Home / Browse projects / Mumbai Suburban, Maharashtra / A and O EMINENTE

Registered No litigation declared Others project

A and O EMINENTE

By ASHAPURA HOUSING PRIVATE LIMITED

RG-MH-24747 · RERA P51800005475 · Last updated on MahaRERA portal: 17 Mar 2023

Source: official MahaRERA filing

Red flags

  • 93 complaints at MahaRERA
  • Completion date moved by 66 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 66 months from the original
0 of 11Construction stages donefurthest along: Stilt Floor, 95%
93Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

A and O EMINENTE is a Others project by ASHAPURA HOUSING PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005475 on 11 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 66 months from the original filing. 93 complaints are on record with the regulator.

At a glance

Project

  • NameA and O EMINENTE
  • TypeOthers
  • Location
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005475
  • ReraGenie IDRG-MH-24747

Builder

  • NameASHAPURA HOUSING PRIVATE LIMITED
  • Entity typeCompany

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A and O EMINENTE- WING A TO ENA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

A and O EMINENTE- WING A TO E: 49% average across the applicable activities

ActivityProgress
Excavation93%
Basement (if any)87%
Podiums (if any)0%
Plinth87%
Stilt Floor95%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises42%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 17 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes25%
Solid Waste Management And DisposalYes25%
Water conservation /Rain water harvestingYes25%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable

Parking filed119

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots119
Closed/Covered119

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,554 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI25962.19
Proposed, not sanctioned17,003 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch82, MEENA APT, HILL ROAD, BANDRA WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA ULHAS PAGNIS
EngineerGIREESH M RAJADHYAKSHA
PartnerRole in project
ASHAPURA HOUSING PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800015080Jun 2021 → Dec 2026

Reason as filed by the promoterSince 19 August 2019 until 23 June 2020 were we awaiting further approvals from SRA which were long delayed and due to which the construction of the project which was targeted to be completed could not be achieved. Moreover from middle of the March 2020 our work of construction got completely stopped due to COVID-19 Pandemic and due to resultant prolonged lock-down that took place. The labourers / workers migrated to their native places / states and hence even after partial lifting of lockdown, the availability of labourers / workers were meagre and hence the required work could not be underta

EXT51800009953Jun 2021 → Jun 2022

Reason as filed by the promoter1.The Promoter is hereby making an application for extension of the Project registration as the Promoter was unable to complete the Project due to force majeure conditions i.e. due delay in approvals granted by the Slum Rehabilitation Authority (“SRA”) and due to lock-down announced by the Govt. of India as well as the Govt. of Maharashtra in order to curb the spread of the Coronavirus Disease (“COVID-19") 2.In view of the aforesaid curbs and measures imposed by the Governments, the Promoter had to stop all activities and construction work of the Project 3.Moreover, due to the ongoing lockdown

Litigation declared1

CaseCourtStatus
147/14/51-52/16/2016Controller of Stamps PuneCLOSED FOR ORDERS

Complaints filed with MahaRERA93

Case no.ComplainantRespondentFiled
CC006000000344299malcolm dsouzaAshapura Housing Private Limited10/02/2023
CC006000000057431Sanjay ShahAshapura Housing Pvt Ltd26/12/2018
CC006000000078250Nilesh PatelAshapura Housing Pvt Ltd25/02/2019
CC006000000193264Saurabh SrivastavaAshapura Housing Private Limited03/06/2020
CC006000000193740Shreedhar BangarAshapura Housing Pvt Ltd21/08/2020
CC006000000193743Apurva ChikaniAshapura Housing Pvt Ltd21/08/2020
CC006000000193744Nilay ChikaniAshapura housing Pvt Ltd21/08/2020
CC006000000193746Saurabh AdhiyaAshapura Housing Ltd21/08/2020
CC006000000193748Sagar KumavatAshapura Housing Ltd21/08/2020
CC006000000193749Meenakshi SawantAshapura Housing Ltd21/08/2020
CC006000000193799Masarat SayyedAshapura Housing PvtLtd21/08/2020
CC006000000193800Xerxes CardozoAshapura Housing Pvt Ltd21/08/2020
CC006000000193801Seema BinrajkaAshapura Housing Pvt Ltd21/08/2020
CC006000000193833Ajay BhorawatAshapura Housing pvtltd11/11/2020
CC006000000196051Vitesh AdhiyaAshapura Housing Pvt Ltd16/02/2021
CC006000000197987Smita SHindeAshapura Housing Pvt Ltd25/08/2021
CC006000000199084Vinayak WaghmodeAshapura Housing Chs Ltd23/11/2021
CC006000000195805Ridge Henry CorreiaAshapura Housing Pvt Ltd03/02/2021
CC006000000197050Jignesh PanchalAshapura Housing Pvt Ltd22/05/2021
CC006000000197424Mr. Rajeev Chaturvedi and Mrs. Pallavi Rajeev ChaturvediAshapura Housing Pvt Ltd28/06/2021
CC006000000198833Ms. Anshuma SharmaAshapura Housing Private Limited27/10/2021
CC006000000210169Richa ShettyAshapura Housing Private Limited28/02/2022
CC006000000209915Amruta ParabAshapura Housing Private Limited05/02/2022
CC006000000209920Bhavyata Acharya & Sanket AcharyaAshapura Housing Private Limited05/02/2022
CC006000000209923Shodhan B ShettyAshapura Housing Private Limited05/02/2022
CC006000000209924Rakesh SolankiAshapura Housing Private Limited05/02/2022
CC006000000209925Balkrishna DigheAshapura Housing Private Limited05/02/2022
CC006000000209936Mini Muraleedharan NairAshapura Housing Private Limited07/02/2022
CC006000000209948Saurabh PimpaleAshapura Housing Private Limited18/02/2022
CC006000000209971Jatin ParmarAshapura Housing Private Limited09/02/2022
CC006000000209989SNEHA HIREN MERAIAshapura Housing Private Limited10/02/2022
CC006000000210202Mahesh ChetiwalAshapura Housing Private Limited01/03/2022
CC006000000210287Mangesh ElagAsha Pura Housing Private Limited07/03/2022
CC006000000210303Davesh PorwalAsha Pura Housing Private Limited25/03/2022
CC006000000210355Kavil NairAshapura Housing Private Limited10/03/2022
CC006000000220928Santosh Shantaram SankheAshapura Housing Private Limited28/04/2022
CC006000000251508Vency Ambrose FigerA&O Eminente (Abhishek Patel)18/06/2022
CC006000000251573NILESH HEMANRT DHARGALKARMr Nishit Patel23/06/2022
CC006000000262034Priyangini Bal PatilAshapura Housing pvt ltd25/07/2022
CC006000000292267Mohit Harishchandra KadamAshapura Housing Private Limited09/08/2022
CC006000000302930Pranit Pradip RaoraneAshapura Housing Private limited21/10/2022
CC006000000354453Vishaldeep Ramkumar AdvaniASHAPURA HOUSING PRIVATE LIMITED10/03/2023
CC006000000344219SWAPNIL HEGISHTEAshapura Housing Private Limited25/03/2023
CC006000000354403MANOHAR DHONDU GAWDEPRAVIN GIRISH CHAMARIA , CHETAN SUNDARJI BHANUSHALI, MAYA HIKMAT UDHAN, MEENA CHETAN BHANUSHALI19/02/2023
CC006000000364772Nilesh Prakash NandeASHAPURA HOUSING PRIVATE LIMITED16/04/2023
CC006000000374772Dakshata Vishram SawantA & O EMINENTE19/04/2023
CC006000000374799BIPIN DAMODAR CHURIASHAPURA HOUSING PRIVATE LIMITED22/03/2023
CC006000000375235Supriya Hemant GosaviAshapura Housing Private Limited17/04/2023
CC006000000375247Nishant Kiran GandhiASHAPURA HOUSINGPRIVATE LIMITED16/04/2023
CC006000000375290Arun Gaurishankar SharmaAshapura Housing Private Limited16/04/2023
CC006000000375284Swapnil Ulhas SawantAshapura Housing Private Limited16/04/2023
CC006000000375283swapnil laxman chowkekarAshapura Housing Private Limited17/04/2023
CC006000000375291Gurunath Gopal PatkarASHAPURA HOUSING PRIVATE LIMITED16/04/2023
CC006000000375292PRASHANT VASUDEO VAIDYAASHAPURA HOUSING PVT. LTD16/04/2023
CC006000000375296ADITYA PRASHANT VAIDYAASHAPURA HOUSING PVT. LTD16/04/2023
CC006000000395532Deepak KhanvilkarAshapura Housing Pvt Ltd04/05/2023
CC006000000395533Shalaka KhanvilkarAshapura Housing Pvt Ltd04/05/2023
CC006000000396145Varun Suresh KotianAshapura Housing PVT LTD04/07/2023
CC006000000396261Nishant Arun TrivediAshapura Housing Private Limited16/06/2023
CC006000000396264Pankaj Kishore TrivediAshapura Housing Private Limited16/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Aug 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Eminente Form 3 September 2022.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 March 2020.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 December 2021.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form June 2022.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 June 2021.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 March 2021.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 September 2021.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 March 2022.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 Dec 2018.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 June 2018.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 March 2018.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 March 2019.pdf17 Mar 2023
Certificates of CA (Form 3)File: Eminente Form 3 Sept 2018.pdf17 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Ashapura Housing 20-21.pdf16 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Ashapura Housing 21-22.pdf16 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing Dec 2020 Upload.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing March 2021 Upload.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing Dec 2021 Upload.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing March 2022 Upload.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing Sept 2022 Upload.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1) Eminente- Ashapura Housing June 2022 Upload.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ashapura Housing March 2021.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ashapura Housing June 2021.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ashapura Housing September 2021.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ashapura Housing March 2022.pdf27 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ashapura Housing September 2022.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Ashapura Housing Form 1 30-09-2017.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Ashapura Housing Form 1 31-12-2017 upload.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Ashapura Housing Form 1 31-03-2018 upload.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Ashapura Houshing Form 1 30-09-2018 Upload.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Ashapura Houshing Form 1 31-12-2018 upload.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8 Ashapura Houshing Form 1 30-03-2019 Upload.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9 Ashapura Housing Form 1 26-06-2019 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Ashapura Housing Form2 30-09-2017 2.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Ashapura Housing Form 2 31-12-2017 2.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Ashapura Housing Form2 18-05-2018 2.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Ashpura housing Form2 19-10-2018 2 R.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 Ashpura housing Form2 19-02-2019 2 R.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 Ashpura housing Form2 29-04-2019 for 31-03-2019.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18 Ashapura Houshing Form 2 08-07-2019 June 2019 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19 Ashapura Housing Form 2 18-10-2019 Sept 2019 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20 Ashapura Housing Form 2 15-01-2020 Dec 2019 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 22 Ashapura Housing Form 2 Dated 30-06-2020 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 23 Ashapura Housing Form 2 Dated 30-09-2020 Upload.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 24 Ashapura Housing Form 2 Dated 31-12-2020 Upload.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Declaration Form 2 A Ashapura Housing 2020 2021.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Declaration - Eminente- Form 2A.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Declaration - Eminente- Form 2A.pdf1 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration-Eminente- Society Formation.pdf1 Jul 2021
Declaration about Commencement CertificateFile: For Upload- Discosure- Eminente- CC.pdf30 Jun 2021
Disclosure of sold/ booked inventoryFile: For upload Eminente- Sold - Unsold - Upload- 23rd June, 2021.pdf30 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: For Upload- Form 5- Eminente- March 2020_compressed.pdf30 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Ashapura Housing Form 5 FY 2018 2019 to upload.pdf20 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ashapura Housing Form 5 FY 2018 2019 to upload.pdf20 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Upload Further CC 23062020.pdf26 Jun 2020
Building plan approvalFile: Amended IOA Sale Bldg dt 14082019 Eminente.pdf28 Aug 2019
Building Plan Approval (IOD)File: Amended IOA Sale Bldg dt 14082019 Eminente.pdf28 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: further CC 14122018.pdf6 Dec 2018
Certificates of CA (Form 5)File: form 5 Eminente for uploading.pdf29 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: CC Emi 14122017.pdf19 Dec 2017
Details of encumbrancesFile: Encumbrance Certificate A and O eminente.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Sale Bldg.pdf31 Jul 2017
Proforma of Allotment letterFile: AFS 31072017 7 A and O Eminente.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form3.pdf30 Jul 2017
OtherFile: Eminente Disclosures.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Binder.pdf28 Jul 2017
Building plan approvalFile: IOA eminente.pdf27 Jul 2017
Layout approvalFile: Layout Plan eminente.pdf27 Jul 2017
PAN CardFile: Ashapura Housing Pan card0001.pdf27 Jul 2017
Copy of the legal title reportFile: TITLE CERTI EMINENTE.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan eminente.pdf27 Jul 2017
Building Plan Approval (IOD)File: IOA eminente.pdf27 Jul 2017
Declaration in FORM BFile: Affidavit Ashapura Housing Pvt Ltd.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate eminente.pdf27 Jul 2017
OtherFile: Certificate of Stabililty Eminente.pdf27 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep A and O EMINENTE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmA and O EMINENTECompleted 112Lapsed / revoked 76Other 177Dot size: filed unitsN

Filed coordinates, straight-line distance. 365 registered projects within 2 km.

Builder: ASHAPURA HOUSING PRIVATE LIMITED

ASHAPURA HOUSING PRIVATE LIMITED has 1 registration on MahaRERA, including A and O EMINENTE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if A and O EMINENTE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of A and O EMINENTE?

The registered promoter entity is ASHAPURA HOUSING PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in A and O EMINENTE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against A and O EMINENTE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for A and O EMINENTE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at A and O EMINENTE?

The professionals named in the filing: Architect: RAJENDRA ULHAS PAGNIS; Engineer: GIREESH M RAJADHYAKSHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in A and O EMINENTE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About A and O EMINENTE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save A and O EMINENTE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.