Home / Browse projects / Mumbai City, Maharashtra / VARDHMAN FLORA PHASE I

Registered No litigation declared Residential / Group Housing project

VARDHMAN FLORA PHASE I

By VARDHMAN DEVELOPERS LTD

RG-MH-20407 · RERA P51900008829 · Last updated on MahaRERA portal: 27 Feb 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 36 months
  • 3 extensions taken
  • Rs 228.00 crore secured on the land, in favour of Land T Infrastructure Finance Company Limited

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 72%
40 of 113Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

VARDHMAN FLORA PHASE I is a Residential / Group Housing project by VARDHMAN DEVELOPERS LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900008829 on 19 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 73 of the 113 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameVARDHMAN FLORA PHASE I
  • TypeResidential / Group Housing
  • Location
    • RAMBHAU BHOGALE MARG
    • GHODAPDEO
    • Mumbai City
    • 400033
  • Pincode400033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900008829
  • ReraGenie IDRG-MH-20407

Builder

  • NameVARDHMAN DEVELOPERS LTD
  • Entity typeCompany
  • ChairpersonRAMESH BABULAL VARDHAN
  • Managing DirectorRAJESH BABULAL VARDHAN
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed136 files

Current status

65%73 of 113 units booked

Figures as on 27 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AAANA57501130113

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 72%.

AAA: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure72%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises38%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.42%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 27 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes20%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed200

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots200
Closed/Covered200

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,701 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofLand T Infrastructure Finance Company Limited
Secured amountRs 228.00 crore
CERSAI search filedYes
Declared on4 Feb 2026
LandownerVillageDistrict
VIJAY KASHIRAM BHINGARDE AND KAMLESH KOTHARIMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI11025.04
Proposed, not sanctioned5,081 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Manekji Wadia Building, Nanik Motwani Marg, Fort, Mumbai - 400001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKALPESH SHAH
EngineerShankey Bafna
Chartered AccountantTODI TULSYAN & CO
Chartered AccountantManish B Ranpariya
PartnerRole in project
VARDHMAN DEVELOPERS LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018272Dec 2023 → Dec 2024

Reason as filed by the promoterThe Project got delayed due to complete lock down in vicinity of the project because of COVID-19 and coupled with acute scarcity of workers. Most workers had left to their native places for longer time after COVID. Keeping in view of the above genuine hardship and difficulties, project construction work got affected and caused delay in completion thereof. Therefore, we need extension for the project by one year under section 6 of RERA from the declared date of completion on 30.12.2023 till 29.12.2024.

EXT51900027323Dec 2023 → Dec 2025

Reason as filed by the promoterThat we have taken project loan from L&T finance (The NBFC) & that NBFC was having financial strain which had impacted disbursement of the loan on time as and when required for the smooth construction activities of the project. Ultimately the NBFC had closed real estate finance only disbursing 60% loan. This incident impacted badly the timely progress of the project. 5. That in addition to the aforesaid reasons, the project was badly impacted due to consequential impact of COVID pandemic, labour problems, recovery from the allottees, fresh booking was big challenge, etc. That we are clear and

EA04022619703Dec 2023 → Dec 2026

Reason as filed by the promoterThat we have taken project loan from L&T finance (The NBFC) & that NBFC was having financial strain which had impacted disbursement of the loan on time as and when required for the smooth construction activities of the project. Ultimately the NBFC had closed real estate finance only disbursing 60% loan. This incident impacted badly the timely progress of the project. 5. That in addition to the aforesaid reasons, the project was badly impacted due to consequential impact of COVID pandemic, labour problems, recovery from the allottees, fresh booking was big challenge, etc. That we are clear and

Litigation declared11

CaseCourtStatus
887/2016SMALL CAUSE COURTISSUES
888/2016SMALL CAUSE COURTISSUES
889/2016SMALL CAUSE COURTISSUES
890/2016SMALL CAUSE COURTISSUES
1411/2015SMALL CAUSE COURTISSUES
1412/2015SMALL CAUSE COURTISSUES
1413/2015SMALL CAUSE COURTISSUES
380/2013SMALL CAUSE COURTHEARING ON AMENDMENT APPLICATION
1971/2014BOMBAY CITY CIVILISSUES
4328/2013BOMBAY CITY CIVILISSUES
1089/2014BOMBAY CITY CIVILHEARING ON SPECIFIC RELIEF

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000196105Mrs. Mangal Namdev ShindeM/s Vardhman Developers Ltd.22/02/2021
CC006000000196106NAMDEV DHONDIBA SHINDEM/S VARDHMAN DEVELOPERS LTD.22/02/2021
CC006000000196107MRS. MANGAL NAMDEV SHINDEM/S VARDHMAN DEVELOPERS LTD.22/02/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A.pdf27 Feb 2026
Form 5 (FY 2024-2025)File: Form 5.pdf27 Feb 2026
Form 1File: ARCHITEC CERTIFICATE 31_03_2025.pdf2 Feb 2026
Form 2File: ENGINEER CERTIFICATE 31_03_2025.pdf2 Feb 2026
Form 3File: CA CERTIFICATE 31_03_2025.pdf2 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 31_03_2025.pdf2 Feb 2026
Form 1File: ARCHITEC CERTIFICATE 30_06_2025.pdf2 Feb 2026
Form 2File: ENGINEER CERTIFICATE 30_06_2025.pdf2 Feb 2026
Form 3File: CA CERTIFICATE - 30_06_2025.pdf2 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 30_06_2025.pdf2 Feb 2026
Form 1File: ARCHITEC CERTIFICATE 30_09_2025.pdf2 Feb 2026
Form 2File: ENGINEER CERTIFICATE 30_09_2025.pdf2 Feb 2026
Form 3File: CA CERTIFICATE 30_09_2025.pdf2 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 30_09_2025.pdf2 Feb 2026
Form 1File: ARCHITEC CERTIFICATE 31_12_2025.pdf2 Feb 2026
Form 2File: ENGINEER CERTIFICATE 31_12_2025.pdf2 Feb 2026
Form 3File: CA CERTIFICATE 31_12_2025.pdf2 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 31_12_2025.pdf2 Feb 2026
Declaration in FORM BFile: Rs 500 stamp paper_Form B.pdf27 Feb 2025
Certificates of CA (Form 5)File: Form 5-comp.pdf31 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 flora 31122024.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vardhman Flora Form 1 31_12_2023.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vardhman Flora Form 1 30_6_2024.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vardhman Flora Form 1 30_9_2024.pdf28 Jan 2025
Certificates of CA (Form 3)File: Form3 Flora_30_06_2024.pdf28 Jan 2025
Certificates of CA (Form 3)File: Form3 Flora_30_09_2024.pdf28 Jan 2025
Certificates of CA (Form 3)File: Form3 Flora_31_12_2024.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 as on_31_12_23.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31_3_24.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_300624.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_300924.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 _301224.pdf28 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_FY 23-24.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure abt inventory as on 31_12_24.pdf27 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 FY_21_22 Phase1.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 FY_22_23 phase 1.pdf16 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Flora mar 2023.pdf9 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Flora june 2023.pdf9 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Flora sept 2023.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vardhman Flora Form-2 as on 31_03_2022.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vardhman Flora Form-2 as on 31_03_2023.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vardhman Flora Form-2 as on 30_06_2023.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vardhman Flora Form-2 as on 30_09_2023.pdf9 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A 21 22 Vardhman Flora.pdf9 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A 22 23 Vardhman Flora.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: vardhman flora.pdf9 Feb 2024
Certificates of CA (Form 3)File: Form 3 as on 31_03_2022_signed.pdf9 Feb 2024
Certificates of CA (Form 3)File: Form 3 as on 31_03_2023_signed.pdf9 Feb 2024
Certificates of CA (Form 3)File: Form 3_as on 30_6_23_signed.pdf9 Feb 2024
Certificates of CA (Form 3)File: Flora Form 3_as on 30_9_23_signed.pdf9 Feb 2024
Certificates of CA (Form 3)File: Form 3 Flora (1).pdf25 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: flora march 2022.pdf22 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Flora June 2022.pdf22 Jul 2022
Certificates of CA (Form 3)File: FORM 3.pdf22 Jul 2022
Certificates of CA (Form 5)File: FORM 5.pdf22 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 2196593_furthercc_signed.pdf10 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: CC REVALIDATION.pdf10 Jan 2022
Certificates of CA (Form 5)File: Annual Report VDL.pdf7 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FLORA-min.pdf1 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FLORA-min.pdf1 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-compressed.pdf25 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch-compressed.pdf25 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg.pdf25 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg.pdf25 Mar 2019
Certificates of CA (Form 3)File: ca flora.pdf25 Mar 2019
Certificates of CA (Form 5)File: form 5.pdf25 Mar 2019
Building plan approvalFile: 0001-min.pdf20 Nov 2018
Building plan approvalFile: 0002-min.pdf20 Nov 2018
Building plan approvalFile: 0003-min.pdf20 Nov 2018
Building plan approvalFile: 0004-min.pdf20 Nov 2018
Building plan approvalFile: 0005-min.pdf20 Nov 2018
Building plan approvalFile: 0006-min.pdf20 Nov 2018
Building plan approvalFile: 0007-min.pdf20 Nov 2018
Building plan approvalFile: 0008-min-min.pdf20 Nov 2018
Building plan approvalFile: 0009-min-compressed.pdf20 Nov 2018
Building plan approvalFile: 0010-min.pdf20 Nov 2018
Building plan approvalFile: 0011-min-min.pdf20 Nov 2018
Building plan approvalFile: 0012-min.pdf20 Nov 2018
Building plan approvalFile: 0013-min.pdf20 Nov 2018
Building Plan Approval (IOD)File: 0001-min.pdf20 Nov 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VARDHMAN GALAXYMUMBAI74CompletedDec 2014Late, Oct 2015
VARDHMAN VISTAMUMBAI38CompletedApr 2014Late, Oct 2014

How this compares with Mumbai City

65%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 36 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDHMAN FLORA PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHODAPDEO780+ in Mumbai City

2 kmVARDHMAN FLORA PHASE ICompleted 10Lapsed / revoked 16Other 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: VARDHMAN DEVELOPERS LTD

VARDHMAN DEVELOPERS LTD has 6 registrations on MahaRERA, including VARDHMAN EMPIRE and VARDHMAN GRANDEUR. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if VARDHMAN FLORA PHASE I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHMAN FLORA PHASE I?

The registered promoter entity is VARDHMAN DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHMAN FLORA PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VARDHMAN FLORA PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VARDHMAN FLORA PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHMAN FLORA PHASE I?

The professionals named in the filing: Architect: KALPESH SHAH; Engineer: Shankey Bafna; Chartered Accountant: TODI TULSYAN & CO; Chartered Accountant: Manish B Ranpariya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHMAN FLORA PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHMAN FLORA PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHMAN FLORA PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.