Home / Browse projects / Pune, Maharashtra / Vasant Vihar Co-operative Housing Society
Vasant Vihar Co-operative Housing Society
By Kotibhaskar Infrastructures &Developers Pvt.Ltd.
RG-MH-08606 · RERA P52100004322 · Last updated on MahaRERA portal: 13 Oct 2021
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 27 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vasant Vihar Co-operative Housing Society is a Residential / Group Housing project by Kotibhaskar Infrastructures &Developers Pvt.Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100004322 on 9 Aug 2017. The registration is recorded completed; possession was promised by 19 Dec 2019.
At a glance
Project
- NameVasant Vihar Co-operative Housing Society
- TypeResidential / Group Housing
- Location
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004322
- ReraGenie IDRG-MH-08606
Builder
- NameKotibhaskar Infrastructures &Developers Pvt.Ltd.
- Entity typeCompany
- CINU45209PN2011PTC140254
- GSTIN27AAQCS2145B1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorsDilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar
- ChairpersonsChidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar
- Other registrations27 more →
- Completed15 of 28
- No longer live1 lapsed, de-registered or revoked
- Past their filed date2
- Declared earlier projects11 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Aug 2017
- Promised completion19 Dec 2019
- Revised completionNone
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vasant Vihar Co-operative Housing Limited | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.
Vasant Vihar Co-operative Housing Limited: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 13 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | Yes | 50% |
Parking filed84
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shinde Joshi & Associates |
| Engineer | Dr A B Kulkarni & Associates |
| Partner | Role in project |
|---|---|
| Kotibhaskar Infrastructures &Developers Pvt.Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 May 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration certificate - Vasantvihar_compressed.pdf | 13 Oct 2021 |
| Certificates of CA (Form 5)File: Form 5.pdf | 6 Jun 2019 |
| Certificates of Architect (Form 4)File: VV Form 4.PDF | 30 May 2019 |
| Building plan approvalFile: DWG1_compressed.pdf | 16 May 2019 |
| Building Plan Approval (IOD)File: DWG1_compressed.pdf | 16 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC1_compressed.pdf | 16 May 2019 |
| Building plan approvalFile: DWG1.pdf | 2 May 2018 |
| Building plan approvalFile: DWG2.pdf | 2 May 2018 |
| Building plan approvalFile: DWG3.pdf | 2 May 2018 |
| Building plan approvalFile: DWG4.pdf | 2 May 2018 |
| Building plan approvalFile: DWG5.pdf | 2 May 2018 |
| Building plan approvalFile: DWG6.pdf | 2 May 2018 |
| Building plan approvalFile: DWG7.pdf | 2 May 2018 |
| Building plan approvalFile: DWG8.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG1.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG2.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG3.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG4.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG5.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG6.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG7.pdf | 2 May 2018 |
| Building Plan Approval (IOD)File: DWG8.pdf | 2 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC1.pdf | 2 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Vasant Vihar Commencement.pdf | 16 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Vasant Vihar Commencement.pdf | 15 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vasant Vihar Engineer Certificate.PDF | 28 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vasant Vihar Engineer Certificate.PDF | 28 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vasant Vihar Engineer Certificate.PDF | 28 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vasant Vihar Engineer Certificate.PDF | 28 Oct 2017 |
| Building plan approvalFile: DWG8.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: DWG8.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: vasantvihar architect form 1.PDF | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vasant Vihar Engineer Certificate.PDF | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Vasant_Vihar ca certificate.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: Vasant Vihar Form B RERA Declaration.PDF | 24 Jul 2017 |
| Building plan approvalFile: DWG1.pdf | 18 Jul 2017 |
| Building plan approvalFile: DWG9.pdf | 18 Jul 2017 |
| Layout approvalFile: DWG1.pdf | 18 Jul 2017 |
| Details of encumbrancesFile: DEED OF SIMPLE MORTGAGE VASANT VIHAR - INDEX II.pdf | 18 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: DWG1.pdf | 18 Jul 2017 |
| Building Plan Approval (IOD)File: DWG1.pdf | 18 Jul 2017 |
| Building Plan Approval (IOD)File: DWG9.pdf | 18 Jul 2017 |
| Proforma of Allotment letterFile: Vasant Vihar-Agreement draft as per RERA.pdf | 18 Jul 2017 |
| Copy of the legal title reportFile: VASANTVIHAR TITLE REPORT.PDF | 5 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Vasant Vihar C C 25 10 2016.pdf | 5 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Vasant Vihar CC 28 12 2016.PDF | 5 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Vasantvihar CC 31 03 2017 page 1.pdf | 5 Jul 2017 |
Promoter's earlier projects11
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| INDUKIRAN CO-OP HOUSING SOCIETY LIMITEDP52100046237 | KOTHRUD, Pune | 1 | Jun 2022 | Completed | Nov 2025 | Oct 2024 |
| SARITA CHSLP52100034229 | KOTHRUD, Pune | 70 | Mar 2022 | Completed | Oct 2025 | May 2025 |
| Purva HeightsP53100034113 | Warnali, Sangli | 36 | Mar 2022 | Completed | Sep 2025 | Mar 2025 |
| PRABHAKAR CHSLP52100049315 | Pune, Pune | - | Feb 2023 | Completed | Jul 2025 | Apr 2025 |
| Kajal Co operative Housing Society LtdP52100032652 | Kothrud, Pune | 67 | Jan 2022 | Ongoing | Dec 2024 | Not delivered |
| MUKUNDP52100045860 | MAHARSHI KARVENAGAR, Pune | - | Jun 2022 | Completed | May 2024 | Late, Jun 2024 |
| SHUBHASHREEP52100045350 | PUNE, Pune | - | May 2022 | Completed | Mar 2024 | Late, Jun 2024 |
| Annapurna | Hingane Budruk Haveli Pune | 5 | - | Completed | Dec 2017 | Jun 2017 |
| Ankoorshree Co-operative Housing Society | Happy Colony Lane 3 Kothrud Pune | 21 | - | Completed | Oct 2017 | May 2017 |
| Snehvardhan Co-operative Housing Society | Patwardhan Co-operative Housing Society | 20 | - | Completed | May 2017 | Jan 2017 |
| Chinar Co-operative Housing Society | Kothrud Pune | 24 | - | Completed | Mar 2014 | Mar 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 27 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
Keep Vasant Vihar Co-operative Housing Society on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kothrud13,700+ in Pune
Filed coordinates, straight-line distance. 350 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: Kotibhaskar Infrastructures &Developers Pvt.Ltd.
Kotibhaskar Infrastructures &Developers Pvt.Ltd. has 28 registrations on MahaRERA, including Sugam Cooperative Housing Society Limited and Vasant Vihar Co-operative Housing Society. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Vasant Vihar Co-operative Housing Society is delayed beyond 19 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vasant Vihar Co-operative Housing Society?
The registered promoter entity is Kotibhaskar Infrastructures &Developers Pvt.Ltd., a company as per the filing. Its CIN U45209PN2011PTC140254 and GSTIN 27AAQCS2145B1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vasant Vihar Co-operative Housing Society?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vasant Vihar Co-operative Housing Society?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vasant Vihar Co-operative Housing Society?
The professionals named in the filing: Architect: Shinde Joshi & Associates; Engineer: Dr A B Kulkarni & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vasant Vihar Co-operative Housing Society?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback