Home / Browse projects / Palghar, Maharashtra / VRINDAVAN GARDEN
VRINDAVAN GARDEN
RG-MH-27801 · RERA P99000024184 · Last updated on MahaRERA portal: 25 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VRINDAVAN GARDEN is a Residential / Group Housing project by SAI DREAM HOMES DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000024184 on 24 Jan 2020. Possession is promised by 30 Jun 2027. 17 of the 55 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameVRINDAVAN GARDEN
- TypeResidential / Group Housing
- Location
- KELVE STATION ROAD
- KELVE ROAD
- Zanzroli
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000024184
- ReraGenie IDRG-MH-27801
Builder
- NameSAI DREAM HOMES DEVELOPERS
- Entity typePartnership
- GSTIN27AEAFS5371Q1ZD
- PartnersRAMREKHA PARASNATH PAL, ANIL RAJDEO PAL, DURGAPRASAD RAMCHANDRA YADAV, VINAY BHOLANATH SINGH, JAGWANTA JAGMOHAN PAL, OMPRAKASH RAMDULAR PAL, AMARSINGH RAMJEET PAL
- PartnerDILIP SANKATHA VISHWAKARMA
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jan 2020
- Promised completion30 Jun 2027
- Revised completionNone
- Buildings1 building record
- Documents filed61 files
Current status
Figures as on 25 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VRINDAVAN GARDEN, BUILDING NO 1, A WING, TYPE A1 | NA | 8 | 8 | 42 | 13 | 55 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
VRINDAVAN GARDEN, BUILDING NO 1, A WING, TYPE A1: 36% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| DILIP SANKATHA VISHWAKARMA | Vasai-Virar City (M Corp) | Palghar |
| ANIL RAJDEO PAL | Vasai-Virar City (M Corp) | Palghar |
| DURGAPRASAD RAMCHANDRA YADAV | Vasai-Virar City (M Corp) | Palghar |
| VINAY BHOLANATH SINGH | Vasai-Virar City (M Corp) | Palghar |
| RAMREKHA PARASNATH PAL | Vasai-Virar City (M Corp) | Palghar |
| JAGWANTA JAGMOHAN PAL | Vasai-Virar City (M Corp) | Palghar |
| OMPRAKASH RAMDULAR PAL | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RENDER POINT |
| Engineer | MESHRAM AND THUKRAL |
| Engineer | PRADEEP YADAV |
| Chartered Accountant | KANTHAWALA & CO |
| Chartered Accountant | CHANDAN KUMAR CHOUDHARY |
| Chartered Accountant | SANJEEV RAJARAM CHAUDHARY |
| Partner | Role in project |
|---|---|
| SAI DREAM HOMES DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed61
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: SAI DREAMS FORM2A VRINDAVAN 099000024184.pdf | 25 Mar 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 VRINDAVAN 24-25.pdf | 25 Mar 2026 |
| Form 1File: VG FORM 1 Q4.pdf | 18 Feb 2026 |
| Form 2File: VG FORM 2 Q4.pdf | 18 Feb 2026 |
| Form 3File: VG FORM 3 Q4 24-25.pdf | 18 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: VG SOLD UNSOLD Q 4.pdf | 18 Feb 2026 |
| Form 1File: VG FORM 1 Q1.pdf | 18 Feb 2026 |
| Form 2File: VG FORM 2 Q1.pdf | 18 Feb 2026 |
| Form 3File: VG FORM 3 Q1 25-26.pdf | 18 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: VG SOLD UNSOLD Q 1.pdf | 18 Feb 2026 |
| Form 1File: VG FORM 1 Q2.pdf | 18 Feb 2026 |
| Form 2File: VG FORM 2 Q2.pdf | 18 Feb 2026 |
| Form 3File: VG FORM 3 Q2 25-26.pdf | 18 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: VG SOLD UNSOLD Q 2.pdf | 18 Feb 2026 |
| Form 1File: VG FORM 1 Q3.pdf | 18 Feb 2026 |
| Form 2File: VG FORM 2 Q3.pdf | 18 Feb 2026 |
| Form 3File: VG FORM 3 Q3 25-26.pdf | 18 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: VG SOLD UNSOLD Q 3.pdf | 18 Feb 2026 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER ENTITY_11zon.pdf | 12 Mar 2024 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE_11zon_11zon.pdf | 12 Mar 2024 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 12 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 5 20-21.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf | 11 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPERATE BANK ACCOUNT.pdf | 11 Mar 2024 |
| Deviation Report with respect to Allotment letterFile: DEVIATION REPORT WITH ALLOTMENT LETTER.pdf | 11 Mar 2024 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT RERA AGREEMENT.pdf | 11 Mar 2024 |
| Other - TechnicalFile: DECLARATION CUM UNDERTAKING.pdf | 11 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: DECLARATION - ENCUMBRANCE- LEGAL.pdf | 29 Feb 2024 |
| Details of encumbrances concerned to LegalFile: DECLARATION - ENCUMBRANCE- LEGAL.pdf | 29 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH CERTIFICATE.pdf | 29 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGNIEER CERTIFICATE.pdf | 29 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE 21-22.pdf | 29 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE 22-23.pdf | 29 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF BOOKED SOLD AND UNSOLD.pdf | 29 Feb 2024 |
| CERSAI detailsFile: DECLARATION_ cersai.pdf | 29 Feb 2024 |
| Building plan approvalFile: REVISED BLUE PRINT VRINDAVAN.pdf | 5 Aug 2021 |
| Layout approvalFile: REVISED LAYOUT OF KELVE 7 FLOOR_2.pdf | 5 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: REVISED LAYOUT OF KELVE 7 FLOOR_2.pdf | 5 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: REVISED BLUE PRINT VRINDAVAN.pdf | 5 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: REVISED CC COMPRESSED.pdf | 5 Aug 2021 |
| Declaration about Commencement CertificateFile: CC DECLARATION VRINDAVAN GARDEN.pdf | 5 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY CERTIFICATE VRINDAVAN HEIGHTS.pdf | 5 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LIST VRINDAVAN.pdf | 5 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VRINDAVAN FORM 5 19-20.pdf | 5 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: VRINDAVAN FORM 5 20-21.pdf | 5 Aug 2021 |
| Layout approvalFile: LAYOUT PLAN GUT NO 148.pdf | 18 Jan 2020 |
| Building plan approvalFile: Blue Print VRINDAVAN GARDEN.pdf | 18 Jan 2020 |
| PAN CardFile: PAN CARD SAI DREAM HOMES DEVELOPERS_2.pdf | 18 Jan 2020 |
| Copy of the legal title reportFile: TITLE SEARCH DEVELOPER.pdf | 18 Jan 2020 |
| Details of encumbrancesFile: encumbrance VRINDAVAN garden DEVELOPERS.pdf | 18 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN GUT NO 148.pdf | 18 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Blue Print VRINDAVAN GARDEN.pdf | 18 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: NA AND CC ORDER.pdf | 18 Jan 2020 |
| Declaration in FORM BFile: FORM B COMPANY DEVELOPER.pdf | 18 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT certificate developers.pdf | 18 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A FORM 3 VRINDAVAN GARDEN.pdf | 18 Jan 2020 |
| Proforma of Allotment letterFile: Draft Sale Agreement and Allotment Letter-converted.pdf | 18 Jan 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 61 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VRINDAVAN GARDEN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KELVE ROAD3,200+ in Palghar
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: SAI DREAM HOMES DEVELOPERS
SAI DREAM HOMES DEVELOPERS has 2 registrations on MahaRERA, including VRINDAVAN GARDEN and MADHUBAN GARDEN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if VRINDAVAN GARDEN is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VRINDAVAN GARDEN?
The registered promoter entity is SAI DREAM HOMES DEVELOPERS, a partnership as per the filing. Its GSTIN 27AEAFS5371Q1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VRINDAVAN GARDEN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VRINDAVAN GARDEN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VRINDAVAN GARDEN?
The professionals named in the filing: Architect: RENDER POINT; Engineer: MESHRAM AND THUKRAL; Engineer: PRADEEP YADAV; Chartered Accountant: KANTHAWALA & CO; Chartered Accountant: CHANDAN KUMAR CHOUDHARY; Chartered Accountant: SANJEEV RAJARAM CHAUDHARY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VRINDAVAN GARDEN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback