ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / VRINDAVAN COMPLEX

Registration lapsed No litigation declared Others project

VRINDAVAN COMPLEX

By KRISHNARAJ DEVELOPERS

RG-MH-51614 · RERA P99000014497 · Last updated on MahaRERA portal: 25 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
0 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

VRINDAVAN COMPLEX is a Others project by KRISHNARAJ DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000014497 on 5 Dec 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVRINDAVAN COMPLEX
  • TypeOthers
  • Location
    • Village Mahim
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000014497
  • ReraGenie IDRG-MH-51614

Builder

  • NameKRISHNARAJ DEVELOPERS
  • Entity typePartnership
  • PartnersRANJITKUMAR REVASHANKAR SINGH, AKHILESH ABHAYRAJ SINGH, MANISH RAVJI SAIYA
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

40 months past promisethis monthRegisteredDec 2017First promiseJun 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Dec 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2022)
  • Buildings3 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VRINDAVAN ANA120000
VRINDAVAN BNA100000
VRINDAVAN CNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 25 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

VRINDAVAN A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VRINDAVAN B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VRINDAVAN C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered23
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
VRINDAVAN A7512
VRINDAVAN B5510
VRINDAVAN C111021

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,715 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4623.61
Proposed, not sanctioned4,624 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOLD NAGARDAS ROAD, ANDHERI EAST, MUMBAI 400069

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHANT P PATIL VASTUSHILP ASSOCIATES
EngineerYOGESH D VAJA DARSH CONSULT
PartnerRole in project
KRISHNARAJ DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000012083Jun 2022 → Jun 2023

Reason as filed by the promoterWe, hereby apply for extension u/s 6 of the registered project bearing vide no. P99000014497. Since due to covid-19 situation project got delayed by almost for 18 months. Hence we required further 1 year more to complete the project. But RERA registration is valid till 30/06/2022. Hence we humbly request to extend the validity by 1 year from 30/06/2022 to 30/06/2023. As per Query Raised we have uploaded all the details in documents upload window. Kindly process the application for extension at the earliest. Respected Sir, As per Query Raised we have uploaded Declaration letter in Form-D under

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Dec 2024

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf25 Apr 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 b no 1 and 2.pdf3 Dec 2024
OtherFile: form 4 b no 3.pdf3 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Building No 3 - OC.pdf3 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf15 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf15 Feb 2024
Declaration about Commencement CertificateFile: Form D.pdf17 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Building 3.pdf13 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate For Building 3.pdf13 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate For Building 2.pdf13 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate For Building 1.pdf13 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200239657162_For_Asset_Based_Search_14_06_2022_10_35_51_858.pdf13 Jul 2022
Disclosure of sold/ booked inventoryFile: Krd sold unsold.pdf13 Jul 2022
Certificates of CA (Form 3)File: Rera Form3.pdf13 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC for Building 1 AND 2.pdf13 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf22 Jun 2022
CERSAI detailsFile: Letter for CERSAI.pdf20 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19 Form 5.pdf17 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20 Form 5.pdf17 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 20-21 Form 5.pdf17 Jun 2022
Copy of the legal title reportFile: Title Certificate.pdf20 Jan 2022
Certificates of CA (Form 5)File: Form 5.pdf18 Feb 2019
OtherFile: Full page photo.pdf17 Oct 2018
OtherFile: Full page photo1.pdf17 Oct 2018
Proforma of Allotment letterFile: 8 Draft Allotment Letter.pdf30 Nov 2017
Building plan approvalFile: Building Layout.pdf29 Nov 2017
Layout approvalFile: Layout of Type A-compressed.pdf29 Nov 2017
Layout approvalFile: Layout of Type C-compressed.pdf29 Nov 2017
Layout approvalFile: Layout of Type D-compressed.pdf29 Nov 2017
PAN CardFile: Firm Pancard.pdf29 Nov 2017
Copy of the legal title reportFile: Title Clear Certificate.pdf29 Nov 2017
Details of encumbrancesFile: Encumbrances Letter.pdf29 Nov 2017
Copy of Layout Approval (in case of layout)File: Layout of Type A-compressed.pdf29 Nov 2017
Copy of Layout Approval (in case of layout)File: Layout of Type C-compressed.pdf29 Nov 2017
Copy of Layout Approval (in case of layout)File: Layout of Type D-compressed.pdf29 Nov 2017
Building Plan Approval (IOD)File: Building Layout.pdf29 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate part 1.pdf29 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate part 2.pdf29 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate part 3.pdf29 Nov 2017
Declaration in FORM BFile: Form B.pdf29 Nov 2017
Certificates of CA (Form 3)File: Ca Certificate.pdf29 Nov 2017
Proforma of Allotment letterFile: Draft Agreement for Sale.pdf29 Nov 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRINDAVAN COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Mahim3,200+ in Palghar

2 kmVRINDAVAN COMPLEXCompleted 28Lapsed / revoked 28Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: KRISHNARAJ DEVELOPERS

Krishnaraj Developers has 4 registrations on MahaRERA, including Nakshatra and Nakshatra. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that VRINDAVAN COMPLEX shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VRINDAVAN COMPLEX is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRINDAVAN COMPLEX?

The registered promoter entity is KRISHNARAJ DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRINDAVAN COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRINDAVAN COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRINDAVAN COMPLEX?

The professionals named in the filing: Architect: NISHANT P PATIL VASTUSHILP ASSOCIATES; Engineer: YOGESH D VAJA DARSH CONSULT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRINDAVAN COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRINDAVAN COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRINDAVAN COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.