ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / Ruparel Jewel

Registered No litigation declared Residential / Group Housing project

Ruparel Jewel

By Renuka Realtors

RG-MH-08962 · RERA P51900003058 · Last updated on MahaRERA portal: 25 Aug 2026

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken
  • Rs 130.00 crore secured on the land, in favour of Vistra ITCL

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 73%
106 of 191Units unsoldnot recorded sold or booked
12Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

Ruparel Jewel is a Residential / Group Housing project by Renuka Realtors in Mumbai City, Maharashtra, registered with MahaRERA as P51900003058 on 4 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 85 of the 191 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 12 complaints are on record with the regulator.

At a glance

Project

  • NameRuparel Jewel
  • TypeResidential / Group Housing
  • Location
    • JERBAIWADIA ROAD
    • PAREL/ SEWREE
    • Mumbai City
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900003058
  • ReraGenie IDRG-MH-08962

Builder

  • NameRenuka Realtors
  • Entity typePartnership
  • PartnersAmit Ruparel, Sarvesh Builders India Pvt Ltd
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2022)
  • Buildings1 building record
  • Documents filed133 files

Current status

45%85 of 191 units booked
67.5%Work done, per cost certificate

Figures as on 25 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ruparel JewelNA776017417191

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 73%.

Ruparel Jewel: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure73%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises62%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes30%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed397

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots397
Closed/Covered397

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,864 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofVistra ITCL
Secured amountRs 130.00 crore
CERSAI search filedYes
Declared on27 Mar 2026
LandownerVillageDistrict
Rubberwala Hsg & Infrasturcture Ltd.Mumbai CityMumbai City
Kantilal KothariMumbai CityMumbai City

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI10941.24
Proposed, not sanctioned10,941 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHANE
Estimated costRs 499.88 cr
Cost incurredRs 337.49 cr
Work done67.51%
BuildingWingEstimatedIncurred
Ruparel JewelNARs 499.88 crRs 337.49 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Kamathi
EngineerAjay Pandurang Gade
EngineerJW Consultants LLP
Chartered AccountantShereena Jose Jacob
Chartered AccountantSarveshwar Sharma
PartnerRole in project
Renuka Realtors-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900005723Dec 2022 → Dec 2023

Reason as filed by the promoterDue to typographical error

EXT51900027082Dec 2022 → Dec 2026

Reason as filed by the promoterWe, M/s. Renuka Realtors, the promoter of the project “Ruparel Jewel” (RERA Registration No. P51900003058), respectfully submit this application for an extension of the project completion date to 31st December 2026 under the provisions of Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The RERA certificate issued on 09th September 2021 is valid until 30th December 2024. However, due to unforeseen and uncontrollable circumstances, the project has encountered delays, as elaborated below: Change in DCPR Regulation The implementation of the Development Control and Promotion

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000195122Raseek Jivraj HariyaRenuka Realtors11/12/2020
CC006000000079284Nirmal Kumar JainM/s Renuka Realtors21/05/2019
CC006000000197535Nirmalkumar JainM/s Renuka Realtors08/07/2021
CC006000000079383Arvind Kumar JainM/S Renuka Realtors21/05/2019
CC006000000197544Mr. Arvindkumar JainM/s Renuka Realtors08/07/2021
CC006000000161293Bharat M Panchal and Jaswant M PanchalM/S Rubberwala Housing and Infrastructure Ltd.22/10/2019
CC006000000251496RASSEEK JIVARAJ HARIYAM/s. Renuka Realtors16/06/2022
CC006000000396848Jitendra Gulab ShuklaM/s Renuka Realtors02/08/2023
CC006000000540742SRINIVAS GOPALRENUKA REALTORS12/06/2024
CC12501002Kishan Jawaharlal GuptaRenuka Realtors22/03/2025
CC12502616Rumana Jujar LokhandwalaRenuka Realtors29/07/2025
CC12604506Disha ParikhRenuka Realtors18/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Aug 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC Further Extended upto 45th Floor as per IOA 181024 dt 020626.pdf25 Aug 2026
Withdrawal Update Form 1File: Form 1 Ruparel Jewel 31032026.pdf25 Aug 2026
Withdrawal Update Form 1File: Form-1 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 1File: Form-1 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 2File: Form 2 Ruparel Jewel 31032026.pdf25 Aug 2026
Withdrawal Update Form 2File: Form-2 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 2File: Form-2 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 3File: Form 3 Ruparel Jewel 31032026.pdf25 Aug 2026
Withdrawal Update Form 3File: Form-3 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 3File: Form-3 Ruparel Jewel 30062026.pdf25 Aug 2026
Withdrawal Update Form 1File: Form 1 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 1File: Form 1 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 2File: Form 2 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 2File: Form 2 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 3File: Form 3 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 3File: Form 3 Ruparel Jewel.pdf28 Jul 2026
Withdrawal Update Form 1File: Form 1 Ruparel Jewel 31122025.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2 Ruparel Jewel 31122025.pdf30 Mar 2026
Withdrawal Update Form 3File: Form 3 Ruparel Jewel 31122025.pdf30 Mar 2026
Withdrawal Update Form 1File: Form 1 Ruparel Jewel 31122025.pdf27 Mar 2026
Withdrawal Update Form 2File: Form 2 Ruparel Jewel 31122025.pdf27 Mar 2026
Withdrawal Update Form 3File: Form 3 Ruparel Jewel 31122025.pdf27 Mar 2026
Form 1File: Form 1 Ruparel Jewel 30062025.pdf26 Mar 2026
Form 2File: Form 2 Ruparel Jewel 30062025.pdf26 Mar 2026
Form 3File: Form 3 Ruparel Jewel 30062025.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ruparel Jewel 30062025.pdf26 Mar 2026
Form 1File: Form 1 Ruparel Jewel 30092025.pdf26 Mar 2026
Form 2File: Form 2 Ruparel Jewel 30092025.pdf26 Mar 2026
Form 3File: Form 3 Ruparel Jewel 30092025.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ruparel Jewel 30092025.pdf26 Mar 2026
Form 1File: Form 1 Ruparel Jewel 31122025.pdf26 Mar 2026
Form 2File: Form 2 Ruparel Jewel 31122025.pdf26 Mar 2026
Form 3File: Form 3 Ruparel Jewel 31122025.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ruparel Jewel 31122025.pdf26 Mar 2026
Form 1File: Form 1 Ruparel Jewel 31032025.pdf27 May 2025
Form 2File: Form 2 Ruparel Jewel 31032025.pdf27 May 2025
Form 3File: Form 3 Ruparel Jewel 31032025.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Ruparel Jewel Sold Unsold Inventory 31032025.pdf27 May 2025
Self-declaration of Quarterly ProgressFile: Self Delcaration Letter Ruparel Jewel.pdf27 May 2025
Form 1File: 4 Form 1 Architect Certificate Jewel 31 12 24.pdf21 May 2025
Form 2File: Form 2 Ruparel Jewel 31122024 Final.pdf21 May 2025
Form 3File: Form 3 Ruparel Jewel Final Compressed.pdf21 May 2025
Form 5 (FY 2023-2024)File: Form 5 Jewel FY 23-24.pdf19 May 2025
Layout approvalFile: 1.pdf1 Feb 2025
Layout approvalFile: 1.pdf1 Feb 2025
Layout approvalFile: 2.pdf1 Feb 2025
Layout approvalFile: 3.pdf1 Feb 2025
Layout approvalFile: 4.pdf1 Feb 2025
Layout approvalFile: 5.pdf1 Feb 2025
Layout approvalFile: 6.pdf1 Feb 2025
Layout approvalFile: 7.pdf1 Feb 2025
Layout approvalFile: 8.pdf1 Feb 2025
Layout approvalFile: 9.pdf1 Feb 2025
Layout approvalFile: 10.pdf1 Feb 2025
Layout approvalFile: 11.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 1.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 2.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 3.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 4.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 5.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 6.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 7.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 8.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 9.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 10.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 11.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 1.pdf1 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ruparel Jewel 31122024 Final.pdf1 Feb 2025
Declaration in FORM BFile: Form B Ruparel Jewel Final.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Ruparel Jewel Sold Unsold Inventory 311224.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Ruparel Jewel Sold Unsold Inventory 311224.pdf23 Jan 2025
Declaration about Commencement CertificateFile: Format D Declaration cum Undertaking Ruparel Jewel.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 2023.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A March 2024.pdf23 Jan 2025
Certificates of CA (Form 3)File: Form 3 Ruparel Jewel Final Compressed.pdf7 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Jewel FY 22-23.pdf7 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Jewel FY 23-24.pdf7 Jan 2025
Declaration in FORM BFile: 3 FORM B Jewel Renuka Realtors.pdf4 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form 1 Architect Certificate Jewel 31 12 24.pdf4 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: 1 Sale CC Re endorsed.pdf4 Jan 2025

How this compares with Mumbai City

45%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 48 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ruparel Jewel on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PAREL/ SEWREE780+ in Mumbai City

2 kmRuparel JewelCompleted 42Lapsed / revoked 31Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: Renuka Realtors

Renuka Realtors has 2 registrations on MahaRERA, including Ruparel Jewel and Ruparel Millennia. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Ruparel Jewel is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ruparel Jewel?

The registered promoter entity is Renuka Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ruparel Jewel?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ruparel Jewel?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ruparel Jewel?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ruparel Jewel?

The professionals named in the filing: Architect: Rahul Kamathi; Engineer: Ajay Pandurang Gade; Engineer: JW Consultants LLP; Chartered Accountant: Shereena Jose Jacob; Chartered Accountant: Sarveshwar Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ruparel Jewel?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ruparel Jewel. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ruparel Jewel to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.