Home / Browse projects / Mumbai City, Maharashtra / VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT

Registration lapsed Litigation declared Residential / Group Housing project

VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT

By VARDHMAN DEVELOPERS LTD

RG-MH-28480 · RERA P51900026521 · Last updated on MahaRERA portal: 12 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Rs 228.00 crore secured on the land, in favour of Vardhman Developers Limited

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
1 of 11Construction stages donefurthest along: Stilt Floor, 75%
19 of 29Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT is a Residential / Group Housing project by VARDHMAN DEVELOPERS LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900026521 on 30 Sep 2020. Possession was promised by 30 Jun 2024 and is now 28 months past that date. 10 of the 29 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameVARDHMAN FLORA PHASE -II - VARDHMAN HABITAT
  • TypeResidential / Group Housing
  • Location
    • RAMBHAU BHOGALE MARG
    • GHODAPDEO
    • Mumbai City
    • 400033
  • Pincode400033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900026521
  • ReraGenie IDRG-MH-28480

Builder

  • NameVARDHMAN DEVELOPERS LTD
  • Entity typeCompany
  • ChairpersonRAMESH BABULAL VARDHAN
  • Managing DirectorRAJESH BABULAL VARDHAN
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

28 months past promisethis monthRegisteredSep 2020PromisedJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Sep 2020
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed100 files

Current status

34%10 of 29 units booked

Figures as on 12 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CD BUILDINGNA262329029

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 75%.

CD BUILDING: 34% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor75%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,701 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofVardhman Developers Limited
Secured amountRs 228.00 crore
CERSAI search filedYes
Declared on4 Jun 2026
LandownerVillageDistrict
MR VIJAY KASHIRAM BHINGARDE & MR KAMLESH KOTHARIMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI1293.47
Proposed, not sanctioned313 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, MANEKJI WADIA BUILDING , NANIK MOTWANI MARG, FORT, MUMBAI - 400001

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKALPESH SHAH
EngineerMR SHANKEY BAFNA
Chartered AccountantShravan Gandhi
Chartered AccountantTodi Tulsyan & Co
Chartered AccountantManish Ranpariya
PartnerRole in project
VARDHMAN DEVELOPERS LTD-

Litigation declared1

CaseCourtStatus
1543/2017BOMBAY CITY CIVILDraft Issues

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12400161Manoj Kumar MishraVARDHMAN DEVELOPERS LTD20/09/2024
CC12501138Rohit Tejbahadur SinghVARDHMAN DEVELOPERS LTD05/04/2025
CC12600852-VARDHMAN DEVELOPERS LTD15/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 as on 31_03_2022.pdf12 Jun 2026
Form 2File: Form 2 as on 31_03_2022.pdf12 Jun 2026
Form 3File: FORM 3_ as on 31_3_22_ signed.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure as on 31_03_2022.pdf12 Jun 2026
Form 1File: FORM 1_as on 31_3_23.pdf12 Jun 2026
Form 2File: FORM 2_as on 31_3_23.pdf12 Jun 2026
Form 3File: FORM 3_as on 31_3_23_signed.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure as on 31_3_23.pdf12 Jun 2026
Form 1File: Form 1 as on 30 06 2023.pdf12 Jun 2026
Form 2File: Form 2 as on 30 06 2023.pdf12 Jun 2026
Form 3File: Form 3 as on 30 06 2023.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure as on 30 06 2023.pdf12 Jun 2026
Form 1File: Form 1 as on 30 09 2023.pdf12 Jun 2026
Form 2File: Form 2 as on 30 09 2023.pdf12 Jun 2026
Form 3File: Form 3 as on 30 09 2023.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure as on 30 09 2023.pdf12 Jun 2026
Form 1File: Form 1 as on 31_12_2023.pdf12 Jun 2026
Form 2File: form 2 as on_31_12_23.pdf12 Jun 2026
Form 3File: FORM 3 as on 31_12_23.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure 31_12_23.pdf12 Jun 2026
Form 1File: Form 1 as on 31_3_24.pdf12 Jun 2026
Form 2File: form 2 as on_31_3_24.pdf12 Jun 2026
Form 3File: FORM 3 as on 31_03_24.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure 31_3_24.pdf12 Jun 2026
Form 1File: Form 1 30_6_24.pdf12 Jun 2026
Form 2File: form 2 30_6_24.pdf12 Jun 2026
Form 3File: FORM 3 30_06_24.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure 30_6_24.pdf12 Jun 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vardhman Habitat Form 1 31_12_2023.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vardhman habitat Form 1 31_3_2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vardhman habitat Form 1 30_6_2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vardhman habitat Form 1 30_9_2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_31_12_24.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 31_12_2023_Habitat.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 31_03_2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 30_06_2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 30_09_2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 31_12_2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 as on_31_12_23.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 as on_31_3_24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_June 2024 habitat.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_Sept 2024 habitat.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_Dec 2024 habitat.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 FY_21_22 phase 2.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 FY_2022_23 phase2.pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: habitat mar 2023.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: habitat june 20023.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: habitat sept2023.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 31_03_2022.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 31 03 2023.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 30 06 2023.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 30 09 2023.pdf13 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: habitat Form 2A 2020-21.pdf13 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: habitat Form 2 A 22-23.pdf13 Feb 2024
Disclosure of sold/ booked inventoryFile: vardhman habitat.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ as on 31_3_22_ signed.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_as on 31_3_23_signed.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vardhman habitat 30 6 2023_signed-compressed.pdf13 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vardhman habitat 30 9 2023_signed-compressed.pdf13 Feb 2024
Details of encumbrancesFile: HABITAT.pdf7 Jul 2021
Proforma of Allotment letterFile: habitat Sale Agreement draft.pdf7 Jul 2021
Details of encumbrancesFile: Scan10001.PDF25 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Certificate Wing CD.pdf25 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 25SEPT.pdf25 Sep 2020
Building plan approvalFile: Amended ISSUE letter.pdf24 Sep 2020
Building plan approvalFile: 0001-min.pdf24 Sep 2020
Building plan approvalFile: 0002-min.pdf24 Sep 2020
Building plan approvalFile: 0003-min.pdf24 Sep 2020
Building plan approvalFile: 0004-min.pdf24 Sep 2020
Building plan approvalFile: 0005-min.pdf24 Sep 2020
Building plan approvalFile: 0006-min.pdf24 Sep 2020
Building plan approvalFile: 0007-min.pdf24 Sep 2020
Building plan approvalFile: 0008-min-min.pdf24 Sep 2020
Building plan approvalFile: 0009-min-compressed.pdf24 Sep 2020
Building plan approvalFile: 0010-min.pdf24 Sep 2020
Building plan approvalFile: 0011-min-min.pdf24 Sep 2020
Building plan approvalFile: 0012-min.pdf24 Sep 2020
Building plan approvalFile: 0013-min.pdf24 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Amended ISSUE letter.pdf24 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: 0001-min.pdf24 Sep 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VARDHMAN GALAXYMUMBAI74CompletedDec 2014Late, Oct 2015
VARDHMAN VISTAMUMBAI38CompletedApr 2014Late, Oct 2014

How this compares with Mumbai City

34%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHODAPDEO780+ in Mumbai City

2 kmVARDHMAN FLORA PHASE -IICompleted 3Lapsed / revoked 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: VARDHMAN DEVELOPERS LTD

VARDHMAN DEVELOPERS LTD has 6 registrations on MahaRERA, including VARDHMAN EMPIRE and VARDHMAN GRANDEUR. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

The registered promoter entity is VARDHMAN DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

The professionals named in the filing: Architect: KALPESH SHAH; Engineer: MR SHANKEY BAFNA; Chartered Accountant: Shravan Gandhi; Chartered Accountant: Todi Tulsyan & Co; Chartered Accountant: Manish Ranpariya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.