Registration lapsed No litigation declared Residential / Group Housing project

VENKATESH HEIGHTS

By VENKATESH ASSOCIATES

RG-MH-91592 · RERA P52100015206 · Last updated on MahaRERA portal: 23 Aug 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 39 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

VENKATESH HEIGHTS is a Residential / Group Housing project by VENKATESH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100015206 on 7 Feb 2018. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 39 months from the original filing.

At a glance

Project

  • NameVENKATESH HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • NAGAR PUNE HIGHWAY
    • BABURAO NAGAR
    • SHIRUR
    • Shirur Gramin
    • Shirur
    • Pune
    • 412210
  • Pincode412210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015206
  • ReraGenie IDRG-MH-91592

Builder

  • NameVENKATESH ASSOCIATES
  • Entity typePartnership
  • PartnersRAMDAS DATTU HOLE, RAMBHAU KISAN JAGTAP, NITIN DATTATRAY CHAURE, SUNIL RAMRAO RAUT, AMBADAS RAMDAS CHAUDHARI
  • Other registrations13 more →
  • Completed7 of 14
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

34 months past promisethis monthRegisteredFeb 2018First promiseSep 2020Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Feb 2018
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Sep 2020)
  • Buildings2 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING-ANA60000
WING-BNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

WING-A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING-B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered2
Open Space36
BuildingClosed/CoveredOpen SpaceTotal
WING-A13435
WING-B123

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,551 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
KAILAS PANDHARINATH SONAVANE-Pune
ROHIDAS PANDHARINATH SONWANEKastiAhmednagar
SUNIL PANDHARINATH SONAVANEKastiAhmednagar

Approvals and building plan

Permissible FSI2162.5
Proposed, not sanctioned2,162 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchH NO 2197, MUTHA EMPIRE, REVENUE COLONY, NEAR POST OFFICE, SHIRUR, DIST PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Dnyaneshwar Abnave
EngineerKishor Sopanrao Gawali
PartnerRole in project
VENKATESH ASSOCIATES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008455Sep 2020 → Sep 2021

Reason as filed by the promoterOut-of-state workers have not yet arrived due to corona disease. There are difficulties in making local labor available.The work has stopped. BUILDING NO. B is 95% complete. But building no. A is 80% complete. Therefore, Rera term should be extended for 1 year.

EXT52100016511Sep 2020 → Dec 2023

Reason as filed by the promoterThe completion of the project was delayed due to covid. But now application has been submitted in PMRDA for project completion. Project visit has not been done yet. However, we should get Project Extension by 31st December 2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Aug 2023

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcitect form 1.pdf23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certi form 2.pdf23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Cert Form2.pdf14 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Partners Declaration_compressed.pdf14 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: architect certificate declaration.pdf14 Aug 2023
Details of encumbrances concerned to FinanceFile: affidevit shirur.pdf9 Aug 2023
Details of encumbrances concerned to LegalFile: affidevit shirur.pdf9 Aug 2023
Declaration in FORM BFile: affidevit shirur.pdf8 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: declarstion 2022-23.pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SKM_C36423071508240.pdf15 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate.pdf15 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Declaration of 1917 - 18.pdf15 Jul 2023
Declaration about Commencement CertificateFile: Declaration about commencement.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf11 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- 2021-22.pdf24 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-1 2019-20.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-2 2019-20.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-3 2019-20.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q-4 2019-20.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-1 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-2 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-3 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q-4 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-1 2021-22.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-2 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-3 2020-21.pdf9 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q-4 2021-22.pdf9 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- 2018-19.pdf9 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 2019-20.pdf9 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- 2020-21.pdf9 Apr 2023
Building plan approvalFile: Plan-01.pdf17 Jan 2018
Building plan approvalFile: Plan-02.pdf17 Jan 2018
Building plan approvalFile: Plan-03.pdf17 Jan 2018
Copy of the legal title reportFile: Search Report.pdf17 Jan 2018
Details of encumbrancesFile: Search Report.pdf17 Jan 2018
Building Plan Approval (IOD)File: Plan-01.pdf17 Jan 2018
Building Plan Approval (IOD)File: Plan-02.pdf17 Jan 2018
Building Plan Approval (IOD)File: Plan-03.pdf17 Jan 2018
Proforma of Allotment letterFile: Agreement Declaration.pdf17 Jan 2018
Layout approvalFile: Plan-001.pdf3 Jan 2018
PAN CardFile: Pan.pdf3 Jan 2018
Copy of Layout Approval (in case of layout)File: Plan-001.pdf3 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: PMRDA Cerificate.pdf3 Jan 2018
Declaration in FORM BFile: FORM B-Vyankatesh.pdf3 Jan 2018
Certificates of CA (Form 3)File: CA.pdf3 Jan 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 39 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VENKATESH HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BABURAO NAGAR, SHIRUR13,700+ in Pune

2 kmVENKATESH HEIGHTSCompleted 12Lapsed / revoked 17Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: VENKATESH ASSOCIATES

VENKATESH ASSOCIATES has 14 registrations on MahaRERA, including OXY EVOLVE and OXY DESIRE. Its filings disclose 12 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that VENKATESH HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VENKATESH HEIGHTS is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VENKATESH HEIGHTS?

The registered promoter entity is VENKATESH ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VENKATESH HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VENKATESH HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VENKATESH HEIGHTS?

The professionals named in the filing: Architect: Rajesh Dnyaneshwar Abnave; Engineer: Kishor Sopanrao Gawali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VENKATESH HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VENKATESH HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VENKATESH HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.