SHREE VENKATESH BUILDCON PVT LTD: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
SHREE VENKATESH BUILDCON PVT LTD has 20 registrations in this build, including VENKATESH GRAFFITI PHASE 2 and VENKATESH LAKE ORCHID. Its filings disclose 23 earlier MahaRERA projects: 23 of 23 past projects completed on time.
Projects in this build
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| VENKATESH SHARVIL | 31 Mar 2014 | 9 Jul 2013 | On time |
| VENKATESH BILVA | 31 Dec 2014 | 24 Jul 2014 | On time |
| VENKATESH LAKE VISTA | 31 Dec 2015 | 25 Feb 2015 | On time |
| VENKATESH GRAFFITI PHASE 1 | 31 Jul 2017 | 10 Apr 2017 | On time |
| VENKATESH JOYNEST PHASE 1 | 31 Jul 2017 | 10 Mar 2017 | On time |
| VENKATESH GRAFFITI PHASE 7 | 31 Mar 2018 | 25 Jan 2018 | On time |
| Venkatesh Joynest Phase 2 | 31 May 2018 | 9 Feb 2018 | On time |
| VENKATESH LAKE LIFE PHASE 1 | 30 Jun 2018 | 4 Jun 2018 | On time |
| VENKATESH GRAFFITI PHASE 2 | 31 Dec 2018 | 25 Jan 2018 | On time |
| VENKATESH LAKE ORCHID | 31 Dec 2018 | 26 Dec 2018 | On time |
| VENKATESH JOYNEST PHASE 3 | 30 Sep 2019 | 16 May 2019 | On time |
| VENKATESH GRAFFITI PHASE 3 | 31 Dec 2019 | 22 Oct 2018 | On time |
Frequently asked questions
How do I verify SHREE VENKATESH BUILDCON PVT LTD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHREE VENKATESH BUILDCON PVT LTD?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.