2024.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C and D Draft Form 30-09-2024.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 CD Wings.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A CD wings.pdf18 Oct 2024
Layout approvalFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Layout approvalFile: HPSCANNER0219_11zon.pdf1 Apr 2024
Building plan approvalFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Building plan approvalFile: HPSCANNER0219_11zon.pdf1 Apr 2024
Copy of Layout Approval (in case of layout)File: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Copy of Layout Approval (in case of layout)File: HPSCANNER0219_11zon.pdf1 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER0213 (1)_11zon.pdf1 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER0219_11zon.pdf1 Apr 2024
Declaration in FORM BFile: Declaration in FORM B Builder.pdf19 Mar 2024
Declaration in FORM BFile: Declaration in FORM B Landowner_11zon.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - CD Wing.pdf19 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf19 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30-6-2023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30-9-2023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31-12-2023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31-3-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 30-6-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 30-9-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 31-12-2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 31-03-2023.pdf28 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 31-12-2023.pdf28 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - CD.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - As on 31-3-23.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - As on 30-6-23.pdf26 Feb 2024

How this compares with Pune

82%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 28 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yashodham on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

Builder: OM DEVELOPERS

OM DEVELOPERS has 31 registrations on MahaRERA, including Aashirwad Apartment and KULSWAMINI APARTMENT. Its filings disclose 10 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Yashodham shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Yashodham is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yashodham?

The registered promoter entity is OM DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAGFO4077P1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yashodham?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yashodham?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yashodham?

The professionals named in the filing: Architect: I P Associates; Engineer: Ashok Admane; Chartered Accountant: Aghav Wavhal & Associates; Chartered Accountant: Kailash R Mundada & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yashodham?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yashodham. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yashodham to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.