ReraGenieLog inGet a buyer report

Home / Browse projects / VASTU VIRAM

Completed No litigation declared Residential / Group Housing project

VASTU VIRAM

By SACHIN SURESH GAWADE

RG-MH-20846 · RERA P52100012563 · Last updated on MahaRERA portal: 23 Jan 2020

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2017Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 16 documents Report an error

VASTU VIRAM is a Residential / Group Housing project by SACHIN SURESH GAWADE in 411014, registered with MahaRERA as P52100012563 on 4 Sep 2017. The registration is recorded completed; possession was promised by 31 Dec 2017.

At a glance

Project

  • NameVASTU VIRAM
  • TypeResidential / Group Housing
  • Location
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100012563
  • ReraGenie IDRG-MH-20846

Builder

  • NameSACHIN SURESH GAWADE
  • Entity typeIndividual

Key dates

this monthRegisteredSep 2017PromisedDec 2017Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Sep 2017
  • Promised completion31 Dec 2017
  • Revised completionNone
  • Buildings1 building record
  • Documents filed16 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VASTU VIRAMNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

VASTU VIRAM: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area583 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
VIMAL RAMRAO THITE-Pune
RAM SAHEBRAO THITE-Pune
RAM VITHALRAO SAKOREShirurPune
ROHAN RAM SAKOREShirurPune

Approvals and building plan

Permissible FSI651.0
Proposed, not sanctioned394 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHAKAN BRANCH PUNE 410501

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRABHAKAR RAMDAS KAMTHE
EngineerRAMCHANDRA RANDHAVE
PartnerRole in project
SACHIN SURESH GAWADE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011203Dec 2017 → Dec 2022

Reason as filed by the promoterWork not completed. Because non availability of funds

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Jan 2020

Documents filed16

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Vastu Viram.pdf23 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: Arch Doc.pdf23 Jan 2020
Details of encumbrancesFile: Encumbrances Certificate.pdf1 Aug 2017
Certificates of CA (Form 3)File: Form 3.pdf1 Aug 2017
Layout approvalFile: Layout 3.pdf31 Jul 2017
Building plan approvalFile: Building approval.pdf31 Jul 2017
PAN CardFile: pan31072017.pdf31 Jul 2017
Copy of the legal title reportFile: Vastushilp_builders_TITLE_SEARCH.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 3.pdf31 Jul 2017
Building Plan Approval (IOD)File: Building approval.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIficate.pdf31 Jul 2017
Declaration in FORM BFile: Form B Affidavit by PromoteR.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi Certi 1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi Certi 2.pdf31 Jul 2017
Proforma of Allotment letterFile: Draft Agreement of RERA.pdf31 Jul 2017

Keep VASTU VIRAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

Builder: SACHIN SURESH GAWADE

SACHIN SURESH GAWADE has 1 registration on MahaRERA, including VASTU VIRAM. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if VASTU VIRAM is delayed beyond 31 Dec 2017?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VASTU VIRAM?

The registered promoter entity is SACHIN SURESH GAWADE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VASTU VIRAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VASTU VIRAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VASTU VIRAM?

The professionals named in the filing: Architect: PRABHAKAR RAMDAS KAMTHE; Engineer: RAMCHANDRA RANDHAVE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASTU VIRAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASTU VIRAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASTU VIRAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.