VOSKI EMERALD II
By VOSKI GROUP
RG-MH-33969 · RERA P52100019268 · Last updated on MahaRERA portal: 30 Sep 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 50 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VOSKI EMERALD II is a Residential / Group Housing project by VOSKI GROUP in KHARADI, 411014, registered with MahaRERA as P52100019268 on 15 Jan 2019. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 50 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- NameVOSKI EMERALD II
- TypeResidential / Group Housing
- Location
- BORATE VASTI
- KHARADI
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019268
- ReraGenie IDRG-MH-33969
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Jan 2019
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 30 Oct 2020)
- Buildings1 building record
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VOSKI EMERALD II | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
VOSKI EMERALD II: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 30 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 20% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed27
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VOSKI GROUP | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANDAR MUSALE |
| Partner | Role in project |
|---|---|
| VOSKI GROUP | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis
Reason as filed by the promoterWe are facing a problem after COVID19 our Labours are going & coming back of COVID situation and we are getting vendors problem,material is not coming on time, so many vendors has shut his company. Our 8th floor is completed before two months only and our 9th & 10th floor is proposed as per plan & we are facing a plan sanction problem of 9th & 10th floor. Because of COVID situation. PMC Corporation officers are not available their, they are always saying today & tomorrow itself in COVID situation.
Reason as filed by the promoterWe are facing a problem after COVID19 our Labours are going & coming back of COVID situation and we are getting vendors problem,material is not coming on time, so many vendors has shut his company. Our 8th floor is completed before two months only and our 9th & 10th floor is proposed as per plan & we are facing a plan sanction problem of 9th & 10th floor. Because of COVID situation. PMC Corporation officers are not available their, they are always saying today & tomorrow itself in COVID situation.
Reason as filed by the promoter1) Due to the COVID-19 pandemic, the regular flow of work is hampered on account of the unavailability of labor on regular basis. 2) Unseasonal and heavy rain during odd months also impacted badly in our project construction phase. 3) The sales in the market was absolutely bad and hence we could not get enough business and fresh income to run the construction flow as per the schedule. 4) Most of our investors and directors faced issues in fund flow and hence even the additional fund pumping also faced tough scenario.
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502789 | Mohit Popat Kalokhe | VOSKI GROUP | 08/08/2025 |
| CC12503247 | Jignya Bimal Manek | VOSKI GROUP | 13/09/2025 |
| CC12503248 | Mohan Namdev Khatal | VOSKI GROUP | 13/09/2025 |
| CC12503249 | Tushar Gangadhar Tathe | VOSKI GROUP | 13/09/2025 |
| CC12504033 | Lt Bhavana M Bulani thro her legal heirs Mr Manoharlal H Bulani | VOSKI GROUP | 15/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Dec 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Dec 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 AR (3 files merged).pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 ENG (4 files merged).pdf | 30 Sep 2023 |
| Certificates of CA (Form 3)File: CA-1 (8 files merged).pdf | 30 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Adobe Scan 19 Jul 2023.pdf | 20 Jul 2023 |
| Declaration in FORM BFile: Form B.pdf | 3 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 3 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 3 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold - Booked.pdf | 3 Jul 2023 |
| Building plan approvalFile: Sanctioned Plan Floor 9 and 10.pdf | 12 Jan 2022 |
| Building Plan Approval (IOD)File: Sanctioned Plan Floor 9 and 10.pdf | 12 Jan 2022 |
| Declaration about Commencement CertificateFile: Form-D.pdf | 29 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: voski21.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226854617_For_Asset_Based_Search_29_12_2021_15_18_00_036.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226854641_For_Asset_Based_Search_29_12_2021_15_18_10_074.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226858785_For_Asset_Based_Search_29_12_2021_15_44_41_239.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226858946_For_Asset_Based_Search_29_12_2021_15_45_33_722.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859035_For_Asset_Based_Search_29_12_2021_15_46_08_622.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859117_For_Asset_Based_Search_29_12_2021_15_46_40_414.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859238_For_Asset_Based_Search_29_12_2021_15_47_26_288.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859279_For_Asset_Based_Search_29_12_2021_15_47_46_542.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859721_For_Asset_Based_Search_29_12_2021_15_50_42_824.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859768_For_Asset_Based_Search_29_12_2021_15_50_59_764.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859855_For_Asset_Based_Search_29_12_2021_15_51_26_306.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859925_For_Asset_Based_Search_29_12_2021_15_51_51_933.pdf | 29 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226859983_For_Asset_Based_Search_29_12_2021_15_52_14_660 (6 files | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 1 Other.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 2 Other.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 3 Other.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 4 Other.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 5 Other.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: 6 Other.pdf | 29 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: voski18.pdf | 29 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: voski18.pdf | 29 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Adobe Scan 29 Dec 2021.pdf | 29 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate - Form 2A-converted (1) new.pdf | 21 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate - Form 2A-converted (1) new.pdf | 21 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: book sold.pdf | 20 Sep 2021 |
| OtherFile: circular 28-1.pdf | 20 Sep 2021 |
| OtherFile: C- 28-2.pdf | 20 Sep 2021 |
| OtherFile: C- 28-3.pdf | 20 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: 29.pdf | 4 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: 29-1.pdf | 4 Sep 2021 |
| OtherFile: 32.pdf | 4 Sep 2021 |
| OtherFile: 28.pdf | 4 Sep 2021 |
| OtherFile: 28-1.pdf | 4 Sep 2021 |
| Declaration in FORM BFile: S22C-2140110102400-1.pdf | 10 Jan 2019 |
| Declaration in FORM BFile: S22C-2140110102500-2.pdf | 10 Jan 2019 |
| Building plan approvalFile: HPSC0360 BUILDING PLAN.pdf | 20 Dec 2018 |
| Building plan approvalFile: HPSC0361.pdf | 20 Dec 2018 |
| Building plan approvalFile: HPSC0363.pdf | 20 Dec 2018 |
| Building plan approvalFile: HPSC0365.pdf | 20 Dec 2018 |
| Layout approvalFile: LAYOUT.pdf | 20 Dec 2018 |
| PAN CardFile: 1545309295_tmp_IMG_0435-pan card.pdf | 20 Dec 2018 |
| Copy of the legal title reportFile: title report.pdf | 20 Dec 2018 |
| Details of encumbrancesFile: voski encumbrances.pdf | 20 Dec 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: HPSC0360 BUILDING PLAN.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: HPSC0361.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: HPSC0363.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: HPSC0365.pdf | 20 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: 1.pdf | 20 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: 2.pdf | 20 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VOSKI ARCHITECT CER.pdf | 20 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf | 20 Dec 2018 |
| Certificates of CA (Form 3)File: CA CERTI.pdf | 20 Dec 2018 |
| Proforma of Allotment letterFile: AGREEMENT TO SALE DRAFT VOSKI EMRELD.pdf | 20 Dec 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| VOSKI GROUP | PUNE | Completed | Apr 2015 | Late, Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VOSKI EMERALD II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHARADI
Filed coordinates, straight-line distance. 72 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: VOSKI GROUP
VOSKI GROUP has 2 registrations on MahaRERA, including VOSKI EMERALD and VOSKI EMERALD II. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that VOSKI EMERALD II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VOSKI EMERALD II is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VOSKI EMERALD II?
The registered promoter entity is VOSKI GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VOSKI EMERALD II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VOSKI EMERALD II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VOSKI EMERALD II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VOSKI EMERALD II?
The professionals named in the filing: Architect: MANDAR MUSALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VOSKI EMERALD II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback