Registration lapsed No litigation declared Residential / Group Housing project

VALENCIA

By HEKS INFRASTRUCTURE & DEVELOPERS

RG-MH-21143 · RERA P51900006034 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date
  • Completion date moved by 96 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 95%
3 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

VALENCIA is a Residential / Group Housing project by HEKS INFRASTRUCTURE & DEVELOPERS in Mumbai City, Maharashtra, registered with MahaRERA as P51900006034 on 14 Aug 2017. Possession was promised by 31 Jul 2026 and is now 3 months past that date. The completion date has moved by 96 months from the original filing. 21 of the 24 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameVALENCIA
  • TypeResidential / Group Housing
  • Location
    • PAREL
    • MUMBAI
    • Mumbai City
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900006034
  • ReraGenie IDRG-MH-21143

Builder

  • NameHEKS INFRASTRUCTURE & DEVELOPERS
  • Entity typePartnership
  • PartnersHUMAYUN SHAFIAHMED SHAIKH, ESOOF SHOEB CONTRACTOR, HOZAIFA SHOEB CONTRACTOR

Key dates

3 months past promisethis monthRegisteredAug 2017First promiseJul 2018Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 Jul 2026
  • Revised completionRevised to 31 Jul 2026 (originally 31 Jul 2018)
  • Buildings1 building record
  • Documents filed104 files

Current status

88%21 of 24 units booked
91.8%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VALENCIANA222023124

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

VALENCIA: 97% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises94%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes92%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes92%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered8

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area463 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025

Approvals and building plan

Permissible FSI2910.1
Proposed, not sanctioned2,910 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDR A B NAIR MARG OPP MUMBAI CENTRAL STATION, MUMBAI 400008
Estimated costRs 13.58 cr
Cost incurredRs 12.48 cr
Work done91.85%
BuildingWingEstimatedIncurred
VALENCIANARs 13.07 crRs 12.25 cr
-NARs 51.70 lakhRs 23.18 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHAFEEZ CONTRACTOR
Architectmoham
EngineerJW CONSULTANTS LLP
EngineerDIpesh Joshi
EngineerIDRIS DOHADWALA
Chartered AccountantBSN & ASSOCIATES
Chartered AccountantMOHAN L GUPTA & ASSOCIATES
PartnerRole in project
HEKS INFRASTRUCTURE & DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900011319Jul 2018 → Jan 2024

Reason as filed by the promotern accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 78.95% allottees for purpose of extension of RERA registration period of the said project.

EXT51900025246Jul 2018 → Jul 2025

Reason as filed by the promoterWe are unable to complete the Project on time due to some financial crises but we are trying to close asap with all the formalities & compliance. Its a humble requested to grant for Extension upto 30.7.2025.

EA13082502370Jul 2018 → Jul 2026

Reason as filed by the promoterThe Project is nearing completion. We anticipate wrapping up the primary tasks very soon.To ensure the full and proper utilization of the remaining FSI. we kindly request a one-year extension. This additional time will allow us to make further necessary amendments and consume the balance FSI effectively.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Aug 2019

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arch val jun26.pdf30 Jul 2026
Withdrawal Update Form 2File: Eng val jun26.pdf30 Jul 2026
Withdrawal Update Form 3File: CA val jun26.pdf30 Jul 2026
Withdrawal Update Form 1File: Arch cert Val mar26.pdf3 Jun 2026
Withdrawal Update Form 2File: Eng cert val_mar26.pdf3 Jun 2026
Withdrawal Update Form 3File: CA CERT VAL MAR26.pdf3 Jun 2026
Withdrawal Update Form 1File: Arch cet val dec25.pdf24 Apr 2026
Withdrawal Update Form 2File: ENG CER VAL DEC25.pdf24 Apr 2026
Withdrawal Update Form 3File: ENG CER VAL DEC25.pdf24 Apr 2026
Withdrawal Update Form 1File: ARCH SEP25 VAL.pdf2 Dec 2025
Withdrawal Update Form 2File: Eng Cert sep25_val..pdf2 Dec 2025
Withdrawal Update Form 3File: RERA FORM 3 VALENCIA Q2.pdf2 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 vale_22-23.pdf26 Aug 2025
Form 5 (FY 2023-2024)File: Form 5_23-24 val.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: disc sold valen.pdf26 Jun 2025
Form 1File: ARCH VAL MAR25.pdf26 Jun 2025
Form 2File: ENG CER VALMAR25.pdf26 Jun 2025
Form 3File: CA CERT VAL MAR25.pdf26 Jun 2025
Self-declaration of Quarterly ProgressFile: QPR_Val.pdf26 Jun 2025
Certificates of CA (Form 3)File: CA CERT VAL MAR25_compressed.pdf7 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH VAL MAR25.pdf17 Apr 2025
Certificates of CA (Form 3)File: CA CERT VAL DEC24_compressed.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER VALMAR25.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT_VAL_DEC24.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT_VAL_DEC24.pdf28 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_23-24 val.pdf19 Dec 2024
Declaration in FORM BFile: FORM B - 31-07-25_Valencia.pdf16 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT VAL JUNE24.pdf16 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT VAL SEP24.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: disc sold valen.pdf16 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200331045822_For_Asset_Based_Search_11_12_2024_14_39_02_589.pdf16 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200331045769_For_Asset_Based_Search_11_12_2024_14_38_43_529.pdf16 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Val.pdf16 Dec 2024
Proforma of Allotment letterFile: ALLOTMENT-VALENCIA.pdf28 Nov 2024
Proforma of Agreement for saleFile: Valencia Agreement Draft.pdf28 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disc_esoof.pdf25 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disc_tabrez.pdf25 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disc_hozefa.pdf25 Nov 2024
Certificates of CA (Form 3)File: CA CER VAL SEP 2024_compressed.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT VAL SEP24.pdf13 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT-JUN24-VAL.pdf20 Aug 2024
Certificates of CA (Form 3)File: CA MAR 24-VAL.pdf20 Aug 2024
Certificates of CA (Form 3)File: CA JUNE24-VAL.pdf20 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A_val_21-22.pdf26 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A_val_22-23.pdf26 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A_val_23-24.pdf26 Jun 2024
Certificates of CA (Form 3)File: FORM3-Vale_2023_compressed.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert_22-23_valen.pdf8 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert-valencia_jan-dec2023.pdf8 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch_valenc_jan -mar24.pdf8 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-18-19-val (1).pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-19-20-val (1).pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-20-21-val (1).pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-21-22-val (1).pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert_22-23_valen (1).pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-23-24-val (1).pdf31 May 2024
Certificates of CA (Form 3)File: Form3 Valenc_upto 23.pdf30 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 vale_22-23.pdf30 Mar 2024
Declaration about Commencement CertificateFile: Velencia Revalidate.pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: Valencia updated 29_compressed.pdf17 May 2022
Commencement Certificates / NA Order for plotted developmentFile: revalidated Cc.pdf14 Jan 2022
Declaration about Commencement CertificateFile: Form 32 Valencia.pdf14 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A Valencia Apr 2019_compressed.pdf14 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A Valencia Apr 2020_compressed.pdf14 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A Valencia Apr 2021_compressed.pdf14 Jan 2022
Disclosure of sold/ booked inventoryFile: Circular 29 Valencia.pdf14 Jan 2022
CERSAI detailsFile: Valencia.pdf14 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: VALANCIA form 5 2018-19.pdf14 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VALANCIA form 5 2019-20.pdf14 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: VALANCIA form 5 2020-21a.pdf14 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VALENCIA ARCH CERTIFICATE FORM 1 V1.pdf28 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VALENCIA NOC LETTER FOR OC.pdf28 Aug 2019
Building plan approvalFile: 1.pdf30 Jan 2018
Building plan approvalFile: 2.pdf30 Jan 2018
Building plan approvalFile: 1 Rev plan 18 Dec 17.pdf30 Jan 2018
Building plan approvalFile: 2 Rev plan 18 Dec 17.pdf30 Jan 2018
Building plan approvalFile: 3 Rev plan 18 Dec 17.pdf30 Jan 2018
Building Plan Approval (IOD)File: 1.pdf30 Jan 2018
Building Plan Approval (IOD)File: 2.pdf30 Jan 2018
Building Plan Approval (IOD)File: 1 Rev plan 18 Dec 17.pdf30 Jan 2018

How this compares with Mumbai City

88%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 96 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VALENCIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI780+ in Mumbai City

2 kmVALENCIACompleted 46Lapsed / revoked 37Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: HEKS INFRASTRUCTURE & DEVELOPERS

HEKS INFRASTRUCTURE & DEVELOPERS has 1 registration on MahaRERA, including VALENCIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that VALENCIA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VALENCIA is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VALENCIA?

The registered promoter entity is HEKS INFRASTRUCTURE & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VALENCIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VALENCIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VALENCIA?

The professionals named in the filing: Architect: HAFEEZ CONTRACTOR; Architect: moham; Engineer: JW CONSULTANTS LLP; Engineer: DIpesh Joshi; Engineer: IDRIS DOHADWALA; Chartered Accountant: BSN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VALENCIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VALENCIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VALENCIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.