ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Vishal Vishwa Phase 2 - Building Number 3

Completed No litigation declared Residential / Group Housing project

Vishal Vishwa Phase 2 - Building Number 3

By Vishal Constructions

RG-MH-09322 · RERA P52100000612 · Last updated on MahaRERA portal: 16 Feb 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

Vishal Vishwa Phase 2 - Building Number 3 is a Residential / Group Housing project by Vishal Constructions in Pune, Maharashtra, registered with MahaRERA as P52100000612 on 18 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameVishal Vishwa Phase 2 - Building Number 3
  • TypeResidential / Group Housing
  • Location
    • VISHAL VISHWA ROAD
    • TALEGAON DHAMDHERE
    • Shirur
    • Pune
    • 412208
  • Pincode412208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000612
  • ReraGenie IDRG-MH-09322

Builder

  • NameVishal Constructions
  • Entity typePartnership
  • PartnersSuhas Shivdas Nandode, Sandhya Pramod Muttha, Sarita Ashok Sasane, Tarachand Dagdu Tejinkar, Anjali Vilas Sable
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017First promiseDec 2018Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing E and FNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Wing E and F: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 16 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%
CCTV CameraYes100%
2 Lifts in each wingYes100%

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered32
Open Space24

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,969 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4067.98
Proposed, not sanctioned4,068 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK, GAT NUMBER 1067, HOTEL SAI LODGING, SHIKRAPUR, DIST - PUNE - 412208

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeepak Deshchoughele
PartnerRole in project
Vishal Constructions-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005141Dec 2018 → Dec 2020

Reason as filed by the promoterWe are not able to complete our some project work due to some technical problems raised by agencies which are as follows. 1. Lift's testing is under progress 2. solar water setup testing work is under progress 3. Also we need time to obtain building completion certificate procedure is under progress. 4. also development control rules were changed by authorities in year 2013 as well as in year 2017 due to this reason our submission of revised plan got delayed. Now revised plans are submitted on 21 NOV 2019 to PMRDA Pune for sanctions.

EXT52100000892Dec 2018 → Dec 2020

Reason as filed by the promoterConstruction work for project Vishal Vishwa Phase 2 Building Number 3 is fully completed but for BCC required document like (1) final fire NOC (2) final lift NOC yet to be received. (3) Final measurement plan of buildings from sub registrar office is yet to be obtained. For getting all documents mentioned above we will require some time. Then we have to apply for B.C.C to PMRDA Pune, after submission to PMRDA we will get B.C.C all above procedure require maximum time of one year.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Feb 2023

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Regarding Project Status.pdf16 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Regarding Project Status.pdf16 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Regarding Project Status.pdf16 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Regarding Project Status.pdf16 Feb 2023
Disclosure of sold/ booked inventoryFile: Regarding Project Status.pdf16 Feb 2023
CERSAI detailsFile: Regarding Project Status.pdf16 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Regarding Project Status.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Regarding Project Status.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Regarding Project Status.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Regarding Project Status.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Regarding Project Status.pdf16 Feb 2023
Proforma of Agreement for saleFile: Regarding Project Status.pdf16 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Regarding Project Status.pdf16 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Regarding Project Status.pdf16 Feb 2023
Status of ConveyanceFile: Regarding Project Status.pdf16 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Regarding Project Status.pdf16 Feb 2023
Deviation Report with respect to Allotment letterFile: Regarding Project Status.pdf16 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Regarding Project Status.pdf16 Feb 2023
Architect’s Certificate on Completion of Project (Form 4)File: architect certificate.pdf6 Dec 2019
Certificates of CA (Form 5)File: form 5-ilovepdf-compressed.pdf14 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: CC vishal vishwa02012019132740-ilovepdf-compressed (1).pdf2 Jan 2019
Declaration in FORM BFile: Form B Declearation.pdf17 Jul 2017
Certificates of CA (Form 3)File: CA Form No3.pdf17 Jul 2017
Proforma of Allotment letterFile: Agreement to Sale Vishal Constructions.pdf17 Jul 2017
Copy of the legal title reportFile: Title report Vishal Constructions.pdf15 Jul 2017
Details of encumbrancesFile: Details of Encubrance.pdf15 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate .PDF13 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate -Revised.PDF13 Jul 2017
Building plan approvalFile: Building Layout Vishal Constructions.pdf12 Jul 2017
Layout approvalFile: Layout Approval Vishal Constructions.pdf12 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Approval Vishal Constructions.pdf12 Jul 2017
Building Plan Approval (IOD)File: Building Layout Vishal Constructions.pdf12 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Vishal Vishwa Phase 1S.No.3668 Mali Mala Road Opposite L&T Phata Near john Deer Compnay.131CompletedDec 2011Dec 2011

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vishal Vishwa Phase 2 - Building Number 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALEGAON DHAMDHERE13,700+ in Pune

Builder: Vishal Constructions

Vishal Constructions has 2 registrations on MahaRERA, including Vishal Vishwa Phase 2 - Building Number 3 and VISHAL VISHWA PHASE 2 - BUILDING NUMBER 1 AND 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Vishal Vishwa Phase 2 - Building Number 3 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vishal Vishwa Phase 2 - Building Number 3?

The registered promoter entity is Vishal Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vishal Vishwa Phase 2 - Building Number 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vishal Vishwa Phase 2 - Building Number 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vishal Vishwa Phase 2 - Building Number 3?

The professionals named in the filing: Architect: Deepak Deshchoughele. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vishal Vishwa Phase 2 - Building Number 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vishal Vishwa Phase 2 - Building Number 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vishal Vishwa Phase 2 - Building Number 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.