Home / Browse projects / Mumbai Suburban, Maharashtra / VAAYU

Registered No litigation declared Residential / Group Housing projectRedevelopment

VAAYU

By KOLTE-PATIL DEVELOPERS LIMITED

RG-MH-29590 · RERA P51800029034 · Last updated on MahaRERA portal: 7 Nov 2026

Why this is marked a redevelopment: this filing shows a redevelopment, tenant or alternate accommodation document on file. MahaRERA has no redevelopment field, so this is ReraGenie's reading of the filing. Redevelopment across Mumbai Suburban.

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 13 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 27 months from the original
29 of 44Construction stages doneacross 4 buildings; furthest along: Stilt Floor, 0%
48 of 161Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

VAAYU is a Residential / Group Housing project by KOLTE-PATIL DEVELOPERS LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029034 on 23 Apr 2021. Possession is promised by 30 Apr 2027. The completion date has moved by 27 months from the original filing. 113 of the 161 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete.

At a glance

Project

  • NameVAAYU
  • TypeResidential / Group Housing
  • Location
    • Laxman Mhatre Road
    • village mandpeshwar
    • Dahisar west
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029034
  • ReraGenie IDRG-MH-29590

Builder

  • NameKOLTE-PATIL DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200PN1991PLC129428
  • GSTIN27AAACK7310G1ZT
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Joint Managing DirectorYashvardhan Rajesh Patil
  • Executive DirectorMilind Digambar Kolte
  • Other registrations63 more →
  • Completed14 of 64
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredApr 2021First promiseJan 2025Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Apr 2021
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Jan 2025)
  • Buildings4 building records
  • Documents filed115 files

Current status

70%113 of 161 units booked
93.6%Work done, per cost certificate

Figures as on 7 Nov 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing A ground floor to 20th floorNA272777077
Wing A 21st floor to 32nd floor ProposedNA121244044
Wing BNA252535035
Wing CNA2525505

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 7 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 0%.

Wing A ground floor to 20th floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing A 21st floor to 32nd floor Proposed0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed270

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots270
Closed/Covered253
Open Space17
BuildingClosed/CoveredOpen SpaceTotal
Wing A ground floor to 20th floor81081
Wing A 21st floor to 32nd floor Proposed40848
Wing B70474
Wing C62567

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,995 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Aug 2026
LandownerVillageDistrict
Sagar Vaibhav Co-operative Housing Society LimitedBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI15373.69
Proposed, not sanctioned12,350 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor, Fortune 2000, Bandra Kurla Complex, Mumbai
Estimated costRs 102.44 cr
Cost incurredRs 95.89 cr
Work done93.61%
BuildingWingEstimatedIncurred
Wing A ground floor to 20th floorNARs 67.73 crRs 63.42 cr
-NARs 34.71 crRs 32.47 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectReza Kabul
EngineerUmang Shah
Chartered AccountantSPCM & Associates
Chartered AccountantVIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS
Chartered AccountantCA Nikita Bajaj
PartnerRole in project
KOLTE-PATIL DEVELOPERS LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA05082622022Jan 2025 → Apr 2027

Reason as filed by the promoterWe have registered project under the name and style "Vaayu" vide MahaRERA registration No. P51800029034. The project consists of 3 (Three) Wings namely Wings A, B and C. The proposed completion date for Wings B and C was 31t January, 2024 and for Wing C it was 31St January, 2025. The proposed completion date for the entire project was 31t January, 2025. With respect to Wings A, B and C we have to inform you as under: The construction of Wings B and C is completed and we have received full Occupation Certificate on 20th June, 2024 from Competent Authority with respect to Wing B and C. The copy

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architects certificate_VAAYU.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate_VAAYU.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate_VAAY.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate_VAAYU.pdf7 Nov 2026
Withdrawal Update Form 1File: Architects certificate_VAAYU.pdf7 Nov 2026
Withdrawal Update Form 2File: Form-2 Sagar Vaibhav-Vaayu.pdf7 Nov 2026
Withdrawal Update Form 2File: Form-2 Sagar Vaibhav-Vaayu.pdf7 Nov 2026
Withdrawal Update Form 2File: Plannerfy form 2_20251016172627.pdf7 Nov 2026
Withdrawal Update Form 2File: VAAYU form 2_20260119180232.pdf7 Nov 2026
Withdrawal Update Form 2File: VAAYU FORM 2_20260418133542.pdf7 Nov 2026
Withdrawal Update Form 2File: VAAYU FORM 2_20260720181334.pdf7 Nov 2026
Withdrawal Update Form 2File: VAAYU FORM - 2_20261019162219.pdf7 Nov 2026
Withdrawal Update Form 3File: Form-3 Sagar Vaibhav-Vaayu.pdf7 Nov 2026
Withdrawal Update Form 3File: Form-3 Sagar Vaibhav-Vaayu.pdf7 Nov 2026
Withdrawal Update Form 3File: Signed Form-3 Vaayu.pdf7 Nov 2026
Withdrawal Update Form 3File: VAAYU Form 3 Signed.pdf7 Nov 2026
Withdrawal Update Form 3File: Signed Form 3 Sagar vaibhav.pdf7 Nov 2026
Withdrawal Update Form 3File: Signed Form3 Sagar Vaibhav.pdf7 Nov 2026
Withdrawal Update Form 3File: Signed Form3 Sagar Vaibhav.pdf7 Nov 2026
Form 2A (FY 2021-2022)File: Form 2A - Vaayu_2022.pdf7 Nov 2026
Form 2A (FY 2022-2023)File: Form 2A - Vaayu_2023.pdf7 Nov 2026
Form 2A (FY 2023-2024)File: Form 2A - Vaayu_2024.pdf7 Nov 2026
Form 2A (FY 2024-2025)File: Form 2A - Vaayu_2025.pdf7 Nov 2026
Form 2A (FY 2025-2026)File: Form 2A -Vaayu_2026.pdf7 Nov 2026
Form 5 (FY 2024-2025)File: Form 5_FY25.pdf7 Nov 2026
Form 5 (FY 2025-2026)File: Form 5_FY26.pdf7 Nov 2026
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf4 Aug 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf4 Aug 2026
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf4 Aug 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaayu form 3_Signed 1.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sagar Vaibhav.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: VAAYU (SAGAR VAIBHAV) INVENTORY.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Vaayu (Sagar Vaibhav) - Rera Data dec 23.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Vaayu ( Sagar Vaibhav ) Rera Data Mar 24.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA DATA - SAGAR VAIBHAV (VAAYU) jun 24.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA DATA-SAGAR VAIBHAV (VAAYU) sep 24.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA DATA-SAGAR VAIBHAV (VAAYU) dec 24.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sagar Vaibhav_Vaayu.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sagar Vaibhav - Vaayu.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Vaayu.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Vaayu.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VAAYU.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sagar Vaibhav-Vaayu.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sagar Vaibhav-Vaayu.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sagar vaibhav Vaayu.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaayu.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vaayu.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vaayu.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vaayu.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vaayu.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaayu.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Vaayu.pdf29 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sagar Vaibhav Society - Vaayu.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaayu Sagar Vaibhav.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate-March-23_ Sagar Vaibhav.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: VAAYU RERA.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vaayu_20230415131301.pdf20 Apr 2023
CERSAI detailsFile: Cersai Details KPDL.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaayu.pdf13 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vaayu.pdf19 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Vaayu.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate - Vaayu.pdf16 Jan 2023
CERSAI detailsFile: Final File Cersai.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: VAAYU RERA.pdf11 Jan 2023
Details of encumbrancesFile: Vaayu.pdf7 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Vaayu.pdf2 Nov 2022
Disclosure of sold/ booked inventoryFile: Vaayu RERA 20221018115636.pdf19 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sagar Vaibhav 30 09 2022 Signed.pdf19 Oct 2022
CERSAI detailsFile: Cersai Report.pdf18 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate Vaayu.pdf15 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Certificate_Vaayu.pdf30 Sep 2022

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

13 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
EVARAP51800026949Borivali, Mumbai Suburban-Nov 2020CompletedOct 2024Oct 2024
24K Stargaze - J BuildingP52100027791Bavdhan, Pune-Jan 2021CompletedJun 2024Jun 2024
Western AvenueP52100000917Wakad, Pune-Jul 2017CompletedDec 2023Registered original: Dec 2022Jan 2023
24K StargazeP52100018473Bavdhan, Pune-Nov 2018CompletedMar 2023Mar 2023
Redevelopment of Jai Vijay CHSL - Phase IP51800004446Vile-Parle (East), Mumbai Suburban-Aug 2017CompletedSep 2022Registered original: Sep 2019Sep 2022
24K ATRIAP52100000428Vishal Nagar, Pimple Nilakh, Pune-Jul 2017CompletedDec 2021Dec 2021
STARGAZEP52100009722Bavadhan BK, Pune-Aug 2017CompletedDec 2018Dec 2018
Ivy Estate Umang PremierP52100000655WAGHOLI, Pune-Jul 2017CompletedSep 2018Sep 2018
GLITTERATIP52100006257Pimpri Chinchawad (M Corp.), Pune-Aug 2017CompletedJun 2018Jun 2018
GLITTERATI IIP52100000319Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedApr 2018Registered original: Dec 2017Apr 2018
Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase IP51800008272Andheri, Mumbai Suburban-Aug 2017CompletedMar 2018Registered original: Dec 2017Mar 2018
GlitteratiPimple Nilakh Pune - 411014187-CompletedApr 2016Apr 2016
City BayDhole-Patil road Pune-41100127-CompletedApr 2014Apr 2014

How this compares with Mumbai Suburban

70%of this project is bookeddistrict median 29%
35%of Mumbai Suburban projects moved their completion datethis one moved by 27 months
20%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,900+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAAYU on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dahisar west6,900+ in Mumbai Suburban

2 kmVAAYUCompleted 82Lapsed / revoked 56Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 275 registered projects within 2 km.

Builder: KOLTE-PATIL DEVELOPERS LIMITED

KOLTE-PATIL DEVELOPERS LIMITED has 64 registrations on MahaRERA, including 24K OPULA and 24K ATRIA. Its filings disclose 14 earlier MahaRERA projects: declares 13 of 14 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VAAYU is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAAYU?

The registered promoter entity is KOLTE-PATIL DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200PN1991PLC129428 and GSTIN 27AAACK7310G1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAAYU?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VAAYU?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAAYU?

The professionals named in the filing: Architect: Reza Kabul; Engineer: Umang Shah; Chartered Accountant: SPCM & Associates; Chartered Accountant: VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS; Chartered Accountant: CA Nikita Bajaj. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAAYU?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAAYU. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAAYU to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.