Home / Browse projects / Velstand Phase 2 - formerly Kul scapes

Completed No litigation declared Residential / Group Housing project

Velstand Phase 2 - formerly Kul scapes

By Pathare Family

RG-MH-24060 · RERA P52100005825 · Last updated on MahaRERA portal: 21 Dec 2023

Source: official MahaRERA filing

Red flags

  • 8 complaints at MahaRERA
  • Completion date moved by 41 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2023Possession promisedregistration recorded completed
15 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 99%
8Complaints at MahaRERAon this registration
Jump to the 141 documents Report an error

Velstand Phase 2 - formerly Kul scapes is a Residential / Group Housing project by Pathare Family in Tukaram Nagar, 411014, registered with MahaRERA as P52100005825 on 14 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 41 months from the original filing. 8 complaints are on record with the regulator.

At a glance

Project

  • NameVelstand Phase 2 - formerly Kul scapes
  • TypeResidential / Group Housing
  • Location
    • Magarpatta Road
    • Tukaram Nagar
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005825
  • ReraGenie IDRG-MH-24060

Builder

  • NamePathare Family
  • Entity typeOthers
  • Named personsBapusaheb Tukaram Pathare HUF, Pandharinath Tukaram Pathare HUF

Key dates

this monthRegisteredAug 2017First promiseJul 2020Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Jul 2020)
  • Buildings2 building records
  • Documents filed141 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA270000
B WingNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 99%.

A Wing100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%
B Wing100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 21 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered2
Open Space44
BuildingClosed/CoveredOpen SpaceTotal
A Wing12728
B Wing11718

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,033 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI19102.33
Proposed, not sanctioned9,274 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Pathare Complex Survey No 8 Mundwa ByPass Kharadi Near Radisson Hotel

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Vikas Achalkar
EngineerJW Consultants LLP
Chartered AccountantShah Khandelwal Jain & Associates
PartnerRole in project
Pathare Family-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005010Jul 2020 → Jun 2021

Reason as filed by the promoter1. Before RERA came into force, we had entered into Joint Development Agreement (“JDA”) with Kumar Urban Development Private Limited (“KUDPL”) wherein KUDPL was the developer of the project. Bookings for some of the flats were taken by KUDPL. However, due to financial difficulties of KUDPL, they were unable to take ahead the construction of the said project and therefore the said JDA was cancelled. Thereafter, we started developing the project on our own and named the Project as “Velstand Phase - II”. After registering the project under RERA, there were some unforeseen complications which were

EXT52100011995Jul 2020 → Dec 2022

Reason as filed by the promoterWe, Pathare Family, having our office at Sr.No.9, Tukaram Nagar, Haveli, Pune-411014 with reference to our residential real estate project ‘Velstand Phase 2’ (formerly known as ‘Kulscapes)-MahaRERA Reg No. P52100005825 located at Sr No 8/3 Sr No 9/1/1P Sr.No.9/1/19P, Kharadi, Haveli, Pune-411014 state that the registration for above mentioned project granted under section 5 of the Real Estate (Regulation and Development) Act, 2016(‘RERA’) is valid up to 30th June 2022. However, the project is under completion and requires extension under provisions of Maha RERA. The Construction Industry has b

EXT52100013039Jul 2020 → Jun 2023

Reason as filed by the promoterBefore RERA came into force, we had entered into Joint Development Agreement (“JDA”) with Kumar Urban Development Private Limited (“KUDPL”) wherein KUDPL was the developer of the project. Bookings for some of the flats were taken by KUDPL. However, due to financial difficulties of KUDPL, they were unable to take ahead the construction of the said project and therefore the said JDA was cancelled. Thereafter, we started developing the project on our own and named the Project as “Velstand Phase - II”. After registering the project under RERA, there were some unforeseen complications which were fa

EXT52100016820Jul 2020 → Dec 2023

Reason as filed by the promoterThe project is delayed on account of following reasons: 1. The project is almost completed but some minor finishes are pending. Further, the Promotor has applied for the NOC and completion certificate with the competent Authorities. Further, the Construction Industry has been hit hard due to outbreak of the coronavirus since March 2020. Also, due to the outbreak of coronavirus, the Government had imposed various restrictions and took measures such as lockdown in the country. So the pace of the construction activities was slowed down. The construction work is mainly dependent on unskilled causa

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC005000000010932Nikhil RaneLalit Kumar Jain17/01/2018
CC005000000085502Nikhil RanePathare Family13/05/2021
CC005000000340856Nikhil Shriram RaneSukumar Enviro Farms Pvt. Ltd.03/05/2024
CC005000000010951A N Janardhanan NairLalit Kumar Jain20/01/2018
CC005000000085568SUBHASH SINGH CHOUDHARY THROUGH POWER OF ATTORNEY MUKESH SINGH CHOUDHARYM/s Velstand22/05/2021
CC005000000116936ANIL C AGARWALM/s. Sukumar Enviro Farms Pvt Ltd14/04/2022
CC005000000157331Mr. Ajit Janardhanan Through POA Mr. A.N.Janardhanan NairSukumar Enviro Farms Pvt. Ltd14/07/2022
CC12500552Nikhil Shriram RanePathare Family17/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Dec 2023

Documents filed141

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate.pdf21 Dec 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf19 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: NAME RESERVATION OF SOCIETY.pdf19 Dec 2023
OtherFile: Velstand OC.pdf19 Dec 2023
OtherFile: Velstand Rera From 4.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera_Form_5_Final.pdf6 Nov 2023
Certificates of CA (Form 5)File: Rera_Form_5.pdf28 Oct 2023
Certificates of CA (Form 3)File: FORM 3 VELSTAND.pdf12 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Certificate For Quality Assurance.pdf20 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked Inventory_compressed.pdf20 Jun 2023
Certificates of CA (Form 3)File: 150 Rera From 3 Velstand March 23.pdf20 Jun 2023
Certificates of CA (Form 3)File: Rera From 3 Velstand March 23 DSC_compressed.pdf13 Apr 2023
Certificates of CA (Form 3)File: Rera From 3 Velstand Feb 23 DSC_compressed.pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Velstand Architect Certificate.pdf5 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Velstand Engineer Certificate.pdf5 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Velstand QUALITY ASSURANCE.pdf5 Apr 2023
Disclosure of sold/ booked inventoryFile: Inventory.pdf5 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate velstand_compressed.pdf9 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate_compressed (4).pdf7 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurence velstand _compressed.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: velstand sold unsold_compressed (1).pdf7 Jan 2023
Certificates of CA (Form 3)File: form 3_compressed.pdf7 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VELSTAND ARCHITECT CERTIFICATE_compressed (1).pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE VELSTAND_compressed.pdf7 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEERS QUALITY ASSURANCE CERTIFICATE VELSTAND_compressed.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSILD INVENTORY VELSTAND_compressed.pdf7 Oct 2022
Certificates of CA (Form 3)File: From - 3 Velstand phase 2 DSC_compressed.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 with Annexures Signed V1 Velstand.pdf30 Sep 2022
Certificates of CA (Form 5)File: Form 5 Final along with Annexures Signed.pdf28 Sep 2022
OtherFile: Form 5 Final along with Annexures Signed.pdf28 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VELSTAND ARCHITECT CERTIFICATE_compressed.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE VELSTAND_compressed.pdf7 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEERS QUALITY ASSURANCE CERTIFICATE VELSTAND_compressed.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: VELSTAND SOLD UNSOLD_compressed.pdf7 Jul 2022
Certificates of CA (Form 3)File: form 3 velstand-compressed_compressed.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate Q4 Velstand.pdf11 Apr 2022
Certificates of CA (Form 3)File: Form 3 Velstand Q4 Final.pdf11 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Compressed.pdf8 Apr 2022
Disclosure of sold/ booked inventoryFile: VELSTAND SOLD UNSOLD INVENTORY compressed.pdf8 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Velstand Engineer Certificate_compressed.pdf5 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Velstand Quality Assurance Certificate_compressed.pdf5 Apr 2022
OtherFile: RERA CERTIFICATE.pdf6 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VELSTAND Architect Certificate Rera Feb 2022.pdf3 Mar 2022
Certificates of CA (Form 3)File: Signed Form 3-Velstand.pdf2 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance certificate ( compressed).pdf25 Feb 2022
Disclosure of sold/ booked inventoryFile: sold unsold 24-02-2022_compressed (1)_compressed (1)-compressed.pdf25 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VELSTAND ENGINEERS CERTIFICATE.pdf11 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: velstand_compressed.pdf9 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance certificate velstand.pdf9 Jan 2022
Disclosure of sold/ booked inventoryFile: Velstand Disclosure of sold_compressed.pdf9 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-compressed.pdf7 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE-compressed.pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEERS ASSURANCE CERTIFICATE-compressed.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Velstand Dt- 30-09-2021-compressed.pdf7 Oct 2021
Certificates of CA (Form 3)File: Form 3 Signed_compressed.pdf7 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rera Audit Form 5 Final.pdf28 Sep 2021
Certificates of CA (Form 3)File: Form 3 Signed.pdf24 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate FY- 19-20.pdf16 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate FY- 20-21.pdf16 Aug 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf13 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE 30-06-2021.pdf13 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf13 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory Velstand.pdf13 Aug 2021
Building plan approvalFile: B P LAYOUT.pdf5 Jul 2021
Layout approvalFile: D P LAYOUT.pdf5 Jul 2021
Copy of Layout Approval (in case of layout)File: D P LAYOUT.pdf5 Jul 2021
Building Plan Approval (IOD)File: B P LAYOUT.pdf5 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: DP Layout CC No 0447-21_compressed.pdf28 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: BP Layout CC No 0447-21 (1)_compressed (1).pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Inventory Details_compressed.pdf28 Jun 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_19-36_a.pdf11 Mar 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_19-36_a.pdf11 Mar 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_19-36_a.pdf11 Mar 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_1-18_a.pdf11 Mar 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_37-54_a.pdf11 Mar 2021
Copy of the legal title reportFile: Title Search Report FY- 16-17_19-36_a.pdf11 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 final.pdf1 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf17 Jul 2020
Copy of the legal title reportFile: Title Search 5-08-2019_compressed.pdf24 Dec 2019
Details of encumbrancesFile: Encumberance Certificate_compressed (1).pdf24 Dec 2019

Keep Velstand Phase 2 - formerly Kul scapes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tukaram Nagar

Builder: Pathare Family

Pathare Family has 1 registration on MahaRERA, including Velstand Phase 2 - formerly Kul scapes. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if Velstand Phase 2 - formerly Kul scapes is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Velstand Phase 2 - formerly Kul scapes?

The registered promoter entity is Pathare Family, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Velstand Phase 2 - formerly Kul scapes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Velstand Phase 2 - formerly Kul scapes?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Velstand Phase 2 - formerly Kul scapes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Velstand Phase 2 - formerly Kul scapes?

The professionals named in the filing: Architect: Ar Vikas Achalkar; Engineer: JW Consultants LLP; Chartered Accountant: Shah Khandelwal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Velstand Phase 2 - formerly Kul scapes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Velstand Phase 2 - formerly Kul scapes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Velstand Phase 2 - formerly Kul scapes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.