Home / Browse projects / Pune, Maharashtra / VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)

Registration lapsed No litigation declared Residential / Group Housing project

VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)

By VIVANTA SPACES

RG-MH-10166 · RERA P52100001309 · Last updated on MahaRERA portal: 11 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
19 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 166 documents Report an error

VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) is a Residential / Group Housing project by VIVANTA SPACES in Pune, Maharashtra, registered with MahaRERA as P52100001309 on 27 Jul 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameVIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)
  • TypeResidential / Group Housing
  • Location
    • GAT NO 3440
    • 3444
    • 3445
    • Talegaon Dhamdhere
    • Shirur
    • Pune
    • 412208
  • Pincode412208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001309
  • ReraGenie IDRG-MH-10166

Builder

  • NameVIVANTA SPACES
  • Entity typePartnership
  • PartnerSudesh Harichand Aggarwal

Key dates

28 months past promisethis monthRegisteredJul 2017First promiseDec 2020Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jul 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Dec 2020)
  • Buildings3 building records
  • Documents filed166 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIVANTA SARTHAK BLDG A- RIDDHINA60000
BLDG B - ADITINA60000
BLDG C - SIDDHINA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

VIVANTA SARTHAK BLDG A- RIDDHI73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLDG B - ADITI42%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BLDG C - SIDDHI73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes30%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
VIVANTA SARTHAK BLDG A- RIDDHI11
BLDG B - ADITI11
BLDG C - SIDDHI11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,486 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
HARICHAND SHYAMLAL AGGARWALUNDRIPune

Approvals and building plan

Sanctioning authoritySUB DIVISIONAL OFFICER MAVAL
Permissible FSI3480.6
Proposed, not sanctioned3,481 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKONDHWA KHURD

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWAPNIL SHETH
PartnerRole in project
VIVANTA SPACES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008541Dec 2020 → Dec 2021

Reason as filed by the promoterDue to no sale & poor market condition we were unable to complete the project within the due time.

EXT52100011923Dec 2020 → Jun 2024

Reason as filed by the promoterAs we know Covid 19 has impacted all the sectors and real estate is not an exception from them. Many hurdles emerged with the beginning of the pandemic. We faced difficulty as there was a lack of essential raw material and unavailabiilty of manufacturing equipment has halted the construction activity. With imposition of international trade restrictions amid pandemic ,supply lines have been struck short and as a consequence inflation hit high and resulted in increasing the price of inputs required for project. As a result project under construction experienced a delay .So please grant us the re

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed166

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 166 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FOrm b.pdf11 Mar 2025
Certificates of CA (Form 3)File: Form 3 VivantaSarthak _ SEP 24.pdf27 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dec 2022.pdf4 Dec 2024
Certificates of CA (Form 5)File: form 5 2017 -18.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A 2019-20.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2020 -21.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Sep 2017.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Dec 2017.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2018.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2018.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Sep 2018.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Dec 2018.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2019.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2019.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Sep 2019.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: dec 2019.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2020.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2020.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sep 2020.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: dec 2020.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2021.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2021.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sep 2021.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: dec 2021.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2022.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2022.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sep 2022.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: dec 2022.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2023.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2023.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sep 2023.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: dec 2023.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Mar 2024.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Jun 2024.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Sep 2024.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A 2021-22.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 2023-24.pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2017.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2017.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2018.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2018.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sept 2018.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dec 2018.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2019.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2019.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2019.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dec 2019.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2020.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2020.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2020.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dec 2020.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2021.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2021.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2021.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dec 2021.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2022.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2022.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2022.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2023.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2023.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2023.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dec 2023.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2024.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 2024.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sep 2024.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 sept 2017.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2017.pdf3 Dec 2024
Certificates of CA (Form 3)File: FORM 3 MAR 18.pdf3 Dec 2024
Certificates of CA (Form 3)File: FORM 3 JUN 18.pdf3 Dec 2024
Certificates of CA (Form 3)File: FORM 3 SEP 18.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 18.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 mar 2019.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2019.pdf3 Dec 2024
Certificates of CA (Form 3)File: SEP 19.pdf3 Dec 2024
Certificates of CA (Form 3)File: DEC 19.pdf3 Dec 2024
Certificates of CA (Form 3)File: FORM 3 MAR 20.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2020.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sept 2020.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2020.pdf3 Dec 2024
Certificates of CA (Form 3)File: MAR 21.pdf3 Dec 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 42 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Talegaon Dhamdhere13,700+ in Pune

2 kmVIVANTA SARTHAK PHASE 1 Completed 8Lapsed / revoked 15Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: VIVANTA SPACES

VIVANTA SPACES has 1 registration on MahaRERA, including VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C). Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

The registered promoter entity is VIVANTA SPACES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

The professionals named in the filing: Architect: SWAPNIL SHETH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C). Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.