Home / Browse projects / Palghar, Maharashtra / VIVA VISHNUPURAM - ANAND
VIVA VISHNUPURAM - ANAND
RG-MH-19647 · RERA P99000005718 · Last updated on MahaRERA portal: 10 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 54 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIVA VISHNUPURAM - ANAND is a Residential / Group Housing project by VIVA HOMES PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000005718 on 11 Aug 2017. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 22 of the 39 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameVIVA VISHNUPURAM - ANAND
- TypeResidential / Group Housing
- Location
- Dungipada
- Near Meher Park
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000005718
- ReraGenie IDRG-MH-19647
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 10 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ANAND | NA | 5 | 5 | 39 | 0 | 39 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 65%.
ANAND: 52% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 10 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ajay Wade |
| Engineer | PARESH UNNARKAR |
| Engineer | Rajendra Nirgudwar |
| Chartered Accountant | I P MEHTA & COMPANY |
| Chartered Accountant | R J RATHI & CO. |
| Partner | Role in project |
|---|---|
| VIVA HOMES PRIVATE LIMITED | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. In addition, construction activities has severely been affected due to lockdown imposed by concerned authorities, Migration of labor forces and material supply etc. for past 1.5 year.
Reason as filed by the promoterWe are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years.
Reason as filed by the promoterWe are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years.
Reason as filed by the promoterWe are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 of Anand Sep2025.pdf | 10 Jan 2026 |
| Form 2File: Form 2 of Anand Sep2025.pdf | 10 Jan 2026 |
| Form 3File: Form 3 of Anand Sep2025.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Anand Inventory Sep -25.pdf | 10 Jan 2026 |
| Form 1File: Anand Form 1 2017.pdf | 10 Jan 2026 |
| Form 2File: ENGINEER CERTIFICATE OF ANAND 2017.pdf | 10 Jan 2026 |
| Form 3File: ANAND CA CERTIFICATE JULY 2017.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Inventory of 2017.pdf | 10 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A Anand Sep2024.pdf | 10 Jan 2026 |
| Form 2A (FY 2023-2024)File: Form 2A Anand March2024.pdf | 10 Jan 2026 |
| Form 2A (FY 2022-2023)File: FORM 2A ANAND.pdf | 10 Jan 2026 |
| Form 5 (FY 2017-2018)File: Form 5 17-18.pdf | 10 Jan 2026 |
| Form 5 (FY 2018-2019)File: Form 5 18-19.pdf | 10 Jan 2026 |
| Form 5 (FY 2019-2020)File: FORM 5 20-21.pdf | 10 Jan 2026 |
| Form 5 (FY 2020-2021)File: form 5 21-22.pdf | 10 Jan 2026 |
| Form 5 (FY 2021-2022)File: form 5 21-22.pdf | 10 Jan 2026 |
| Form 5 (FY 2022-2023)File: FORM 5 22-23.pdf | 10 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5 23-24.pdf | 10 Jan 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 OF ANAND.pdf | 10 Jan 2026 |
| Form 1File: Anand form 1 Jun25.pdf | 1 Aug 2025 |
| Form 2File: Anand form 2.pdf | 1 Aug 2025 |
| Form 3File: Form 3 of Anand Jun25.pdf | 1 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory of Anand.pdf | 1 Aug 2025 |
| Form 1File: Anand Form 1 Mar 2025.pdf | 19 Jul 2025 |
| Form 2File: Form 2 Anand.pdf | 19 Jul 2025 |
| Form 3File: Form 3 of Anand.pdf | 19 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Anand.pdf | 19 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Anand Form 1 Mar 2024.pdf | 19 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Anand Form 1 Sep 2024.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: Anand Form 3 Mar 2024.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: Anand Form 3 Sep 2024.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Anand Form 2 Mar 2024.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Anand Form 2 Sep 2024.pdf | 19 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Anand Form 5.pdf | 19 Dec 2024 |
| Declaration in FORM BFile: Form B- Anand.pdf | 18 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY ANAND.pdf | 18 Dec 2024 |
| Proforma of Agreement for saleFile: Anand Agreement Draft.pdf | 10 Dec 2024 |
| Proforma of Allotment letterFile: New Format of Allotment -Anand.pdf | 7 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Sheet of Allotment -Anand.pdf | 7 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Sheet of Agreement -Anand.pdf | 7 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: DECLARATION OF NO AN ENCUMBRANCE OF LEGAL OR FINANCE - ANAND.pdf | 5 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY ANAND.pdf | 5 Dec 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A ANAND.pdf | 5 Dec 2024 |
| Details of encumbrances concerned to LegalFile: DECLARATION OF NO AN ENCUMBRANCE OF LEGAL OR FINANCE - ANAND.pdf | 5 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A ANAND.pdf | 5 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Anand March2024.pdf | 5 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Anand Sep2024.pdf | 5 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance availed for the Anand.pdf | 5 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Anand March 2024.pdf | 28 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE OF ANAND 2020.pdf | 20 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE OF ANAND 2022.pdf | 20 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE OF ANAND 2024.pdf | 20 Mar 2024 |
| Certificates of CA (Form 3)File: FORM 3 OF ANAND.pdf | 30 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 OF ANAND.pdf | 29 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY OF ANAND 1.pdf | 8 Jan 2024 |
| Declaration in FORM BFile: FORM B OF ANAND.pdf | 16 Dec 2023 |
| CERSAI detailsFile: CERSAI Search Report.pdf | 16 Dec 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A ANAND.pdf | 16 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 OF ANAND.pdf | 15 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A ANAND.pdf | 14 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY OF ANAND.pdf | 14 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory of Anand.pdf | 27 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Anand.pdf | 27 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - ANAND.pdf | 26 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Viva form 5 Anand.pdf | 26 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate ANAND 31-3-20.pdf | 29 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 ANAND -20.pdf | 29 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 ANAND -21.pdf | 29 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Anand Form 5 2018-2019.pdf | 26 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: ANAND INVENTORY.pdf | 22 Jun 2021 |
| Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf | 21 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Anand.pdf | 21 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate ANAND.pdf | 7 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2.pdf | 25 Sep 2019 |
| Certificates of CA (Form 5)File: FORM5 -ANAND.pdf | 16 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 5 Apr 2018 |
| Proforma of Allotment letterFile: VISHNUPURAM - ANAND.PDF | 16 Feb 2018 |
| Copy of the legal title reportFile: legal title report .pdf | 31 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Anand.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: VIVSH- ANAND.pdf | 31 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VIVA VINDHYAGIRI | VIVA VINDHYAGIRI NEAR ST. PETER HIGH SCHOOL MANVELPADA ROAD VIRAR EAST | 56 | Completed | May 2012 | Late, Jan 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VIVA VISHNUPURAM - ANAND on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Meher Park3,200+ in Palghar
Filed coordinates, straight-line distance. 58 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: VIVA HOMES PRIVATE LIMITED
VIVA HOMES PRIVATE LIMITED has 12 registrations on MahaRERA, including VIVA VISHNUPURAM- AMRUT and VIVA VISHNUPURAM -ARCHIT. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that VIVA VISHNUPURAM - ANAND shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VIVA VISHNUPURAM - ANAND is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIVA VISHNUPURAM - ANAND?
The registered promoter entity is VIVA HOMES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIVA VISHNUPURAM - ANAND?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VIVA VISHNUPURAM - ANAND?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIVA VISHNUPURAM - ANAND?
The professionals named in the filing: Architect: Ajay Wade; Engineer: PARESH UNNARKAR; Engineer: Rajendra Nirgudwar; Chartered Accountant: I P MEHTA & COMPANY; Chartered Accountant: R J RATHI & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIVA VISHNUPURAM - ANAND?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback