VENKATESH HEIGHTS
RG-MH-91592 · RERA P52100015206 · Last updated on MahaRERA portal: 23 Aug 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- Completion date moved by 39 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VENKATESH HEIGHTS is a Residential / Group Housing project by VENKATESH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100015206 on 7 Feb 2018. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 39 months from the original filing.
At a glance
Project
- NameVENKATESH HEIGHTS
- TypeResidential / Group Housing
- Location
- NAGAR PUNE HIGHWAY
- BABURAO NAGAR
- SHIRUR
- Shirur Gramin
- Shirur
- Pune
- 412210
- Pincode412210
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100015206
- ReraGenie IDRG-MH-91592
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Feb 2018
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 30 Sep 2020)
- Buildings2 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING-A | NA | 6 | 0 | 0 | 0 | 0 |
| WING-B | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
WING-A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING-B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING-A | 1 | 34 | 35 |
| WING-B | 1 | 2 | 3 |
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| KAILAS PANDHARINATH SONAVANE | - | Pune |
| ROHIDAS PANDHARINATH SONWANE | Kasti | Ahmednagar |
| SUNIL PANDHARINATH SONAVANE | Kasti | Ahmednagar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rajesh Dnyaneshwar Abnave |
| Engineer | Kishor Sopanrao Gawali |
| Partner | Role in project |
|---|---|
| VENKATESH ASSOCIATES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOut-of-state workers have not yet arrived due to corona disease. There are difficulties in making local labor available.The work has stopped. BUILDING NO. B is 95% complete. But building no. A is 80% complete. Therefore, Rera term should be extended for 1 year.
Reason as filed by the promoterThe completion of the project was delayed due to covid. But now application has been submitted in PMRDA for project completion. Project visit has not been done yet. However, we should get Project Extension by 31st December 2023.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jan 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jan 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jan 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 14 Aug 2023
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcitect form 1.pdf | 23 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certi form 2.pdf | 23 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 16 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 16 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Cert Form2.pdf | 14 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Partners Declaration_compressed.pdf | 14 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: architect certificate declaration.pdf | 14 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: affidevit shirur.pdf | 9 Aug 2023 |
| Details of encumbrances concerned to LegalFile: affidevit shirur.pdf | 9 Aug 2023 |
| Declaration in FORM BFile: affidevit shirur.pdf | 8 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: declarstion 2022-23.pdf | 8 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SKM_C36423071508240.pdf | 15 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate.pdf | 15 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Declaration of 1917 - 18.pdf | 15 Jul 2023 |
| Declaration about Commencement CertificateFile: Declaration about commencement.pdf | 11 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf | 11 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- 2021-22.pdf | 24 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-1 2019-20.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-2 2019-20.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-3 2019-20.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-4 2019-20.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-1 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-2 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-3 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-4 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-1 2021-22.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-2 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-3 2020-21.pdf | 9 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-4 2021-22.pdf | 9 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- 2018-19.pdf | 9 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 2019-20.pdf | 9 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- 2020-21.pdf | 9 Apr 2023 |
| Building plan approvalFile: Plan-01.pdf | 17 Jan 2018 |
| Building plan approvalFile: Plan-02.pdf | 17 Jan 2018 |
| Building plan approvalFile: Plan-03.pdf | 17 Jan 2018 |
| Copy of the legal title reportFile: Search Report.pdf | 17 Jan 2018 |
| Details of encumbrancesFile: Search Report.pdf | 17 Jan 2018 |
| Building Plan Approval (IOD)File: Plan-01.pdf | 17 Jan 2018 |
| Building Plan Approval (IOD)File: Plan-02.pdf | 17 Jan 2018 |
| Building Plan Approval (IOD)File: Plan-03.pdf | 17 Jan 2018 |
| Proforma of Allotment letterFile: Agreement Declaration.pdf | 17 Jan 2018 |
| Layout approvalFile: Plan-001.pdf | 3 Jan 2018 |
| PAN CardFile: Pan.pdf | 3 Jan 2018 |
| Copy of Layout Approval (in case of layout)File: Plan-001.pdf | 3 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: PMRDA Cerificate.pdf | 3 Jan 2018 |
| Declaration in FORM BFile: FORM B-Vyankatesh.pdf | 3 Jan 2018 |
| Certificates of CA (Form 3)File: CA.pdf | 3 Jan 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 13 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VENKATESH HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BABURAO NAGAR, SHIRUR13,700+ in Pune
Filed coordinates, straight-line distance. 58 registered projects within 2 km.
SUNDAR SHRUSHTI
RAMLING LAND DEVELOPERS LLP
Rayat Residency
SOHAM CONSTRUCTIONS AND DEVELOPERS
NAKSHATRA AROMA
NITU ASSOCIATES
NAKSHATRA SAFFRON
NAMRATA DEVELOPERS
Rayat Regency
SOHAM CONSTRUCTIONS AND DEVELOPERS
KEWAL KUNJ
BORA EXCELLENCY DEVELOPERS UNIT 1
Builder: VENKATESH ASSOCIATES
VENKATESH ASSOCIATES has 14 registrations on MahaRERA, including OXY EVOLVE and OXY DESIRE. Its filings disclose 12 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that VENKATESH HEIGHTS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VENKATESH HEIGHTS is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VENKATESH HEIGHTS?
The registered promoter entity is VENKATESH ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VENKATESH HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VENKATESH HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VENKATESH HEIGHTS?
The professionals named in the filing: Architect: Rajesh Dnyaneshwar Abnave; Engineer: Kishor Sopanrao Gawali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VENKATESH HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback