Home / Browse projects / Pune, Maharashtra / Vasant Ganesh Vishwa Phase II

Registered No litigation declared Residential / Group Housing project

Vasant Ganesh Vishwa Phase II

By Panjabrao Vasantrao Shinde

RG-MH-17010 · RERA P52100029656 · Last updated on MahaRERA portal: 14 Jan 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 36 months from the original
16 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 90%
56 of 96Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

Vasant Ganesh Vishwa Phase II is a Residential / Group Housing project by Panjabrao Vasantrao Shinde in Pune, Maharashtra, registered with MahaRERA as P52100029656 on 14 Jun 2021. Possession is promised by 31 Dec 2028. The completion date has moved by 36 months from the original filing. 40 of the 96 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVasant Ganesh Vishwa Phase II
  • TypeResidential / Group Housing
  • Location
    • Patil Nagar
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100029656
  • ReraGenie IDRG-MH-17010

Builder

  • NamePanjabrao Vasantrao Shinde
  • Entity typeIndividual
  • Named personPanjabrao Vasantrao Shinde

Key dates

this monthRegisteredJun 2021First promiseDec 2025Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jun 2021
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed94 files

Current status

42%40 of 96 units booked
80.3%Work done, per cost certificate

Figures as on 14 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing DNA8848048
Wing ENA8848048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.

Wing D81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Wing E81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes90%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Santosh DangdeBavadhan BKPune
Suvarna DagadeBavadhan BKPune
Khandu Tukaram DagadeBavadhan BKPune
Pandurang DagadeBavadhan BKPune
Pruthviraj DagadeBavadhan BKPune
snehal DagadeBavadhan BKPune
Omraj DagadeBavadhan BKPune
Nanasaheb DagadeBavadhan BKPune
Nirmala DagadeBavadhan BKPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI3507.24
Proposed, not sanctioned3,507 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBAVDHAN
Estimated costRs 12.34 cr
Cost incurredRs 9.90 cr
Work done80.3%
BuildingWingEstimatedIncurred
Wing DNARs 12.34 crRs 9.90 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCubix Architects Associates
EngineerShivbhusan Dhoter
Chartered AccountantJayesh Jain
Chartered AccountantSPAK & Co.
Chartered AccountantPravin Pise
Chartered AccountantVaibhav Bhise
PartnerRole in project
Panjabrao Vasantrao Shinde-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA06012619321Dec 2025 → Dec 2028

Reason as filed by the promoterThe project could not be completed within the approved timeline due to unavoidable delays caused by labour shortages, intermittent disruption in availability of construction materials, and delays in statutory approvals from concerned authorities. These factors were beyond the control of the Promoter and impacted the progress of construction.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601107ajay bhika morePanjabrao Vasantrao Shinde28/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Feb 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2021-2022)File: Form 2A.pdf14 Jan 2026
Form 2A (FY 2022-2023)File: Form 2A.pdf14 Jan 2026
Form 2A (FY 2023-2024)File: Form 2A.pdf14 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf14 Jan 2026
Form 1File: Form 1 - VGVP2 - Mar 25.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 25_compressed.pdf29 Dec 2025
Form 3File: F3-MARCH-25.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - MAR 25.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Dec 24.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Dec 24_compressed.pdf29 Dec 2025
Form 3File: F3-DEC-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - DEC 24.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Sep 24.pdf29 Dec 2025
Form 3File: F3-SEPT-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - SEP 24.pdf29 Dec 2025
Form 2File: F2 - Sep 24 - VGVP2.pdf29 Dec 2025
Form 2File: F2 - Jun 24 - VGVP2.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Jun 24.pdf29 Dec 2025
Form 3File: F3-JUNE-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - JUN 24.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 24.pdf29 Dec 2025
Form 3File: F3-MARCH-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - MAR 24.pdf29 Dec 2025
Form 2File: F2 - Mar 24 - VGVP 2.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 24.pdf29 Dec 2025
Form 2File: F2 - Mar 24 - VGVP 2.pdf29 Dec 2025
Form 3File: F3-MARCH-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - MAR 24.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 24.pdf29 Dec 2025
Form 2File: F2 - Mar 24 - VGVP 2.pdf29 Dec 2025
Form 3File: F3-MARCH-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - MAR 24.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 24.pdf29 Dec 2025
Form 2File: F2 - Mar 24 - VGVP 2.pdf29 Dec 2025
Form 3File: F3-MARCH-24.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - MAR 24.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 3File: F3-MARCH-23_VGVP2 (1).pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 23.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 3File: F3-MARCH-23_VGVP2 (1).pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 23.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 3File: F3-MARCH-23_VGVP2 (1).pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 23.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 23.pdf29 Dec 2025
Form 3File: F3-MARCH-23_VGVP2 (1).pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 23.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 3File: F3-MARCH-22_compressed.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 22.pdf29 Dec 2025
Form 3File: F3-MARCH-22_compressed.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 22.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 3File: F3-MARCH-22_compressed.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 22.pdf29 Dec 2025
Form 1File: Form 1 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 2File: Form 2 - VGVP2 - Mar 22.pdf29 Dec 2025
Form 3File: F3-MARCH-22_compressed.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: SU - Mar 22.pdf29 Dec 2025
Form 5 (FY 2021-2022)File: FORM 5 FY 2021-22.pdf29 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25.pdf29 Dec 2025
Form 5 (FY 2022-2023)File: FORM 5 FY 2022-23.pdf29 Dec 2025
Form 5 (FY 2023-2024)File: FORM 5 FY 2023-24.pdf29 Dec 2025
Withdrawal Update Form 1File: Form 1 - VGVP2 - Jun 25.pdf25 Dec 2025
Withdrawal Update Form 1File: Form 1 - VGVP2 - Sep 25.pdf25 Dec 2025
Withdrawal Update Form 2File: Form 2 - VGVP2 - Jun 25_compressed.pdf25 Dec 2025
Withdrawal Update Form 2File: Form 2 - VGVP2 - Sep 25_compressed.pdf25 Dec 2025
Withdrawal Update Form 3File: F3-JUNE-25.pdf25 Dec 2025
Withdrawal Update Form 3File: F3-SEPT-25.pdf25 Dec 2025
Copy of the legal title reportFile: LEGALTITLE REPORT-1-8.pdf3 Jun 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT-9-16.pdf3 Jun 2021

How this compares with Pune

42%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vasant Ganesh Vishwa Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavadhan BK13,700+ in Pune

Builder: Panjabrao Vasantrao Shinde

Panjabrao Vasantrao Shinde has 1 registration on MahaRERA, including Vasant Ganesh Vishwa Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Vasant Ganesh Vishwa Phase II is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vasant Ganesh Vishwa Phase II?

The registered promoter entity is Panjabrao Vasantrao Shinde, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vasant Ganesh Vishwa Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vasant Ganesh Vishwa Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vasant Ganesh Vishwa Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vasant Ganesh Vishwa Phase II?

The professionals named in the filing: Architect: Cubix Architects Associates; Engineer: Shivbhusan Dhoter; Chartered Accountant: Jayesh Jain; Chartered Accountant: SPAK & Co.; Chartered Accountant: Pravin Pise; Chartered Accountant: Vaibhav Bhise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vasant Ganesh Vishwa Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vasant Ganesh Vishwa Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vasant Ganesh Vishwa Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.