Home / Browse projects / Mumbai Suburban, Maharashtra / VIGHNAHARTA SRA CHS LTD
VIGHNAHARTA SRA CHS LTD
By PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
RG-MH-55323 · RERA P51800016404 · Last updated on MahaRERA portal: 8 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 48 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIGHNAHARTA SRA CHS LTD is a Others project by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800016404 on 10 May 2018. Possession is promised by 31 Dec 2028. The completion date has moved by 48 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameVIGHNAHARTA SRA CHS LTD
- TypeOthers
- Location
- SIDDHARTH COLONY ROAD
- PARALKARWADI VILLAGE CHEMBUR TALUKA KURLA
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800016404
- ReraGenie IDRG-MH-55323
Builder
- NamePARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- CINU42909MH2023PTC404735
- PartnersRAJAN PRABHAKAR PATHARE, KRUPA RAJAN PATHARE, SEENA SUDHANSHU NAIK
- Other registrations4 more →
- Completed1 of 5
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 May 2018
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2024)
- Buildings1 building record
- Documents filed113 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PARSN AVIGHNI | NA | 17 | 17 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
PARSN AVIGHNI: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
| Society Office | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR SUNIL THAKUR |
| Architect | MR SAMIR KULKARNI KULKARNI |
| Engineer | VIJAY BHISE AND ASSOCIATES |
| Engineer | SURA AND ASSOCIATES |
| Engineer | VIJAY NARANG |
| Chartered Accountant | S M BHATT AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterFollowing the issuance of the Commencement Certificate by the Planning Authority, a No Objection Certificate (NOC) from the Public Works Department (PWD) was required, given that the subject project pertains to a Slum Rehabilitation Authority (SRA) initiative. However, the Public Works Department (PWD) took a period of seven years to issue the requisite NOC, due to the frequent and continuous revisions in the rules, regulations, and policies governing such projects. This delay was beyond our control and resulted from the PWD’s need to adapt to and comply with the evolving legal and regulatory
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000057118 | Kaustubh Palande | Parsn Foundation and Engineering Corporation | 30/11/2018 |
| CC006000000195343 | Jude Damian D'Souza | M/s ParsnFoundationand EngineeringCorporation | 22/12/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 May 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed113
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1_ DEC 25_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 2File: FORM 2_ DEC 25_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 3File: FORM 3_ DEC 25_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 25_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 1File: FORM 1_ MARCH 26_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 2File: FORM 2_ MARCH 26_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 3File: FORM 3_ MARCH 26_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 26_ PARSN VIGHNAHARTA.pdf | 8 Jun 2026 |
| Form 1File: FORM 1_ SEP 25_ PARSN_ SHREE VIGHNAHARTA.pdf | 19 Jan 2026 |
| Form 2File: FORM 2_ SEP 25_ PARSN_ SHREE VIGHNAHARTA.pdf | 19 Jan 2026 |
| Form 3File: FORM 3_SEP 25_PARSN VIGHNAHARTA.pdf | 19 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_PARSN VIGHNAHARTA.pdf | 19 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A _24-25_VIGHNAHARTA SRA CHS LTD.pdf | 22 Dec 2025 |
| Form 1File: FORM 1_ JUNE 25_ PARSN_ SHREE VIGHNAHARTA.pdf | 3 Dec 2025 |
| Form 2File: FORM 2_ JUNE 25_ VIGHNARHTA.pdf | 3 Dec 2025 |
| Form 3File: FORM 3_ JUNE 25_ PARSN_ SHREE VIGHNAHARTA.pdf | 3 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25_PARSN_SHREE VIGHNAHARTA.pdf | 3 Dec 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ MARCH 25_compressed.pdf | 20 May 2025 |
| Certificates of CA (Form 3)File: FORM 3_ MARCH 25_ PARSN_ VIGHAHARTHA SRA LTD.pdf | 20 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ MARCH 25_ VIGHNARHTA.pdf | 20 May 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 25_ PARSN_ VIGHNAHARTA.pdf | 20 May 2025 |
| Declaration in FORM BFile: FORM B.pdf | 10 Mar 2025 |
| CERSAI detailsFile: GetUserDocumentFileContent (5).pdf | 6 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ DEC 24.pdf | 4 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3_SRA.pdf | 4 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM_2.pdf | 4 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24.pdf | 4 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Declaration with Respect to Security Interest and Finance Charges.pdf | 3 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: encrumbances finance.pdf | 3 Feb 2025 |
| Declaration in FORM BFile: FORM B.pdf | 3 Feb 2025 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf | 3 Feb 2025 |
| Details of encumbrances concerned to LegalFile: encrumbances finance.pdf | 3 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Declaration with Respect to Security Interest and Finance Charges.pdf | 3 Feb 2025 |
| Proforma of Agreement for saleFile: AGREEEMENT FOR SALE_RERA.pdf | 3 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: GetUserDocumentFileContent-4-5.pdf | 3 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for securedunsecured finance availed for the project.pdf | 3 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5_ MARCH 19.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5_ MARCH 20.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_ MARCH 21.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_ MARCH 22.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5_ MARCH 23.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_ SEP 23.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_ MARCH 24.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SRA.pdf | 5 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_ SEP 23.pdf | 19 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1_ SEP 24.PDF | 16 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3_ SEP 24.pdf | 16 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ SEP 24.pdf | 16 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ SEP 24.pdf | 16 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1_JUNE 24.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM 2_ JUNE 24.PDF | 30 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ JUNE 24.PDF | 30 Jul 2024 |
| Certificates of CA (Form 3)File: 3 FORM 3_ JUNE 24.PDF | 30 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 30 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 2 Format A SRA.pdf | 16 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- VIGHNAHARTA_MARCH 24.pdf | 11 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2- VIGHNAHARTA_MARCH 24.pdf | 11 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A- VIGHNAHARTA_23 24.pdf | 11 May 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD- VIGHNAHARTA_MARCH 24.pdf | 11 May 2024 |
| Certificates of CA (Form 3)File: FORM 3- VIGHNAHARTA_MARCH 24.pdf | 11 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1 _SRA.PDF | 12 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VIGHNAHARTA SRA CHS LTD_FORM 1.pdf | 12 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 _ SRA.pdf | 12 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VIGHNAHARTA SRA CHS LTD_FORM 2.pdf | 12 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold _SRA.pdf | 12 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: VIGHNAHARTA SRA CHS LTD_SOLD UNSOLD_DECEMBER.pdf | 12 Mar 2024 |
| Certificates of CA (Form 3)File: Form_03_Vighnaharta SRA.pdf | 12 Mar 2024 |
| Certificates of CA (Form 3)File: VIGHNAHARTA SRA CHS LTD_FORM 3.pdf | 12 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_ SRA .pdf | 12 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 6 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-VIGHNAHARTA_JUN 23.pdf | 5 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-VIGHNAHARTA_JUN 23.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-VIGHNAHARTA_22 23.PDF | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-VIGHNAHARTA_JUN 23.pdf | 5 Oct 2023 |
| Certificates of CA (Form 3)File: FORM 3-VIGHNAHARTA_JUN 23_compressed.pdf | 5 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-VIGHNAHARTA_MAR 23.pdf | 24 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-VIGHNAHARTA_MAR 23.PDF | 24 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED-VIGHNAHARTA_MAR 23.pdf | 24 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 113 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VIGHNAHARTA SRA CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PARALKARWADI VILLAGE CHEMBUR TALUKA KURLA6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 383 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED has 5 registrations on MahaRERA, including KURLA SAHAYOG CHS LTD., BLDG. NO.68 and NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if VIGHNAHARTA SRA CHS LTD is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIGHNAHARTA SRA CHS LTD?
The registered promoter entity is PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U42909MH2023PTC404735 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIGHNAHARTA SRA CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VIGHNAHARTA SRA CHS LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VIGHNAHARTA SRA CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIGHNAHARTA SRA CHS LTD?
The professionals named in the filing: Architect: MR SUNIL THAKUR; Architect: MR SAMIR KULKARNI KULKARNI; Engineer: VIJAY BHISE AND ASSOCIATES; Engineer: SURA AND ASSOCIATES; Engineer: VIJAY NARANG; Chartered Accountant: S M BHATT AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIGHNAHARTA SRA CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback