Completed No litigation declared Commercial project

VISTAS CENTREPOINT

By Cavalcade Properties Private Limited

RG-MH-53067 · RERA P52100016359 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

VISTAS CENTREPOINT is a Commercial project by Cavalcade Properties Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100016359 on 8 May 2018. The registration is recorded completed; possession was promised by 30 Dec 2021. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVISTAS CENTREPOINT
  • TypeCommercial
  • Location
    • NIBM ROAD
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016359
  • ReraGenie IDRG-MH-53067

Builder

  • NameCavalcade Properties Private Limited
  • Entity typeCompany
  • CINU70100MH2005PTC154307
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Company SecretorySHARMIN VALI PATEL
  • Other registrations7 more →
  • Completed6 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredMay 2018PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 May 2018
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VISTAS CENTREPOINTNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

VISTAS CENTREPOINT: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed59

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots59
Closed/Covered46
Open Space13

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,514 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2851.16
Proposed, not sanctioned2,851 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManeckji Wadia Bldg, Ground Floor, Nanik Motwani Marg, Fort, Mumbai 400 001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKTGY Architecture
ArchitectLaxman Thite
PartnerRole in project
Cavalcade Properties Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000096015Inorbit Malls India Private LimitedDeepak Chandulal Lohana15/09/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Mar 2020

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: Conveyance Declaration VCP.pdf20 Jan 2025
Status of ConveyanceFile: Conveyance Declaration VCP.pdf18 Jul 2024
Status of ConveyanceFile: Conveyance Declaration VCP.pdf19 Jan 2024
OtherFile: Demerger Application VCP.pdf10 Nov 2023
Status of ConveyanceFile: VCP Conveyance Declaration.pdf19 Jan 2023
Status of ConveyanceFile: VCP Conveyance Declaration.pdf18 Oct 2022
Status of ConveyanceFile: Self Declaration _Conveyance_RVP.pdf6 Jul 2022
Status of ConveyanceFile: VCP Conveyance Declaration.pdf4 Apr 2022
Status of ConveyanceFile: Conveyance Decln VCP.pdf31 Dec 2021
Status of ConveyanceFile: VCP Conveyance Declaration.pdf7 Oct 2021
Status of ConveyanceFile: VCP Conveyance.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VC Certificate.pdf30 Sep 2020
Architect’s Certificate on Completion of Project (Form 4)File: Centrepoint_formIV_14_08_2020 (3).pdf8 Sep 2020
Details of Restarting of Construction work post lockdownFile: Centrepoint.pdf21 Jun 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc centrepoint.pdf22 Mar 2020
OtherFile: OC CENTREPOINT.pdf22 Mar 2020
Proforma of Allotment letterFile: Booking Application Form.pdf6 Nov 2019
Annual Audit Report of Statutory CA (Form 5)File: RERA certificate - Vistas Centrepoint.pdf30 Sep 2019
Proforma of Allotment letterFile: CP.pdf25 Sep 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: 8391-1.pdf3 May 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: 8391-2.pdf3 May 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: 8391-3.pdf3 May 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: Intimation letter to Society Registrar for centrepoint (1).pdf3 May 2019
OtherFile: Plot C plinth certificate.pdf17 Dec 2018
Proforma of Allotment letterFile: Provisional Booking Form-Plot C -30 04 2018.pdf3 May 2018
Details of encumbrancesFile: Affidavit cum Declaration Plot C May 2018.pdf2 May 2018
Declaration in FORM BFile: Affidavit cum Declaration Plot C May 2018.pdf2 May 2018
Proforma of Allotment letterFile: RERA AFS - 30 04 2018.pdf2 May 2018
Building plan approvalFile: floor plans 2_3.pdf30 Apr 2018
Layout approvalFile: Layout.pdf30 Apr 2018
Building plan approvalFile: floor_plans 3_3.pdf30 Apr 2018
PAN CardFile: Plot C PAN.pdf30 Apr 2018
Copy of the legal title reportFile: Title Certificate.pdf30 Apr 2018
Copy of Layout Approval (in case of layout)File: Layout.pdf30 Apr 2018
Building Plan Approval (IOD)File: floor plans 2_3.pdf30 Apr 2018
Building Plan Approval (IOD)File: floor_plans 3_3.pdf30 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement_certificate.pdf30 Apr 2018
Certificates of CA (Form 3)File: CA Certificate.pdf30 Apr 2018

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
T13 Phase of the project comprising Building T12 and T1327 Oblique 4 part and others part57CompletedDec 2017Late, Feb 2018
RAHEJA VISTAS BUILDING B2S No 27 Hissa No 1 Oblique B Plus 2 Plus 3 Plot B Part of Village Mohammadwadi Taluka Haveli District Pune44CompletedDec 2016Late, Jun 2018
T5/T6VILLAGE MOHAMMADWADI TALUKA HAVELI DISTRICT PUNE304CompletedSep 2016Late, Dec 2016
RAHEJA VISTAS F5 PHASE IIIVILLAGE MOHAMMADWADI TALUKA HAVELI DISTRICT PUNE43CompletedSep 2014Late, Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VISTAS CENTREPOINT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOHAMMADWADI13,700+ in Pune

2 kmVISTAS CENTREPOINTCompleted 162Lapsed / revoked 119Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: Cavalcade Properties Private Limited

Cavalcade Properties Private Limited has 8 registrations on MahaRERA, including RAHEJA VISTAS BUILDING B2 and T13 - PHASE OF THE PROJECT COMPRISING BUILDING T12 AND T13. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VISTAS CENTREPOINT is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISTAS CENTREPOINT?

The registered promoter entity is Cavalcade Properties Private Limited, a company as per the filing. Its CIN U70100MH2005PTC154307 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISTAS CENTREPOINT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VISTAS CENTREPOINT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VISTAS CENTREPOINT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISTAS CENTREPOINT?

The professionals named in the filing: Architect: KTGY Architecture; Architect: Laxman Thite. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISTAS CENTREPOINT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISTAS CENTREPOINT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISTAS CENTREPOINT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.