ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / WHITE PRESTIGE

Registration lapsed No litigation declared Residential / Group Housing project

WHITE PRESTIGE

By DAGADE PATIL CONSTRUCTIONS

RG-MH-16664 · RERA P52100027935 · Last updated on MahaRERA portal: 8 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 0%
7 of 12Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

WHITE PRESTIGE is a Residential / Group Housing project by DAGADE PATIL CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100027935 on 21 Jan 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 36 months from the original filing. 5 of the 12 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameWHITE PRESTIGE
  • TypeResidential / Group Housing
  • Location
    • PUNE BANGLORE HIGHWAY
    • BANDHAN BK
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100027935
  • ReraGenie IDRG-MH-16664

Builder

  • NameDAGADE PATIL CONSTRUCTIONS
  • Entity typePartnership
  • PartnersSHRIKANT BALASAHEB DAGADE, ANIL TANAJI DAGADE

Key dates

4 months past promisethis monthRegisteredJan 2021First promiseJun 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 20 Jun 2023)
  • Buildings1 building record
  • Documents filed37 files

Current status

42%5 of 12 units booked

Figures as on 8 Jan 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WHITE PRESTIGENA6312012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

WHITE PRESTIGE: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered1
Open Space8

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area560 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Aug 2025

Approvals and building plan

Sanctioning authorityPMRDA Pune
Permissible FSI394.65
Proposed, not sanctioned395 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAVKAR AVENUE NEAR ADITYA SHAGUN MALL NDA ROAD BAVDHAN MAHARASHTRA PUNE 411021

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIINOD & ASSOCIATES
EngineerSHRIKANT BALASAHEB DAGADE
Chartered AccountantDEEPAK YEKHE
Chartered AccountantLaxmikant Shinde
PartnerRole in project
DAGADE PATIL CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025773Jun 2023 → Jun 2026

Reason as filed by the promoterFor PMRDA DP Plan Sanction

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400349Somanath Hindurao PawarDAGADE PATIL CONSTRUCTIONS05/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Dec about commencement certificate.pdf8 Jan 2025
Declaration in FORM BFile: Dagade Patil Form B.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dec 23.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Mar 24.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate June24.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sept 24.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 24.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 24.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dagade Form3 March 24.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 23.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 23.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 23.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 22.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 22.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 22.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dagade Engineer's Certificate Dec 23.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dagade Engineer's Certificate March24.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dagade Engineer's Certificate June 24.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dagade Engineer's Certificate Sept 24.pdf25 Dec 2024
Disclosure of sold/ booked inventoryFile: Dagade Patil Sold inventory.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality-23.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality-23.pdf25 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality-24.pdf25 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA COST SHEET.pdf29 Dec 2020
Proforma of Allotment letterFile: PROFORMA.pdf29 Dec 2020
Copy of the legal title reportFile: search report.pdf6 Dec 2020
Details of encumbrancesFile: ENCUMBRANCES.pdf6 Dec 2020
Layout approvalFile: BUSINESS LAYOUT AND BUILDING.pdf24 Sep 2020
Building plan approvalFile: BUSINESS LAYOUT AND BUILDING.pdf24 Sep 2020
PAN CardFile: PAN.pdf24 Sep 2020
Copy of Layout Approval (in case of layout)File: BUSINESS LAYOUT AND BUILDING.pdf24 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: BUSINESS LAYOUT AND BUILDING.pdf24 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT.pdf24 Sep 2020
Declaration in FORM BFile: shrikant dagade notary.pdf24 Sep 2020

How this compares with Pune

42%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WHITE PRESTIGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANDHAN BK13,700+ in Pune

Builder: DAGADE PATIL CONSTRUCTIONS

DAGADE PATIL CONSTRUCTIONS has 1 registration on MahaRERA, including WHITE PRESTIGE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that WHITE PRESTIGE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if WHITE PRESTIGE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WHITE PRESTIGE?

The registered promoter entity is DAGADE PATIL CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WHITE PRESTIGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against WHITE PRESTIGE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for WHITE PRESTIGE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WHITE PRESTIGE?

The professionals named in the filing: Architect: VIINOD & ASSOCIATES; Engineer: SHRIKANT BALASAHEB DAGADE; Chartered Accountant: DEEPAK YEKHE; Chartered Accountant: Laxmikant Shinde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WHITE PRESTIGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WHITE PRESTIGE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WHITE PRESTIGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.