Home / Browse projects / Thane, Maharashtra / Vinayak Complex Phase-I

Registered No litigation declared Others project

Vinayak Complex Phase-I

By Vinayak Construction

RG-MH-31751 · RERA P51700080086 · Last updated on MahaRERA portal: 15 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 45%
130 of 145Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Vinayak Complex Phase-I is a Others project by Vinayak Construction in Thane, Maharashtra, registered with MahaRERA as P51700080086 on 23 Apr 2025. Possession is promised by 31 Dec 2029. 15 of the 145 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameVinayak Complex Phase-I
  • TypeOthers
  • Location
    • Kalyan Shil Road
    • Dombivali East
    • Behind Kokan Ratna Hotel
    • Padle
    • Thane (M Corp.)
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700080086
  • ReraGenie IDRG-MH-31751

Builder

  • NameVinayak Construction
  • Entity typePartnership
  • PartnersDharmendra Ramkirat Singh, Amitkumar Ramkirat Singh, Abhimannu Jamuna Singh, Anil A Singh, Ramuday Aadik Yadav, Sandesh Prabhakar Bhosale, Smita Ashok Kadam
  • Other registrations8 more →
  • Completed1 of 9
  • No longer live4 lapsed, de-registered or revoked

Key dates

this monthRegisteredApr 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Apr 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed46 files

Current status

10%15 of 145 units booked
20.1%Work done, per cost certificate

Figures as on 15 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vinayak Complex Phase-INA28281387145

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 45%.

Vinayak Complex Phase-I: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises17%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed163

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots163
Closed/Covered48
Open Space115

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 May 2025
LandownerVillageDistrict
Sunil Ambo GaikwadThane (M Corp.)Thane
Vaishali Ravindra JadhavThane (M Corp.)Thane
Dhiraj Ambo GaikwadThane (M Corp.)Thane
Valkya Kanha GaikwadThane (M Corp.)Thane
Kaliram Kanha GaikwadThane (M Corp.)Thane
Meera Namdev GaykvadThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI19485.55
Proposed, not sanctioned9,486 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD GRND FLR 10 11 12 15 16 KASTURI ASHISH DAVDI NAKA KALYAN SHIL RD MAHARASHTRA421201
Estimated costRs 25.00 cr
Cost incurredRs 5.03 cr
Work done20.12%
BuildingWingEstimatedIncurred
Vinayak Complex Phase-INARs 25.00 crRs 5.03 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJitesh P. Pawar & Associates
EngineerShravani Consultant
Chartered AccountantR H Pothiwal & Associates
PartnerRole in project
Vinayak Construction-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Mar 26.pdf15 Jun 2026
Withdrawal Update Form 2File: Form 2_Mar 26.pdf15 Jun 2026
Withdrawal Update Form 3File: CA Certificate_Mar 26_Vinayak Complex Phase-I.pdf15 Jun 2026
Withdrawal Update Form 1File: Form 1 Dec 25 Signed.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Dec 25 Signed.pdf24 Jan 2026
Withdrawal Update Form 3File: FORM 3 DEC 25 VINAYAK COMPLEX SIGNED.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1 Sept 25.pdf17 Nov 2025
Withdrawal Update Form 2File: Form-2 Sept-25.pdf17 Nov 2025
Withdrawal Update Form 3File: CA Certificate_Sep-25.pdf17 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf14 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf14 Aug 2025
Withdrawal Update Form 3File: Form 3.pdf14 Aug 2025
Other - FinanceFile: Declaration.pdf22 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Conf.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Vinayak Complex.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report for AFS.pdf25 Mar 2025
Proforma of Agreement for saleFile: Draft Agreement For Sale_Final.pdf25 Mar 2025
Copy of the legal title reportFile: Title Report - Vinayak Complex Phase-I_page-0001.pdf22 Mar 2025
Declaration in FORM BFile: FORM B DEVELOPER.pdf22 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_page-0001.pdf22 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf22 Mar 2025
Other - FinanceFile: Declaration cum undertaking for no sale_page-0001.pdf22 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estates.pdf22 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf22 Mar 2025
Layout approvalFile: Building Plan.pdf20 Mar 2025
Building plan approvalFile: Building Plan.pdf20 Mar 2025
PAN CardFile: Firm PAN Card.pdf20 Mar 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf20 Mar 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf20 Mar 2025
Copy of Layout Approval (in case of layout)File: Building Plan.pdf20 Mar 2025
Proforma of Allotment letterFile: Allotment Letter.pdf20 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf20 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf20 Mar 2025
Other - LegalFile: POA 9-6-B VINAYAK CONSTRUCTION.pdf20 Mar 2025
Other - LegalFile: Deed of Partership - converted.pdf20 Mar 2025
Other - LegalFile: SATHEKHAT 9-6-B VINAYAK CONSTRUCTION.pdf20 Mar 2025
Other - LegalFile: KHAREDIKHAT 9-9.pdf20 Mar 2025
Other - LegalFile: POA 9-6-B 2019 VINAYAK CONSTRUCTION.pdf20 Mar 2025
Declaration about Commencement CertificateFile: Form D.pdf20 Mar 2025
CERSAI detailsFile: UNDERTAKING WITH REGARDS TO CERSAI REPORT.pdf20 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf20 Mar 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf20 Mar 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf20 Mar 2025
Other - TechnicalFile: Declaration of One Plot One Registration.pdf20 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance availed for the projec.pdf20 Mar 2025

How this compares with Thane

10%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vinayak Complex Phase-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind Kokan Ratna Hotel, Padle7,600+ in Thane

Builder: Vinayak Construction

VINAYAK CONSTRUCTION has 9 registrations on MahaRERA, including C VINAYAK INDUSTRIAL ESTATE and VINAYAK CONSTRUCTION. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Vinayak Complex Phase-I is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vinayak Complex Phase-I?

The registered promoter entity is Vinayak Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vinayak Complex Phase-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vinayak Complex Phase-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vinayak Complex Phase-I?

The professionals named in the filing: Architect: Jitesh P. Pawar & Associates; Engineer: Shravani Consultant; Chartered Accountant: R H Pothiwal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vinayak Complex Phase-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vinayak Complex Phase-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vinayak Complex Phase-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.