Home / Browse projects / Pune, Maharashtra / VENKATESH GRAFFITI PHASE 5

Completed No litigation declared Residential / Group Housing project

VENKATESH GRAFFITI PHASE 5

By SHREE VENKATESH BUILDCON PVT LTD

RG-MH-57958 · RERA P52100018950 · Last updated on MahaRERA portal: 22 Apr 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 23 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 20 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

VENKATESH GRAFFITI PHASE 5 is a Residential / Group Housing project by SHREE VENKATESH BUILDCON PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100018950 on 17 Dec 2018. The registration is recorded completed; possession was promised by 30 Mar 2022.

At a glance

Project

  • NameVENKATESH GRAFFITI PHASE 5
  • TypeResidential / Group Housing
  • Location
    • MUNDHWA MANJARI ROAD
    • KESHAV NAGAR MUNDHWA
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018950
  • ReraGenie IDRG-MH-57958

Builder

  • NameSHREE VENKATESH BUILDCON PVT LTD
  • Entity typeCompany
  • CINU45200PN2008PTC132398
  • GSTIN27AANCS1902K1Z5
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorANKUSH BHIMRAO ASABE
  • Other registrations20 more →
  • Completed12 of 21
  • Past their filed date2
  • Declared earlier projects26 →

Key dates

this monthRegisteredDec 2018PromisedMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Dec 2018
  • Promised completion30 Mar 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING QNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

WING Q: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities20

As on 22 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
PLAY GROUND IN OPEN SPACE 2Yes100%
Swimming Pool & Kids Pool OPEN SPACE 1Yes100%
Community Building Club House Open Space - 1Yes100%
LANSCAPINGAND TREEPLANTING OPEN SPACE 1Yes100%
OWC PLANTYes100%

Parking filed111

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots111
Closed/Covered111

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,468 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
SUJATA ARUN LONKARKeshavnagar-MundwaPune
PRABHAKAR DEVRAM LONKARKeshavnagar-MundwaPune
TUKARAM DEVRAM LONKARKeshavnagar-MundwaPune

Approvals and building plan

Permissible FSI8037.69
Proposed, not sanctioned8,038 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch562-7 RIVER VIEW APT OPP SAVARKAR BHAVAN SHIVAJINAGAR PUNE 411005

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAVLI HINGMIRE AND ASSOCIATES
ArchitectTOMATO ARCHITECTURAL SOLUTIONS PVT LTD
EngineerSPECTRUM CONSULTANTS
PartnerRole in project
SHREE VENKATESH BUILDCON PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Apr 2023

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: NEW FORMAT FORM 5 VENKATESH GRAFFITI PHASE -5-19-4-2023.pdf22 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION WING R and S FINAL.pdf13 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: CONVEYANCE DEED GRAFFITI Q WING - 21-9-2022 PAGE NO-1-100.pdf20 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: CONVEYANCE DEED GRAFFITI Q WING - 21-9-2022 PAGE NO-101-200.pdf20 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: CONVEYANCE DEED GRAFFITI Q WING - 21-9-2022 PAGE NO-201-278.pdf20 Oct 2022
Status of ConveyanceFile: STATUS OF CONVEYANCE DEED GRAFFITI PHASE -5.pdf4 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: VENKATESH GRAFFITI CO-OP HSG SOCIETY FEDERATION LTD CERTIFICATE.pdf21 Jun 2021
Layout approvalFile: 1-2 WING Q LAYOUT ULTRATION.pdf19 Dec 2020
Building plan approvalFile: 2-2 WING Q 13 FLOOR PLAN ALTRATION.pdf19 Dec 2020
Copy of Layout Approval (in case of layout)File: 1-2 WING Q LAYOUT ULTRATION.pdf19 Dec 2020
Building Plan Approval (IOD)File: 2-2 WING Q 13 FLOOR PLAN ALTRATION.pdf19 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: CC GRAFFITI 1435-2020 16-12-2020.pdf19 Dec 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Arch certificate for withdrawal 13-7-20 GRAFFITI PHSAE 5.pdf22 Aug 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: VENKATESH GRAFFITI WING Q SOCIETY CERTIFICATE-3.pdf7 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE FORM 1 GRAFFITI PHASE 5.pdf15 Apr 2020
Certificates of CA (Form 3)File: CA Certiticate Rera Graffiti Phase 5 9-4-20.pdf15 Apr 2020
Certificates of CA (Form 5)File: Form 5 CA Certificate Graffiti Phase 5 3-4-20.pdf15 Apr 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Q WING.pdf15 Apr 2020
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - RERA Arch Certificate Graffiti- Phase 5 - 03042020.pdf15 Apr 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf2 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf2 Mar 2020
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf2 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf4 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf4 Feb 2020
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf4 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf6 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf6 Jan 2020
Form 2AFile: FORM 2A VENKATESH GRAFFITI PHASE 5 DEC 19.pdf6 Jan 2020
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf6 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf7 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf7 Dec 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf7 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE Graffiti Phase 5 Wing Q.pdf3 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf3 Dec 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GR PHASE 5.pdf3 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATRE JOYNEST PH 4.pdf20 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE JOYNEST PH 4.pdf20 Nov 2019
Certificates of CA (Form 3)File: CA CERTIFICATE JOYNEST PH 4.pdf20 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf9 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf9 Nov 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFTITI PHASE 5.pdf9 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf24 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf24 Oct 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf24 Oct 2019
Form 2AFile: FORM 2A GRAFFITI PHASE 5.pdf4 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf23 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf23 Sep 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf23 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf6 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf6 Sep 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf6 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE Venkatesh Graffiti Phase 5 Rera Certificate.pdf26 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf26 Aug 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf26 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE GRAFFITI PHASE 5.pdf2 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5.pdf2 Aug 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5.pdf2 Aug 2019
Form 2AFile: FORM 2 A GRAFFITI PHASE 5 JUN 19.pdf30 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA -Architect Certiticate Graffiti - Phase 5-21062019.pdf24 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE GRAFFITI PHASE 5 1906019.pdf24 Jun 2019
Certificates of CA (Form 3)File: CA CERTIFICATE GRAFFITI PHASE 5 1906019.pdf24 Jun 2019
Form 2AFile: FORM 2A Graffiti Phase 5 MAR-19.pdf10 Apr 2019
Certificates of CA (Form 5)File: Annual Rreport Form 5 Venkatesh Graffiti Phase 5.pdf5 Apr 2019
Form 2AFile: FORM 2A Quality Assurance Certificate Graffiti Phase 5.pdf12 Jan 2019
Copy of the legal title reportFile: Search and Title Report Graffiti Phase 5.pdf30 Nov 2018
Copy of the legal title reportFile: Title Certificate Graffiti Phase 5.pdf30 Nov 2018
Details of encumbrancesFile: No Ebcumbrace Certificate Graffiti Phase 5.pdf30 Nov 2018
Declaration in FORM BFile: Form B Promoter Affidavit.pdf30 Nov 2018
Proforma of Allotment letterFile: Agreement with Allotment Letter Graffiti Phase 5.pdf30 Nov 2018
Certificates of CA (Form 3)File: CA CERTIFICATE VENKATESH GRAFFITI PHASE 5.pdf24 Nov 2018
Layout approvalFile: 01-16.pdf23 Nov 2018
Layout approvalFile: 02-16.pdf23 Nov 2018
Layout approvalFile: 1-3.pdf23 Nov 2018
Building plan approvalFile: 06-16.pdf23 Nov 2018
Building plan approvalFile: 07-16.pdf23 Nov 2018
Building plan approvalFile: 08-16.pdf23 Nov 2018
Building plan approvalFile: 09-16.pdf23 Nov 2018
Building plan approvalFile: 10-16.pdf23 Nov 2018
Building plan approvalFile: 11-16.pdf23 Nov 2018
Building plan approvalFile: 12-16.pdf23 Nov 2018

Promoter's earlier projects23

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

23 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
VENKATESH GRAFFITI ELAN PHASE 2MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036124CompletedJun 2024Sep 2023
VENKATESH GRAFFITI ELAN PHASE 1Sr No 32 2B Manjiri Mundhwa Road Keshav Nagar Mundhwa PUNE 411036125CompletedMay 2024Sep 2023
VENKATESH GRAFFITI GLOVER PHASE 3 - MHADAMUNDHWA MANJIRI ROAD KESHAV NAGAR MUNDHWA PUNE 41103660CompletedSep 2023Aug 2023
VENKATESH GRAFFITI ELITE PHASE 2MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036101CompletedDec 2022Jun 2021
Venkatesh Graffiti Elite Phase 1Sr 31 2 2B Beside Venkatesh Graffiti Open Space 1 Mundhwa Manjari Rd Keshav Nagar PUNE 41103690CompletedAug 2022Nov 2020
VENKATESH GRAFFITI PHASE 6MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036168CompletedDec 2021Jun 2021
VENKATESH NAVITA101 by 7 AMBEGAON KHURD PUNE 411046174CompletedDec 2021Jun 2021
VENKATESH GRAFFITI PHASE 5MUNDHWA MANJARI ROAD KESHAV NAGAR MUNDHWA PUNE 411036104CompletedMar 2021Feb 2020
VENKATESH GRAFFITI PHASE 4MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036100CompletedJul 2020Mar 2019
VENKATESH JOYNEST PHASE - 5PUNE SOLAPUR ROAD LONI KALBHOR PUNE 41220139CompletedMar 2020Dec 2019
VENKATESH JOYNEST PHASE 4PUNE SOLAPUR HIGHWAY LONI KALBHOR PUNE 41220143CompletedDec 2019Nov 2019
VENKATESH GRAFFITI PHASE 3MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 41103664CompletedDec 2019Oct 2018
VENKATESH JOYNEST PHASE 3PUNE SOLAPUR ROAD LONI KALBHOR PUNE 41220186CompletedSep 2019May 2019
VENKATESH LAKE ORCHIDDATTANAGAR JAMBHULWADI ROAD AMBEGAON KHURD PUNE 411046127CompletedDec 2018Dec 2018
VENKATESH GRAFFITI PHASE 2MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036174CompletedDec 2018Jan 2018
VENKATESH LAKE LIFE PHASE 1Venkatesh Lake Life Road Ambegaon Kh Pune 411046189CompletedJun 2018Jun 2018
Venkatesh Joynest Phase 2LONI KALBHOR PUNE 41220143CompletedMay 2018Feb 2018
VENKATESH GRAFFITI PHASE 7KESHAVNAGAR MUNDHWA MANJARI ROAD PUNE 41103628CompletedMar 2018Jan 2018
VENKATESH JOYNEST PHASE 1GAT NO 33 PLUS 34 2 LONI KALBHOR PUNE137CompletedJul 2017Mar 2017
VENKATESH GRAFFITI PHASE 1SR NO 31 PLUS 35 PART KESHAV NAGAR MUNDHWA PUNE 411036358CompletedJul 2017Apr 2017
VENKATESH LAKE VISTASR NO 8 PLUS 9 PART DATTANAGAR JAMBHULWADI ROAD AMBEGAON KHURD PUNE 411046672CompletedDec 2015Feb 2015
VENKATESH BILVAS NO 51 2 2B PLUS 3 DHAYARI GOAN PUNE 41104173CompletedDec 2014Jul 2014
VENKATESH SHARVILSR NO 26 PART DHAYARI PUNE 411041186CompletedMar 2014Jul 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VENKATESH GRAFFITI PHASE 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KESHAV NAGAR MUNDHWA13,700+ in Pune

2 kmVENKATESH GRAFFITI PHASECompleted 86Lapsed / revoked 20Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: SHREE VENKATESH BUILDCON PVT LTD

SHREE VENKATESH BUILDCON PVT LTD has 21 registrations on MahaRERA, including VENKATESH GRAFFITI PHASE 2 and VENKATESH LAKE ORCHID. Its filings disclose 26 earlier MahaRERA projects: declares 26 of 26 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VENKATESH GRAFFITI PHASE 5 is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VENKATESH GRAFFITI PHASE 5?

The registered promoter entity is SHREE VENKATESH BUILDCON PVT LTD, a company as per the filing. Its CIN U45200PN2008PTC132398 and GSTIN 27AANCS1902K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VENKATESH GRAFFITI PHASE 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VENKATESH GRAFFITI PHASE 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VENKATESH GRAFFITI PHASE 5?

The professionals named in the filing: Architect: SAVLI HINGMIRE AND ASSOCIATES; Architect: TOMATO ARCHITECTURAL SOLUTIONS PVT LTD; Engineer: SPECTRUM CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VENKATESH GRAFFITI PHASE 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VENKATESH GRAFFITI PHASE 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VENKATESH GRAFFITI PHASE 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.